D_Schedule of Material Submittals - Copy.xlsx
XLSX spreadsheet 24 KB Posted
- Attached to
- ATFP Construct West Gate ID Check Area Federal contract opportunity
- Solicitation number
- MXDP143001
About this file
This document is a schedule of material submittals for the ATFP Construct West Gate ID Check Area solicitation issued by the Department of the Air Force Air Education and Training Command. The solicitation seeks a firm-fixed price contract to demolish existing facilities at the west gate entrance of Laughlin Air Force Base and construct a new road, gatehouse, ID check area, and canopy along with associated utilities. The schedule outlines 55 required submittals for items such as construction plans, quality control documentation, site safety plans, progress reports, materials lists, shop drawings, operation and maintenance manuals, and as-built drawings. Submittals are due no later than 30 to 60 days after notice to proceed with the exception of bi-weekly progress reports and meeting minutes. The solicitation is set aside for women-owned small businesses with a NAICS code of 236220 and size standard of $39.5 million. The government anticipates award of a firm-fixed price contract as a result of this opportunity.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # MXDP 14-3001 PROJECT TITLE ATFP Construct West Gate ID Check Area SOLICITATION / CONTRACT NO.
| (To be completed by Project Engineer) | (To be completed by Contract Administrator) | |||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | LAUGHLIN DIV 01 SPECS REFERENCE | NUMBER OF PAPER COPIES REQUIRED. DIGITAL COPIES ARE REQUIRED FOR ALL SUBMITTALS | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS |
| SAMPLES | PRODUCT DATA | TEST REPORTS | CERTIFICATIONS | FIELD REPORTS | |
| 10.4.6 | 10.4.5 | 10.4.8 | 10.4.9 | 10.4.11 | APPR |
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
DIS
fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
| Pre-Construction Submittals | ||||||||||
| 1 | Construction Site Plan | 13.1 | NLT 30 Days after NTP 1 | |||||||
| 2 | AF From 103 | 2.2 | NLT 7 Days after NTP 1 | |||||||
| 3 | Vehicle List | 1-10.2 | NLT 30 Days after NTP 1 | |||||||
| 4 | Project Schedule | 6.1.2 | NLT 7 Days after NTP 1 | |||||||
| 5 | Contractor Health and Safety Plan | 3.2.2 | NLT 30 Days after NTP 1 | |||||||
| 6 | Environmental Survey & Protection Plan | 7-4 | NLT 30 Days after NTP 1 | |||||||
| 7 | QC Plan | 4.3.1 | NLT 30 Days after NTP 1 | |||||||
| 8 | QC Manager Qualifications & Key Personnel Resumes | 4.2.4 | NLT 30 Days after NTP 1 | |||||||
| 9 | Safety Data Sheets | 10.4.6 | NLT 30 Days after NTP 1 | |||||||
| 10 | Records of Existing Conditions | sect 7 | NLT 30 Days after NTP 1 | |||||||
| 11 | Shop Drawings | 10.4.4 | 2 | NLT 30 Days after NTP 1 | ||||||
| 12 | Phase Plan | 1-12 | NLT 30 Days after NTP 1 | |||||||
| 13 | Traffic Control Plan | 13.2 | NLT 30 Days after NTP 1 | |||||||
| 14 | OPSEC Training Approval | sect 2.2 | NLT 30 Days after NTP 1 | |||||||
| Construction Submittals | ||||||||||
| 15 | Progress Report | 6.1.3 | Bi-Weekly | |||||||
| 16 | Meeting Minutes | 6.2.1 | NLT 3 Days after meeting | |||||||
| Materials | ||||||||||
| 17 | Concrete | 1 | 1 | 1 | 1 | NLT 60 Days after NTP 1 | ||||
| 18 | Cold-Form metal framing | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 19 | Mineral Fiber Blanket Insulation | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 20 | Insulated Metal Roof Panel | 1 | 1 | 1 | NLT 60 Days after NTP 1 | Both flat and curved versions for the gatehouse and canopy respectively | ||||
| 21 | Metal Roof Panels & Trims | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 22 | Flashing and Sheet Metal | 1 | NLT 60 Days after NTP 1 | |||||||
| 23 | Bullet Resistant Components | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 24 | Door Hardwares | 1 | 1 | NLT 60 Days after NTP 1 | ||||||
| 25 | Security Glazing | 1 | 1 | NLT 60 Days after NTP 1 | ||||||
| 26 | Metal Louvers | 1 | 1 | NLT 60 Days after NTP 1 | ||||||
| 27 | Cement Stucco, lath & accessories | 1 | 1 | NLT 60 Days after NTP 1 | ||||||
| 28 | Gypsum Board | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 29 | Ceramic Tiles | 1 | 1 | 1 | 1 | NLT 60 Days after NTP 1 | ||||
| 30 | Acoustic Ceiling | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 31 | Resilient Flooring | 1 | 1 | 1 | 1 | NLT 60 Days after NTP 1 | ||||
| 32 | Paints and Coatings | 1 | 1 | 1 | 1 | NLT 60 Days after NTP 1 | Submit to HazMat for approval. | |||
| 33 | Exterior & Interior Signage | 1 | NLT 60 Days after NTP 1 | |||||||
| 34 | Toilet Accessories | 1 | 1 | NLT 60 Days after NTP 1 | ||||||
| 35 | Fire Extinguisher | 1 | 1 | NLT 60 Days after NTP 1 | ||||||
| 36 | Window Blinds | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 37 | Plumbing Fixtures & Faucets | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 38 | Pneumatic Sewage Ejector | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 39 | Hvac Vibration and Seismic Controls | 1 | NLT 60 Days after NTP 1 | |||||||
| 40 | Bacnet DDC | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 41 | Hvac Power Ventilator | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 42 | Diffusers, Register & Grilles | 1 | NLT 60 Days after NTP 1 | |||||||
| 43 | Air Conditioning Equipment | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 44 | Fan Coil Unit | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 45 | Exterior & Interior Light Fixtures | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 46 | Sealants | 1 | NLT 60 Days after NTP 1 | Submit to HazMat for approval | ||||||
| 47 | Storm Drainage | 1 | NLT 60 Days after NTP 1 | |||||||
| 48 | Lightning Protection | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 49 | Communications | 1 | 1 | 1 | NLT 60 Days after NTP 1 | |||||
| 50 | Electrical Components | 1 | 1 | 1 | NLT 60 Days after NTP 1 |
| Close-Out | ||||
| 50 | Quality Control Manager Punchlist | 14.5 | 1 | By Pre-Final Inspection |
| 51 | O&M Manuals | 10.4 | 1 | NLT 2 weeks after Final Inspection |
| 52 | Draft DD Form 1354 | 14.4 | 1 | Prior to Pre-Final Inspection |
| 53 | Final DD Form 1354 | 14.4 | 1 | At the Final Inspection |
| 54 | As Built Drawings | 14.2 | 1 | NLT 2 weeks after Final Inspection |
| 55 | Warranty | 14.3 | NLT 2 weeks after Final Inspection | |
| Schedule of Submittals Template, Feb 05 (SAF/AQCP) |
Task Order # FA3099-16-D-0002-0002 SOW Atch 2
&"Times New Roman,Regular"&12Page &P of &N
File details come from the government source that posted it. Updated .