D-398 OVHL TIME LINE.xls

XLS spreadsheet 43 KB Posted

Attached to
52000QR250020289 USCGC BEAR SHIPS SERVICE DIESEL GENERATOR OVERHAUL KIT AND LINE BORE INSPECTION
Solicitation number
52000QR250020289
Issued by

About this file

The file D-398 OVHL TIME LINE.xls is a project timeline for a Caterpillar D-398 ship service diesel generator overhaul for the USCGC BEAR. The timeline spans 42 days, detailing sequential work phases including test run, tag out and drain fluids, electrical and mechanical separation, tear down, parts cleaning, line bore inspection, rebuild, fluid refill, generator attachment, and comprehensive testing.

The associated federal contract opportunity (Solicitation Number 52000QR250020289) is a small business set-aside solicitation issued by the US Coast Guard Surface Force Logistics Center for a Caterpillar D-398 engine overhaul kit and line bore inspection. Key requirements include delivering a complete OEM component kit to Portsmouth, VA during the week of 11 May 2026, conducting a crankshaft line bore inspection on 16-17 June 2026, and returning core parts approximately 75 days after kit delivery. Quotes are due by 04 August 2025 at 9 AM EST, with award anticipated on a firm-fixed price basis to the most advantageous and best-value responsible contractor. Only Caterpillar Authorized Parts & Service Center products are acceptable, and vendors must provide a Letter of Authorization from the original equipment manufacturer.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

MONDAYTUESDAYWEDNESDAYTHURSDAYFRIDAYSATURDAYSUNDAY
Day-1Day-2Day-3Day-4Day-5Day-6Day-7
TEST RUN #1 SSDG TAG OUT & DRAIN FLUIDSEM'S UNWIRE & SEPARATEEM'S SEPARATESTART TEAR DOWNTEAR DOWN
Day-8Day-9Day-10Day-11Day-12Day-13Day-14
TEAR DOWNTEAR DOWNTEAR DOWNTEAR DOWNCRANE SERVICE (On & Off load parts)
Day-15Day-16Day-17Day-18Day-19Day-20Day-21
BLOCK & PARTS CLEANINGLINE BORE/PARTS CLEANINGLINE BORE/PARTS CLEANINGSTART REBUILDREBUILD
Day-22Day-23Day-24Day-25Day-26Day-27Day-28
REBUILDREBUILDREBUILDREBUILDREBUILD
Day-29Day-30Day-31Day-32Day-33Day-34Day-35
REBUILDREBUILDREBUILDREBUILDREBUILD
Day-36Day-37Day-38Day-39Day-40Day-41Day-42
REFILL ALL FLUIDS & TURN ON HEATERSEM'S ATTACH GENEM'S ATTACH GENTEST RUN Unloaded 2-4 hr then loadTEST RUN loaded for total of 24 hrs

&CD-398

SSDG OVERHAUL