This is a pricing sheet for crane and hoist inspection, repair, and maintenance services submitted by contractors to the Washington Suburban Sanitary Commission (WSSC) in Maryland. The WSSC is soliciting sealed responses for annual inspections and recommended preventive maintenance on approximately 206 overhead cranes and hoists located at various facilities throughout Montgomery and Prince George's Counties, Maryland. The contract requires contractors to perform thorough annual inspections of hoisting machinery, provide lubrication to all components, perform emergency repair services on a time and material basis, and potentially change oil and conduct full-rated operational load tests on specified equipment. Services are required at multiple facility locations including water treatment plants, wastewater pumping stations, water resource recovery facilities, and maintenance depots. Sealed responses were due by 2:00 pm on Thursday, May 21, 2026, via the WSSC eProcurement Portal. The pricing sheet lists all 206 cranes and hoists by facility location, crane identification number, manufacturer, and capacity, organized by sections for base term annual inspections, optional renewal terms, and load testing requirements.
The pricing sheet is formatted to capture contractor pricing for Section A (annual inspection and preventive maintenance costs), Section B (load test costs), and Section C (additional work labor classifications including crane service technician, crane helper, and engineer/non-destructive testing hours). Contractors must provide all supervision, labor, service trucks, materials including oil and grease, tools, and equipment necessary for contract performance. The pricing page includes payment discount options of one percent for payment within twenty days or two percent for payment within fifteen days, with net payment due in thirty days. The spreadsheet reflects that all pricing entries currently show $0.00, indicating this is a blank template awaiting contractor bid submissions. The contract includes multiple renewal option terms with associated inspection and maintenance cost requirements for each term period.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
Type Crane ID# Location Manufacturer Capacity BASE TERM Annual Inspection SECTION A 1st OPTION TERM Annual Inspection SECTION A 2ND OPTION TERM Annual Inspection SECTION A 3RD OPTION TERM Annual Inspection SECTION A 4TH OPTION TERM Annual Inspection SECTION A Load Test SECTION B Required Quadrennial
| D E | AN-01 HSE2501216920 | Facilities Maint. Bldg. | ||||||||||
| (Welding Shop) AND1B08D109001, HOIST, WELDING SHOP, TAG AN-01, ANACOSTIA DEPOT | Wright | 5 Ton | ||||||||||
| D E | ANO2 HSE2501135382 | Facilities Maint. Bldg. | ||||||||||
| (E/M Shop) AND1B08D109003, HOIST, E/M SHOP, TAG AN-02, ANACOSTIA DEPOT | Wright | 5 Ton | ||||||||||
| M E | AN-12 HSE2501219357 | Facilities Maint. Bldg. Carpentry Shop AND1B08D109002, HOIST, CARPENTRY SHOP, TAG AN-12, ANACOSTIA DEPOT | C/M Load Star | 1/2 Ton | ||||||||
| DE | AN05 HSE2501212703 | Hydrant Repair Shop AND1B06D109001, HOIST 1, HYDRANT REPAIR SHOP, TAG AN-05, ANACOSTIA DEPOT | Wright | 1 Ton | ||||||||
| D E | AN06 HSE2501138758 | Hydrant Repair Shop AND1B06D109002, HOIST 2, HYDRANT REPAIR SHOP, TAG AN-06, ANACOSTIA DEPOT | Wright | 1 Ton | ||||||||
