CrippleCreek_BidSheet.pdf
PDF 402 KB Posted
- Solicitation number
- IFB #26002
- Issued by
- Greenville County, South Carolina
About this file
This is a bid sheet for the Cripple Creek Stream Improvement and Riparian Area Reclamation (SCIIP) project issued by Greenville County, South Carolina. The project encompasses an 800-foot stream restoration initiative within the Reedy River watershed involving twenty line items with varying quantities and unit measurements. Key deliverables include mobilization, erosion and sediment control, clearing and grubbing (1.5 acres), excavation and grading operations (680 cubic yards cut and fill in place; 3,070 cubic yards cut and remove offsite), installation of instream features (2 cross vanes, 2 single arm vanes, 4 boulder riffles), bank toe treatments (800 linear feet boulder toe, 700 linear feet rock toe), turf reinforcement matting (2,700 square yards at 700G, 500 square yards at 320G, 1,100 square yards permanent), vegetation establishment (1.5 acres), live stakes (80 bundles), and plugs/bare root stems (400 each). The non-mandatory pre-bid meeting and site visit occurred on July 11, 2025, with bid submissions due August 1, 2025, at 3:15 pm and a tentative contract award date of September 8, 2025. The contract includes a 90-calendar day completion timeline with potential liquidated damages of $250 per day for late completion.
The engineer's estimate for the total project is $706,259.40, including a 5% contingency of $33,631.40. Evaluation criteria heavily emphasize cost at 99% of the scoring with only 1% allocated to responsiveness. Contractors are required to provide a 5% bid bond, performance and payment bonds, and maintain comprehensive insurance coverage including $1,000,000 in general liability and automobile liability. The project offers significant cost-saving opportunities with free boulder materials available from the Twin Chimneys Landfill stockpile (11075 Augusta Road, Honea Path, South Carolina 29654) and no tipping fees for spoil material disposal at the same location. All construction must be performed in accordance with project plans, with GPS preferred as the survey method. Contractors must demonstrate experience with similar stream restoration projects and provide references. Compliance with federal and state regulations, including the Illegal Immigration Reform Act, is required.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITEM # DESCRIPTION QTY UNIT UNIT PRICE TOTAL PRICE
1 MOBILIZATION - LS -
2 AS-BUILTS - LS -
3 EROSION AND SEDIMENT CONTROL - LS -
4 CLEARING AND GRUBBING 1.5 AC
5 BEDDING STONE 70 CY
6 RIPRAP, BOULDERS AND AGGREGATE 30 CY
EXCAVATION, FILLING, AND GRADING:
CUT AND FILL IN PLACE
680 CY
EXCAVATION, FILLING, AND GRADING:
CUT AND REMOVE OFFSITE
3,070 CY
9 CROSS VANE 2 EA
10 SINGLE ARM VANE 2 EA
11 BOULDER RIFFLE 4 EA
12 BOULDER TOE 800 LF
13 ROCK TOE 700 LF
14 COIR TURF REINFORCEMENT MATTING (700G) 2,700 SY
15 COIR TURF REINFORCEMENT MATTING (320G) 500 SY
16 PERMANENT TRM 1,100 SY
SEEDING, MULCHING AND VEGETATION
ESTABLISHMENT
1.5 AC
18 LIVE STAKES 80 BN
19 PLUGS/BARE ROOT STEMS 400 EA
20 CONTINGENCY 5 % -
CRIPPLE CREEK STREAM RESTORATION AND RIPRARIAN RECLAMATION: PHASE 1
BID SHEET
MAY 2025
TOTAL
NOTE: IT IS THE CONTRACTOR'S RESPONSIBILITY TO CONSTRUCT IN ACCORDANCE WITH THE PLANS.
GPS IS THE PREFERRED METHOD, BUT OTHER METHODS MAY BE ACCEPTED.
NOTE: ALL SPOIL MATERIAL MUST BE TAKEN TO TWIN CHIMNEY'S LANDFILL (11075 AUGUSTA RD., HONEA PATH, SC 29654). THERE WILL BE NO TIPPING FEE.
NOTE: BOULDERS ARE AVAILABLE AT NO COST WHEN USED ON THIS PROJECT, LOCATED AT TWIN
CHIMNEYS LANDFILL (11075 AUGUSTA RD., HONEA PATH, SC 29654). SEE ATTACHMENT FOR
ADDITIONAL INFORMATION.