CrippleCreek_EngineersEst.pdf

PDF 411 KB Posted

Attached to
Cripple Creek - Stream Improvement and Riparian Area Reclamation (SCIIP)
Solicitation number
IFB #26002
Issued by
Greenville County, South Carolina

About this file

This document is an Engineer's Estimate for the Cripple Creek Stream Restoration and Riparian Reclamation: Phase 1 project, dated May 2025, for a stream improvement initiative in South Carolina. The project encompasses multiple restoration activities including mobilization, erosion and sediment control, clearing and grubbing 1.5 acres, bedding stone placement, riprap and boulder installation, excavation and grading (both in-place and offsite removal), and various stream restoration techniques such as cross vanes, single arm vanes, boulder riffles, and boulder toe treatments. The estimate includes quantities for rock toe installation, coir turf reinforcement matting, permanent turf reinforcement, seeding, mulching, vegetation establishment, live stakes, and plug/bare root stem plantings.

The total estimated project cost is $706,259.40, which includes a 5% contingency of $33,631.40. The pricing is broken down by line item with specific unit prices and total costs, ranging from $2,092.00 for plugs/bare root stems to $192,000.00 for boulder toe installation. The estimate covers 800 linear feet of stream improvement, involving extensive earthwork, erosion control, and ecological restoration techniques designed to stabilize stream banks, reduce erosive energy, and establish riparian vegetation. The project appears to be part of a broader watershed restoration effort in the Reedy River watershed, focusing on creating more sustainable and ecologically sound stream corridor environments.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM # DESCRIPTION QTY UNIT UNIT PRICE TOTAL PRICE

1 MOBILIZATION - LS - 61,148.00$

2 AS-BUILTS - LS - 7,500.00$

3 EROSION AND SEDIMENT CONTROL - LS - 28,400.00$

4 CLEARING AND GRUBBING 1.5 AC 4,000.00$ 6,000.00$

5 BEDDING STONE 70 CY 100.00$ 7,000.00$

6 RIPRAP, BOULDERS AND AGGREGATE 30 CY 150.00$ 4,500.00$

EXCAVATION, FILLING, AND GRADING:

CUT AND FILL IN PLACE

680 CY 50.00$ 34,000.00$

EXCAVATION, FILLING, AND GRADING:

CUT AND REMOVE OFFSITE

3,070 CY 50.00$ 153,500.00$

9 CROSS VANE 2 EA 9,800.00$ 19,600.00$

10 SINGLE ARM VANE 2 EA 3,500.00$ 7,000.00$

11 BOULDER RIFFLE 4 EA 3,300.00$ 13,200.00$

12 BOULDER TOE 800 LF 240.00$ 192,000.00$

13 ROCK TOE 700 LF 80.00$ 56,000.00$

14 COIR TURF REINFORCEMENT MATTING (700G) 2,700 SY 5.44$ 14,688.00$

15 COIR TURF REINFORCEMENT MATTING (320G) 500 SY 5.40$ 2,700.00$

16 PERMANENT TRM 1,100 SY 38.00$ 41,800.00$

SEEDING, MULCHING AND VEGETATION

ESTABLISHMENT

1.5 AC 5,000.00$ 7,500.00$

18 LIVE STAKES 80 BN 175.00$ 14,000.00$

19 PLUGS/BARE ROOT STEMS 400 EA 5.23$ 2,092.00$

20 CONTINGENCY 5 % - 33,631.40$

706,259.40$

CRIPPLE CREEK STREAM RESTORATION AND RIPRARIAN RECLAMATION: PHASE 1

ENGINEER'S ESTIMATE

MAY 2025

TOTAL

File details come from the government source that posted it. Updated .