| D E | AN07 HSE2501137587 | Meter Repair Shop AND1B06D109004, HOIST 4, METER REPAIR SHOP, TAG AN-07, ANACOSTIA DEPOT | Wright | 1/2 Ton | ||||||||
| M E | ANO8 HSE2501130232 | Meter Repair Shop AND1B06D109003, HOIST 3, METER REPAIR SHOP, TAG AN-08, ANACOSTIA DEPOT | Wright | 1 Ton | ||||||||
| D E | AN03 HSE2501216585 | Mobile Equip Shop (North Side) AND1B11D109001, HOIST 1, MOBILE EQUIPMENT SHOP NORTH, TAG AN-03, ANACOSTIA DEPOT | ACCO/Wright | 5 Ton | ||||||||
| D E | AN04 HSE2501214622 | Mobile Equip Shop (South Side) AND1B11D109002, HOIST 2, MOBILE EQUIPMENT SHOP SOUTH, TAG AN-04, ANACOSTIA DEPOT | ACCO/Wright | 5 Ton | ||||||||
| M E | AN09 HSE2501210648 | Garage AND1B03D109003, HOIST, FLEET GARAGE, TAG AN-09, ANACOSTIA DEPOT | Chisholm-Moore | 2 Ton | ||||||||
| M M | AN11 HSE2510060643 | Metal Storage Shed AND1B07D109001, HOIST, STORAGE SHED, TRADE SHOP, TAG AN-11, ANACOSTIA DEPOT | 2 Ton | |||||||||
| M M | AN10 HSE2510060642 | Depot C&M Bldg. AND1B01D109001, HOIST, SERVICE CENTER BUILDING, TAG AN-10, ANACOSTIA DEPOT | Chisholm-Moore | 3 Ton | ||||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||
| $0.00 | ||||||||||||
| D E | A2-01 HSE2501136540 | MOTOR ROOM (EAST) A2SPB11D109001, HOIST, EAST MOTOR ROOM, TAG A2-01, ANACOSTIA 2 WWPS | WRIGHT | 20 TON | ||||||||
| D E | A2-02 HSE2501139932 | MOTOR ROOM (WEST) A2SPB11D109002, HOIST, WEST MOTOR ROOM, TAG A2-02, ANACOSTIA 2 WWPS | WRIGHT | 20 TON | ||||||||
| D E | A2-04 HSE2501134052 | SCREEN ROOM A2SPB11D109004, HOIST, SCREEN ROOM, TAG A2-04, ANACOSTIA 2 WWPS | WRIGHT | 10 TON | ||||||||
| M E | A2-05 HSE2501138638 | UPPER LEVEL A2SPB11D109005, HOIST, MEZZANINE, TAG A2-05, ANACOSTIA 2 WWPS | WRIGHT | 1.5 TON | ||||||||
| M E | A2-03 HSE2501133706 | ROOF A2SPB11D109003, HOIST, ROOF, TAG A2-03, ANACOSTIA 2 WWPS | WRIGHT | 1.5 TON | ||||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| D E | CA-01 HSE2501134577 | PUMP ROOM CAWPB01D109001, HOIST, PUMP ROOM, TAG CA-01, CENTRAL AVENUE WPS | LO-HED | 10 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| D M | HI-01 HSE2501131231 | PUMP ROOM HIWPB01D109001, HOIST, PUMP ROOM, TAG HI-01, HILL ROAD WPS | C&M | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| D E | HY-01 HSE2501131492 | MOTOR ROOM HYSPB01D109001, HOIST, MOTOR ROOM, TAG HY-01, HYATTSVILLE WWPS | ACCO WRIGHT | 15 TON | ||||||
| M E | HY-02 HSE2501138009 | SCREEN ROOM HYSPB01D109002, HOIST, SCREEN ROOM, TAG HY-02, HYATTSVILLE WWPS | ACCO WRIGHT | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M E | LY-01 HSE2501210474 | GARAGE LYD1B01D109001, HOIST, FLEET GARAGE, TAG LY-01, LYTTONSVILLE DEPOT | BUDGIT | 2 TON | ||||||
| JIB E | LY-02 HSE2501211695 | LYD1B06D109002, HOIST, YARD, TAG LY-02, LYTTONSVILLE DEPOT | HARRINGTON | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M E | RC-04 HSE2509021123 | TRUCK BAY RCSFB01D109004, HOIST, TRUCK BAY, TAG RC-04, ROCK CREEK STORAGE FACILITY | COFFIN | 2 TON | ||||||
| M M | RC-01 HSM2501130432 | MOTOR ROOM RCSFB01D109001, HOIST, MOTOR ROOM, TAG RC-01, ROCK CREEK STORAGE FACILITY | CHESTER | 2 TON | ||||||
| M M | RC-03 HSM2501130562 | PUMP ROOM RCSFB01D109003, HOIST 2, PUMP ROOM, TAG RC-03, ROCK CREEK STORAGE FACILITY | CHESTER | 2 TON | ||||||
| M E | RC-02 HSM2501137420 | PUMP ROOM RCSFB01D109002, HOIST 1, PUMP ROOM, TAG RC-02, ROCK CREEK STORAGE FACILITY | CHESTER | 2 TON | ||||||
