This is an Engineer's Estimate document for the Cripple Creek Stream Improvement and Riparian Area Reclamation (SCIIP) project, a stream restoration initiative by Greenville County, South Carolina. The 800-foot stream restoration project addresses erosion mitigation within the Reedy River watershed through comprehensive ecological and structural improvements. Key work items include clearing and grubbing (1.5 acres), excavation and grading (3,750 cubic yards total), installation of instream features such as cross vanes (2 each), single arm vanes (2 each), boulder riffles (4 each), and various bank toe treatments totaling 1,500 linear feet. Additional components encompass turf reinforcement matting installation (4,300 square yards), seeding and vegetation establishment (1.5 acres), live stakes (80 bundles), and plugs/bare root stems (400 each). The project includes mandatory pre-bid site visits and meetings scheduled for July 11, 2025, with bid submissions due August 1, 2025, at 3:15 pm. The anticipated contract award date is September 8, 2025, with a 90-calendar day completion timeline and potential liquidated damages of $250 per day for late completion.
The engineer's estimate totals $706,259.40, including mobilization ($61,148), erosion and sediment control ($28,400), as-builts ($7,500), and a 5% contingency ($33,631.40). Evaluation criteria heavily emphasize cost at 99% of scoring, with only 1% allocated to responsiveness. Bidders must provide a 5% bid bond and maintain performance and payment bonds, along with comprehensive insurance coverage including $1,000,000 in general liability and automobile liability. The project offers significant cost-saving opportunities, including free boulder materials from the Twin Chimneys Landfill stockpile and no tipping fees for spoil material disposal. Contractors must demonstrate experience with similar stream restoration projects and provide references. Federal and state regulations apply, including compliance with the Illegal Immigration Reform Act, though no specific set-aside designations for disadvantaged enterprises are explicitly indicated.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITEM # DESCRIPTION QTY UNIT UNIT PRICE TOTAL PRICE
1 MOBILIZATION - LS - 61,148.00$
2 AS-BUILTS - LS - 7,500.00$
3 EROSION AND SEDIMENT CONTROL - LS - 28,400.00$
4 CLEARING AND GRUBBING 1.5 AC 4,000.00$ 6,000.00$
5 BEDDING STONE 70 CY 100.00$ 7,000.00$
6 RIPRAP, BOULDERS AND AGGREGATE 30 CY 150.00$ 4,500.00$
EXCAVATION, FILLING, AND GRADING:
CUT AND FILL IN PLACE
680 CY 50.00$ 34,000.00$
EXCAVATION, FILLING, AND GRADING:
CUT AND REMOVE OFFSITE
3,070 CY 50.00$ 153,500.00$
9 CROSS VANE 2 EA 9,800.00$ 19,600.00$
10 SINGLE ARM VANE 2 EA 3,500.00$ 7,000.00$
11 BOULDER RIFFLE 4 EA 3,300.00$ 13,200.00$
12 BOULDER TOE 800 LF 240.00$ 192,000.00$
13 ROCK TOE 700 LF 80.00$ 56,000.00$
14 COIR TURF REINFORCEMENT MATTING (700G) 2,700 SY 5.44$ 14,688.00$
15 COIR TURF REINFORCEMENT MATTING (320G) 500 SY 5.40$ 2,700.00$
16 PERMANENT TRM 1,100 SY 38.00$ 41,800.00$
SEEDING, MULCHING AND VEGETATION
ESTABLISHMENT
1.5 AC 5,000.00$ 7,500.00$
18 LIVE STAKES 80 BN 175.00$ 14,000.00$
19 PLUGS/BARE ROOT STEMS 400 EA 5.23$ 2,092.00$
20 CONTINGENCY 5 % - 33,631.40$
706,259.40$
CRIPPLE CREEK STREAM RESTORATION AND RIPRARIAN RECLAMATION: PHASE 1
ENGINEER'S ESTIMATE
MAY 2025
TOTAL