D-398 OVHL TIME LINE.xls
XLS spreadsheet 43 KB Posted
- Attached to
- 52000QR250020289 USCGC BEAR SHIPS SERVICE DIESEL GENERATOR OVERHAUL KIT AND LINE BORE INSPECTION
- Solicitation number
- 52000QR250020289
About this file
The file D-398 OVHL TIME LINE.xls is a project timeline for a Caterpillar D-398 ship service diesel generator overhaul for the USCGC BEAR. The timeline spans 42 days, detailing sequential work phases including test run, tag out and drain fluids, electrical and mechanical separation, tear down, parts cleaning, line bore inspection, rebuild, fluid refill, generator attachment, and comprehensive testing.
The associated federal contract opportunity (Solicitation Number 52000QR250020289) is a small business set-aside solicitation issued by the US Coast Guard Surface Force Logistics Center for a Caterpillar D-398 engine overhaul kit and line bore inspection. Key requirements include delivering a complete OEM component kit to Portsmouth, VA during the week of 11 May 2026, conducting a crankshaft line bore inspection on 16-17 June 2026, and returning core parts approximately 75 days after kit delivery. Quotes are due by 04 August 2025 at 9 AM EST, with award anticipated on a firm-fixed price basis to the most advantageous and best-value responsible contractor. Only Caterpillar Authorized Parts & Service Center products are acceptable, and vendors must provide a Letter of Authorization from the original equipment manufacturer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| JOTFOC CGC Bear SSDG Overhaul Kit and Line Bore-Redacted.pdf | ||
| JOTFOC CGC Bear SSDG Overhaul Kit and Line Bore.pdf | ||
| SOW for Caterpillar D-398 Line Bore Inspection and D-398 Overhaul Kit.docx | DOCX document | |
| Smart Matrix SAP CM FFP.pdf | ||
| 270 WMEC D398 CAT OVHL KIT.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| MONDAY | TUESDAY | WEDNESDAY | THURSDAY | FRIDAY | SATURDAY | SUNDAY |
| Day-1 | Day-2 | Day-3 | Day-4 | Day-5 | Day-6 | Day-7 |
| TEST RUN #1 SSDG TAG OUT & DRAIN FLUIDS | EM'S UNWIRE & SEPARATE | EM'S SEPARATE | START TEAR DOWN | TEAR DOWN | ||
| Day-8 | Day-9 | Day-10 | Day-11 | Day-12 | Day-13 | Day-14 |
| TEAR DOWN | TEAR DOWN | TEAR DOWN | TEAR DOWN | CRANE SERVICE (On & Off load parts) | ||
| Day-15 | Day-16 | Day-17 | Day-18 | Day-19 | Day-20 | Day-21 |
| BLOCK & PARTS CLEANING | LINE BORE/PARTS CLEANING | LINE BORE/PARTS CLEANING | START REBUILD | REBUILD | ||
| Day-22 | Day-23 | Day-24 | Day-25 | Day-26 | Day-27 | Day-28 |
| REBUILD | REBUILD | REBUILD | REBUILD | REBUILD | ||
| Day-29 | Day-30 | Day-31 | Day-32 | Day-33 | Day-34 | Day-35 |
| REBUILD | REBUILD | REBUILD | REBUILD | REBUILD | ||
| Day-36 | Day-37 | Day-38 | Day-39 | Day-40 | Day-41 | Day-42 |
| REFILL ALL FLUIDS & TURN ON HEATERS | EM'S ATTACH GEN | EM'S ATTACH GEN | TEST RUN Unloaded 2-4 hr then load | TEST RUN loaded for total of 24 hrs |
&CD-398
SSDG OVERHAUL
Sheet2
Sheet3