| M M | RC-05 HSE2509021124 | WET WELL RCSFB01D109005, HOIST, WET WELL, TAG RC-05, ROCK CREEK STORAGE FACILITY | INGERSOL | 1/2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M M | CM-01 HSM2501138441 | GENERATOR ROOM CMSPB01D109001, HOIST, GENERATOR ROOM, TAG CM-01, COLMAR MANOR WWPS | WRIGHT | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| D E | PK-06 HSE2501131120 | E/M SHOP PKSFB09D109001, HOIST, ELECTRICAL/MECHANICAL BLDG, TAG PK-06 | ACCO | 3 TON | ||||||
| M E | PK-18 | INCINERATOR BUILDING | SHAW BOX | 4 TON | ||||||
| M E | PK-10 HSM2509021152 | DENITRIFICATION PKSFB25D109001, HOIST, FILTER BLOWERS, DENITE FILTER BLDG, TAG PK-10 | ACCO WRIGHT | 3 TON | ||||||
| M E | PK-11 HSE2501138880 | DENITRIFICATION PKSFB25D109002, HOIST, FILTER PIPE GALLERY, DENITE FILTER BUILDING, TAG PK-11 | BUDGIT | 1 TON | ||||||
| M E | PK-12 HSE2501130844 | DENITRIFICATION PKSFB25D109003, HOIST, FILTER PUMPS, DENITE FILTER BUILDING, TAG PK-12 | ACCO WRIGHT | 5 TON | ||||||
| M E | PK-09 HSE2501136488 | RAS PUMPING STATION PKSFB18D109001, HOIST, RAS PUMPING STATION, TAG PK-09 | HARRINGTON | 1 TON | ||||||
| M E | PK-03 HSE2501133809 | DEWATER TRUCK BAY PKSFB28D109001, HOIST, LOWER LEVEL, BIOSOLIDS DEWATERING BLDG, TAG PK-03 | RAM | 2 TON | ||||||
| M M | PK-04 HSE2501134855 | BIOSOLIDS PKSFB28D109002, HOIST, OVERHEAD BRIDGE CRANE 1, BIOSOLIDS DEWATERING BLDG, TAG PK-04 | RAM | 3 TON | ||||||
| M M | PK-05 HSE2501139175 | BIOSOLIDS PKSFB28D109003, HOIST, OVERHEAD BRIDGE CRANE 2, BIOSOLIDS DEWATERING BLDG, TAG PK-05 | RAM | 3 TON | ||||||
| D E | PK-16 | INCINERATOR BUILDING | DEMAG | 7.5 TON | ||||||
| M M | PK-01 HSM2501136980 | PRIMARY SLUDGE BUILDING PKSFB05D109001, HOIST, PRIMARY SLUDGE PUMPING STATION, TAG PK-01 | WRIGHT | 1/2 TON | ||||||
| D E | PK-07 HSE2501131529 | RAW SEWAGE PUMPING STATION PKSFB12D109001, HOIST, FOR PUMPS 1 & 2, INFLUENT PUMPING STATION, TAG PK-07 | ROBBINS-MYERS | 2 TON | ||||||
| D M | PK-08 HSE2501131581 | RAW SEWAGE PUMPING STATION PKSFB12D109002, HOIST, FOR PUMPS 3 & 4, INFLUENT PUMPING STATION, TAG PK-08 | WRIGHT | 3 TON | ||||||
| D E | PK-02 HSE2501133501 | STATION PKSFB01D109001, HOIST, MIXED LIQUOR RECYCLE BUILDING, TAG PK-02 | DEWAG | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M M | PH-01 HSM2501136927 | PUMP ROOM PHSPB01D109001, HOIST, MOTOR ROOM, TAG PH-01, PUMPKIN HILL WWPS | WRIGHT | 3 TON | ||||||
| M M | PH-02 HSM2501132059 | GENERATOR ROOM PHSPB01D109002, HOIST, GENERATOR ROOM, TAG PH-02, PUMPKIN HILL WWPS | WRIGHT | 6 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| D E | HO-01 HSE2501138200 | PUMP ROOM HOSPB01D109001, HOIST, CONTROL ROOM, TAG HO-01, HORSEPEN WWPS | ROBBIN-MYERS | 2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M M | BO-01 HSM2501139578 | PUMP ROOM BOWPB01D109001, HOIST, PUMP ROOM, TAG BO-01, BOWIE WPS | COFFIN | 2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M M | BE-02 HSM2501132429 | GENERATOR ROOM BESPB01D109002, HOIST, GENERATOR ROOM, TAG BE-02, BEDFORD WWPS | COFFIN | 6 TON | ||||||
| M M | BE-01 HSM2501139578 | PUMP ROOM BESPB01D109001, HOIST, MOTOR ROOM, TAG BE-01, BEDFORD WWPS | COFFIN | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M E | SL-01 HSM2501137653 | CHLORINE ROOM SLWPB01D109001, HOIST, SHOP ROOM, TAG SL-01, SOUTH LAUREL WPS | BUDGIT | 2 TON | ||||||
| D M | SL-02 | PUMP ROOM SLWPB01D109002, HOIST, PUMP ROOM, TAG SL-02, SOUTH LAUREL WPS | BUDGIT | 2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M E | PA-05 HSE2501132838 | CHEMICAL BUILDING (Basement) PAWFB01D109002, HOIST, CHEMICAL ROOM, ADMIN BLDG, TAG PA-05 | ACCO | 4 TON | ||||||
| D E | PA-04 HSE2501133946 | CHLORINE HOIST PAWFB01D109001, HOIST, CHLORINE ROOM, ADMIN BLDG, TAG PA-04 | SHAW BOX | 2 Ton | ||||||
| M E | PA-06 HSE2501136135 | LIME HOIST PAWFB01D109003, HOIST, LIME BUCKET, ADMIN BLDG, TAG PA-06 | ACCO | 4 TON | ||||||
| D E | PA-07 HSE2501138387 | PUMP BUILDING (OLD) PAWFB05D109001, HOIST, HIGH ZONE SIDE, FINISHED WATER PUMPING STATION, TAG PA-07 | LOW HEAD | 7.5 TON | ||||||
| H M | PA-10 HSM2510010220 | FILTER BUILDING (E&M SHOP) PAWFB02D109001, HOIST, FILTER BLDG E/M SHOP, TAG PA-10 | BUDGIT | 1.5 Ton | ||||||
| M M | PA-11 HSE2510010226 | FILTER BUILDING (MECHANICAL ROOM) PAWFB02D109002, HOIST, FILTER BLDG AIR SCOUR ROOM, TAG PA-11 | BUDGIT | 6 Ton | ||||||
| ME | PA-01 HSE2501130902 | PAWFB09D109001, HOIST, BCR-1 HOIST RESIDUAL CENTRIFUGE, TAG PA-01 | R&M MATE | 3 TON | ||||||
| H M | PA-12 HSM2510010221 | FILTER BUILDING (FOYER) PAWFB02D109003, HOIST, FILTER BLDG FOYER, TAG PA-12 | BUDGIT | 1.5 Ton | ||||||
| JIB M | PA-13 HSM2510010222 | FILTER BUILDING (PILOT PLANT) PAWFB02D109004, HOIST, FILTER BLDG PILOT PLANT ROOM, TAG PA-13 | BUDGIT | 1/2 Ton | ||||||
| D E | PA-08 HSE2501139289 | PUMP BUILDING (NEW) PAWFB05D109002, HOIST, MAIN ZONE SIDE, FINISHED WATER PUMPING STATION, TAG PA-08 | ROBBINS-MEYERS | 5 Ton | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M E | PA-09 HSE2501134023 | PAWFB10D109001, HOIST, PUMP ROOM PS-2, TAG PA-09, ROCKY GORGE WPS | YALE | 5 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| E | DU-01 HSE2501133284 | TAINTOR GATE #1 DULTTGH1, HOIST 1, TAINTER GATES, TAG DU-02, DUCKETT DAM | LEITELT | 15 TON | ||||||
| E | DU-02 HSE2501133965 | TAINTOR GATE #2 DULTTGH2, HOIST 2, TAINTER GATES, TAG DU-03, DUCKETT DAM | LEITELT | 15 TON | ||||||
| E | DU-03 HSE2501139345 | TAINTOR GATE #3 DULTTGH3, HOIST 3, TAINTER GATES, TAG DU-04, DUCKETT DAM | LEITELT | 15 TON | ||||||
| D E | DU-04 HSE2501130342 | INTAKE PENSTOCK SCREEN DULTCRN/IV, HOIST, INTAKE PENSTOCK SCREEN, TAG DU-01, DUCKETT DAM | MONK | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| D E | HSE2501134618 | CLWPB01D109001, HOIST, PUMP ROOM, TAG CO-01, COLESVILLE WPS | DRESSER | 2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| D E | HSE2501137815 | NOWPB01D109001, HOIST, PUMP ROOM, TAG NO-01, NORBECK WPS | DRESSER | 2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| D E | PK04 | PUMP ROOM | DRESSER | 2 TON | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| DE | HSM2501139063 | OLSPB01D109002, HOIST, OVER GRINDERS, TAG OL-02, OLNEY WWPS | ROBBIN-MEYERS | 3 TON | ||||||
| D E | HSE2501133956 | OLSPB01D109001, HOIST, PUMP ROOM, TAG OL-01, OLNEY WWPS | ROBBIN-MEYERS | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| D M | HSE2501135688 | RBSPB01D109001, HOIST, ABOVE PUMPS, TAG RB-01, REDDY BRANCH WWPS | C&M | 2 TON | ||||||
| D M | HSM2501130838 | RBSPB01D109002, HOIST, ABOVE GRINDER, TAG RB-02, REDDY BRANCH WWPS | C&M | 2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M E | HSE2501134288 | BHLTB08D109001, HOIST, BASE OF DAM, TAG BH-05, BRIGHTON DAM | YALE | 2 TON | ||||||
| E | HSU2501132809 | BHLTTGH1, HOIST, TAINTER GATE MULE HOIST 1, TAG BH-01, BRIGHTON DAM | YALE | 15 TON | ||||||
| E | HSU2501131255 | BHLTTGH2, HOIST, TAINTER GATE MULE HOIST 2, TAG BH-02, BRIGHTON DAM | YALE | 15 TON | ||||||
| E | HSU2501138188 | BHLTTGH3, HOIST, TAINTER GATE MULE HOIST 3, TAG BH-03, BRIGHTON DAM | YALE | 15 TON | ||||||
| E | HSU2501137600 | BHLTTGH4, HOIST, TAINTER GATE MULE HOIST 4, TAG BH-04, BRIGHTON DAM | YALE | 15 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M M | HSM2510030816 | CLF1B01D109001, HOIST, MECHANICAL ROOM, TAG CL-01, CONSOLIDATED LAB | 1 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| DE | HSE2501134089 | MLSPB01D109001, HOIST, PUMP ROOM, TAG ML-01, MILL BRANCH WWPS | ACCO-WRIGHT | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M M | HSE2501139012 | GBSPB01D109001, HOIST, CONTROL ROOM, TAG GB-01, GREEN BRANCH WWPS | R&M MATE | 1 1/2 TON | ||||||
| M E | HSM2501134527 | GBSPB01D109002, HOIST, JIB, MID LEVEL, TAG GB-02, GREEN BRANCH WWPS | ROBBINS-MYERS | 1 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
| D E | WB07 HSE2501139066 | E/M SHOPWBSFB36D109001, HOIST, E/M BUILDING, TAG WB-07 | DETROIT | 3 TON | ||||||
| D E | WB03 HSE2501133446 | BACK WASH BUILDINGWBSFB16D109001, HOIST, BACKWASH PUMPING STATION, TAG WB-03 | ROBBINS MYERS | 6 TON | ||||||
| D E | WB02 HSE2501134326 | BLOWER BUILDING #2WBSFB11D109001, HOIST, BLOWER BUILDING 2, TAG WB-02 | DETROIT | 10 TON | ||||||
| M E | WB10 HSE2501135136 | POLISHING FILTER BUILDINGWBSFB13D109001, HOIST, FILTER BUILDING, TAG WB-10 | SHEPARDS-NILES | 2 TON | ||||||
| D M | WB15 HSE2501130299 | RAW SEWAGE PUMPING STATION WBSFB26D109001, HOIST, RAW SEWAGE PUMPING STATION, TAG WB-15 | DETROIT | 10 TON | ||||||
| M E | WB09 HSE2501134467 | E/M OIL STORAGE WBSFB33D109001, HOIST, OIL BUILDING, TAG WB-09 | ELECTRO-LIFT | 2 TON | ||||||
| M E | WB20 HSE2501132918 | SOLIDS BUILDING WBSFB23D109005, HOIST, INCINERATOR ROOM, SOLIDS BUILDING, TAG WB-20 | SHEPARDS-NILES | 2 TON | ||||||
| M E | WB18 HSE2501139653 | SOLIDS BUILDING WBSFB23D109003, HOIST, GARAGE BAYS, SOLIDS BUILDING, TAG WB-18 | SHEPARDS-NILES | 3 TON | ||||||
| M E | WB19 HSE2507180719 | SOLIDS BUILDING WBSFB23D109004, HOIST, CENTRIFUGE FEED PUMPS 1-4, SOLIDS BUILDING, TAG WB-19 | SHEPARDS-NILES | 3 TON | ||||||
| M E | WB17 HSE2501139197 | SOLIDS BUILDING/INCINERATOR WBSFB23D109002, HOIST, SOLIDS SCREEN ROOM, SOLIDS BUILDING, TAG WB-17 | SHEPARDS-NILES | 3 TON | ||||||
| M E | WB16 HSE2501132601 | SOLIDS BUILDING WBSFB23D109001, HOIST, DUMPSTER BAY, SOLIDS BUILDING, TAG WB-16 | ACCO-WRIGHT | 2 TON | ||||||
| D E | WB06 HSE2501137362 | SOLIDS/CENTRIFUGE BUILDING WBSFB41D109001, HOIST, CENTRIFUGE BUILDING, TAG WB-06 | SHAW-BOX | 7 1/2 TON | ||||||
| M E | WB05 WB05HSE2501133839 | PLANT WATERING BUILDING WBSFB17D109002, HOIST, OLD PLANT WATER PUMP ROOM, AIR SCOUR BLDG, TAG WB-05 | SHEPARDS-NILES | 3 1/2 TON | ||||||
| D E | WB01 HSE2501130706 | BLOWER BUILDING WBSFB04D109001, HOIST, BLOWER BUILDING 1, TAG WB-01 | DETROIT | 3 TON | ||||||
| D E | WB13 HSE2501138976 | RAS PUMPING STATION WBSFB08D109001, HOIST 1, NORTH SIDE, RAS PUMPING STATION, TAG WB-13 | ACCO-WRIGHT | 3 TON | ||||||
| D E | WB14HSE2501139416 | RAS PUMPING STATION WBSFB08D109002, HOIST 2, SOUTH SIDE, RAS PUMPING STATION, TAG WB-14 | ACCO-WRIGHT | 3 TON | ||||||
| PEDESTAL | WB12 HSE2501131031 | RAS PUMPING STATION WBSFB08D109003, HOIST, JIB, RAS PUMPING STATION, TAG WB-12 | ACCO-WRIGHT | 3 TON | ||||||
| MM | WB08 HSE2501136045 | DAF BUILDING WBSFB03D109001, HOIST, THICKENER BUILDING, TAG WB-08 | YALE | 3 TON | ||||||
| MM | WB04 HSE2501134898 | WBSFB17D109001, HOIST, BLOWER ROOM, AIR SCOUR BLDG, TAG WB-04 | ACCO-WRIGHT | 3 TON | ||||||
| MM | WB21 HSE2501131853 | WBSFB44D109001, HOIST 1, THICKENED SLUDGE STORAGE BLDG, TAG WB-21 | ACCO-WRIGHT | 3 TON | ||||||
| ME | WB23 HSE2501134977 | INFLUENT UV SOUTH WBSFB14D109001, HOIST, UV BASINS 1 AND 2 BANKS, TAG WB-23 | SHAW-BOX | 1/2 TON | ||||||
| ME | WB24 HSE2501136979 | INFLUENT UV EAST WBSFB14D109002, HOIST, UV BASINS 1 AND 2 SCREEN, TAG WB-24 | SHOP STAR | 1/4 TON | ||||||
| ME | WB25 HSE2501139913 | INFLUENT UV NORTH WBSFB14D109003, HOIST, UV BASIN 3 BANK, TAG WB-25 | SHAW-BOX | 1/2 TON | ||||||
| ME | WB26 HSE2501134450 | INFLUENT UV WEST WBSFB14D109004, HOIST, UV BASIN 3 SCREEN, TAG WB-26 | DAYTON | 1/4 TON | ||||||
| M M | WB27 HSE2501130009 | HRAS/NAS WBSFB43D109001, HOIST, HRAS/NAS PUMP STATION, TAG WB-27 | DETROIT | 10 TON | ||||||
| M M | WB22 HSE2501130989 | WBSFB44D109002, HOIST 2, THICKENED SLUDGE STORAGE BLDG, TAG WB-22 | DETROIT | 10 TON | ||||||
| D E | WB11 HSE2501132488 | PLANT WATER STATION WBSFB15D109001, HOIST, PLANT WATER 2 PUMPING STATION, TAG WB-11 | ACCO-WRIGHT | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| D E | PI-11 HSE2501139032 | E/M SHOP - CRANE1 PISFB29D109001, HOIST, E/M SHOP, TAG PI-11 | SHAW-BOX | 5 TON | ||||||
| D E | PI- 12 HSE2501130499 | E/M SHOP - CRANE2 PISFB29D109002, HOIST, E/M STORAGE, TAG PI-12 | SHAW-BOX | 5 TON | ||||||
| M E | PI04 HSM2509020215 | CHEMICAL BUILDING PISFB08D109001, HOIST, CHEMICAL BUILDING, TAG PI-04 | WRIGHT | 1 TON | ||||||
| M E | PI-06 HSE2501133031 | CHLORINE BUILDING (OLD) PISFB09D109001, HOIST, CHLORINE BUILDING, TAG PI-06 | YALE | 2 TON | ||||||
| M E | PI0-9 HSE2501130796 | DEWATERING BUILDING C #1 PISFB28D109001, HOIST 1, DEWATERING BUILDING C, TAG PI-09 | SHAW-BOX | 2 TON | ||||||
| M E | PI-10 HSM2501133028 | DEWATERING BUILDING C #2 PISFB28D109002, HOIST 2, DEWATERING BUILDING C, TAG PI-10 | SHAW-BOX | 2 TON | ||||||
| M E | PI07 HSM2500021155 | DEWATERING BUILDING C #3 PISFB28D109004, HOIST 4, DEWATERING BUILDING C, TAG PI-07 | YALE | 1 TON | ||||||
| B M | PI-02 HSE2501131177 | DEWATERING BUILDING C (OVER BELT FILTER PRESSES)PISFB39D109003, HOIST, SCREEN LEVELING DUMPSTER 6, TAG PI-02 | YALE | 1 TON | ||||||
| M E | PI-16 HSM2509031117 | EFFLUENT PUMPING STATION PISFB10D109001, HOIST, EFFLUENT PUMPING STATION, TAG PI-16 | YALE | 1 TON | ||||||
| M E | PI- 03 HSE2501218746 | U/V BUILDING PISFB11D109001, HOIST, UV BASIN, TAG PI-03 | SHAW-BOX | 1/2 TON | ||||||
| MM | PI-14 HSE2501134849 | FILTER BUILDING PISFB12D109001, HOIST, MCC ROOM, FILTER BUILDING, TAG PI-14 | YALE | 2 TON | ||||||
| D E | PI- 13 HSM2509031100 | FILTER BUILDING PISFB12D109002, HOIST, PIPE GALLERY, FILTER BUILDING, TAG PI-13 | SHAW-BOX | 2 TON | ||||||
| D M | PI17 HSM2509290759 | INFLUENT PUMPING STATIONPISFB39D109001, HOIST, JIB, GRIT CHAMBER 4, TAG PI-17 | YALE | 5 TON | ||||||
| M M | PI-15 HSM2509120713 | NITRIFICATION TUNNEL PISFB06D109002, HOIST 2, TRAIN 2 PIPE GALLERY, TAG PI-15 | CHESTER | 3 TON | ||||||
| M M | PI-01 HSM2509021153 | NITRIFICATION TUNNEL PISFB06D109001, HOIST 1, TRAIN 2 PIPE GALLERY, TAG PI-01 | HARRINGTON | 3 TON | ||||||
| M E | PI-05 HSE2501131177 | CHLORINE BUILDING (NEW) PISFB39D109004, HOIST, SCREEN LEVELING DUMPSTER 8, TAG PI-05 | YALE | 2 TON | ||||||
| M E | PI-08 HSM2509021154 | PM SHOP A&B BUILDING PISFB28D109003, HOIST 3, DEWATERING BUILDING C, TAG PI-08 | YALE | 1 TON | ||||||
| D E | PI18 HSM2509290800 | RAW SEWAGE PUMPING STATION PISFB39D109002, HOIST, JIB, GRIT CHAMBER 5, TAG PI-18 | P&H | 4 TON | ||||||
| HE | PB-02 HSE2501136089 | CAKE RECEIVING BUILDING HOIST 1, IN VAULT, CAKE RECEIVING BUILDING, TAG PB-02, Hoist Electric, In Service | KONE CRANES | 2 TON | ||||||
| HE | PB-04 HSE2505061112 | HOIST, DIGESTER CONTROL BUILDING, TAG PB-04 | ACCO/WRIGHT | 3TON | ||||||
| HE | PB-01 HSE2505061000 | HOIST, POST DEWATERING, SOLIDS BUILDING, TAG PB-01, Hoist Electric, In Service | ACCO/WRIGHT | 2 TON | ||||||
| HE | PB-03 HSE2501131744 | HOIST 2, ABOVE VAULT, CAKE RECEIVING BUILDING, TAG PB-03, Hoist Electric, In Service | KONE CRANES | 2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| MM | SW01 HSE2501135326 | SWSPB01D109001, HOIST, CONTROL ROOM, TAG SW-01, SWAN CREEK WWPS | CHESTER HOIST | 3 TON | ||||||
| MM | SW02 HSE2501136300 | SWSPB01D109002, HOIST, DRY WELL, TAG SW-02, SWAN CREEK WWPS | WRIGHT | 3 TON | ||||||
| MM | SW03 HSE2501135446 | SWSPB01D109003, HOIST, ABOVE GRINDER, TAG SW-03, SWAN CREEK WWPS | WRIGHT | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| MM | FF01 HSM2501131762 | PUMP ROOM FFSPB01D109001, HOIST, PUMP ROOM, TAG FF-01, FORT FOOTE WWPS | WRIGHT | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M E | BC01 HSE2501138196 | PUMP ROOMBCSPB01D109001, HOIST, PUMP ROOM, PUMP STATION BLDG, TAG BC-01, BROAD CREEK WWPS | CHESTER | 6 TON | ||||||
| JIB E | BC02 HSE2508190701 | BCSPB01D109002, HOIST, JIB CRANE 1, PUMP STATION BLDG, TAG BC-02, BROAD CREEK WWPS | CHESTER | 6 TON | ||||||
| JIB E | BC03 HSE2508190702 | BCSPB01D109003, HOIST, JIB CRANE 2, PUMP STATION BLDG, TAG BC-03, BROAD CREEK WWPS | CHESTER | 6 TON | ||||||
| JIB E | BC04 HSE2508190703 | BCSPB01D109004, HOIST, JIB CRANE 3, PUMP STATION BLDG, TAG BC-04, BROAD CREEK WWPS | CHESTER | 6 TON | ||||||
| JIB E | BC05 HSE2508190704 | BCSPB01D109005, HOIST, JIB CRANE 4, PUMP STATION BLDG, TAG BC-05, BROAD CREEK WWPS | CHESTER | 6 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| MM | PI03 | PUMP ROOM | C&M | 1 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| MM | TH01 HSM2501131824 | GARAGETHD1B03D1090001, HOIST 1, FLEET SERVICE GARAGE, TAG TH-01, TEMPLE HILLS DEPOT | CHESTER | 2 TON | ||||||
| MM | TH02 HSM2501135542 | GARAGE THD1B03D1090002, HOIST 2, FLEET SERVICE GARAGE, TAG TH-02, TEMPLE HILLS DEPOT | COFFIN | 1 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| D E | SE02 HSE2501132512 | ADMINISTRATION BUILDINGSESFB01D109002, HOIST, E/M SHOP BRIDGE, TAG SE-02 | WRIGHT | 5 TON | ||||||
| D E | SE03 HSE2501138411 | PUMPING STATION SESFB02D109001, HOIST, INFLUENT PUMPING STATION, TAG SE-03 | STAHL | 5 TON | ||||||
| ME | SE06 HSE2501138304 | TERTIARY (ABOVE TANK) SESFB06D109002, HOIST, ABOVE TANKS, TERTIARY BLDG, TAG SE-06 | WRIGHT | 2 TON | ||||||
| ME | SE05 HSE2501135311 | TERTIARY PUMP ROOM SESFB06D109001, HOIST, ABOVE PUMPS, TERTIARY BLDG, TAG SE-05 | WRIGHT | 5 TON | ||||||
| JIB M | SE20 HSE2501135799 | RETENTION BASIN SESFBLOBCRNJIB1, HOIST 1, RETENTION BASIN JIB, TAG SE-20 | WRIGHT WAY | 1/2 TON | ||||||
| JIB M | SE01 HSE2501133293 | E/M SHOP SESFB01D109001, HOIST, E/M SHOP JIB, TAG SE-01 | LONE STAR | 1/2 TON | ||||||
| ME | SE19 HSE2501134111 | RETENTION BASIN BLOWER BUILDING SESFBLOBCRNE, HOIST, RETENTION BASIN BLOWER BLDG, TAG SE-19 | SHAW-BOX | 5 TON | ||||||
| HE | SE 08 HSM2501139709 | BIOSOLIDS BUILDING MAINTENANCE SHAFTSESFB08D109002, HOIST, BIOSOLIDS BIN, TAG SE-08 | YALE | 1/2 TON | ||||||
| ME | SE15 HSM2501135731 | BLOWER BLUILDING (DOWN STAIRS)SESFB09D109004, HOIST, BLOWER 1, BLOWER BLDG, TAG SE-15 | COFFING | 2 TON | ||||||
| JIB M | SE12 HSE2501139342 | BLOWER BUILDING (UPSTAIRS) SESFB09D109001, HOIST, JIB, BLOWER BLDG, TAG SE-12 | HARRINGTON | 2 TON | ||||||
| D E | SE09 HSE2501133959 | SOLIDS FACILTY SLUDGE THICKENING SESFB08D109003, HOIST, BRIDGE, SOLIDS FACILITY, TAG SE-09 | STAHL | 7.5 TON | ||||||
| ME | SE10 HSE2501130459 | SOLIDS FACILTY EAST STABILIZATION SESFB08D109004, HOIST, EAST STABILIZATION, TAG SE-10 | COFFING | 2 TON | ||||||
| ME | SE11 HSE2501139342 | SOLIDS FACILITY WEST STABILIZATION SESFB08D109005, HOIST, WEST STABILIZATION, TAG SE-11 | COFFING | 2 TON | ||||||
| H M | SE07 HSE2501136588 | BIOSOLIDS BIN BYPASS CONVEYER SESFB08D109001, HOIST, BYPASS CONVEYOR, TAG SE-07 | HARRINGTON | 1 TON | ||||||
| MM | SE14 HSE2501134514 | BLOWER BUILDING SESFB09D109003, HOIST, MONORAIL, BLOWER BLDG, TAG SE-14 | HARRINGTON | 3 TON | ||||||
| MM | SE16 HSM2501130284 | BLOWER BUILDING SESFB09D109005, HOIST, BLOWER 2, BLOWER BLDG, TAG SE-16 | HARRINGTON | 3 TON | ||||||
| MM | SE17 HSM2501132522 | BLOWER BUILDING SESFB09D109006, HOIST, BLOWER 3, BLOWER BLDG, TAG SE-17 | HARRINGTON | 3 TON | ||||||
| MM | SE13 HSE2501136432 | BLOWER BUILDING SESFB09D109002, HOIST, JIB, CLEANING SYSTEM, BLOWER BLDG, TAG SE-13 | HARRINGTON | 3 TON | ||||||
| MM | SE18 HSE2501131144 | SESFB12D109001, HOIST, UV SYSTEM, TAG SE-18 | HARRINGTON | 3 TON | ||||||
| MM | SE 21 HSE2501133246 | SESFBLOBCRNJIB2, HOIST 2, RETENTION BASIN JIB, TAG SE-21 | HARRINGTON | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M M | GA02 HSE2501217087 | YARD GAD1B01D109002, HOIST, YARD, TAG GA-02, GAITHERSBURG DEPOT | PHILADELPHIA | 2 TON | ||||||
| JIB E | GA01 HSM2509021050 | DEPOT YARDGAD1B01D109001, HOIST, FLEET GARAGE, TAG GA-01, GAITHERSBURG DEPOT | YALE | 2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| D E | CP01 HSE2501137199 | PUMP ROOM CPSPB01D109001, HOIST, PUMP ROOM, TAG CP-01, CLOPPER ROAD WWPS | YALE | 1 TON | ||||||
| D E | CP02 HSE2501137566 | PUMP ROOM CPSPB01D109002, HOIST, OVER GRINDER, TAG CP-02, CLOPPER ROAD WWPS | YALE | 1 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| DM | NE HSM2501133027 | PUMP ROOM NEWPB01D109001, HOIST, PUMP ROOM, TAG NE-01, NEELSVILLE WPS | C&M | 4 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| D M | BKET01 HSM2501138966 | BKETWSTKD109001, HOIST, TAG BK-01, BRINK ELEVATED TANK | C&M | 2 TON | ||||||
| DM | BKW2 HSE2501130590 | BKW2B02D109001, HOIST, TAG BK-02, BRINK 2 WPS | C&M | 2 TON | ||||||
| D M | BKWP HSM2501139900 | BKWPB01D109001, HOIST, PUMP ROOM, TAG BK-03, BRINK WPS | C&M | 2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| D M | CE01 HSM2501132201 | PUMP ROOMCEWPB01D109001, HOIST, PUMP ROOM, TAG CE-01, CEDAR HEIGHTS WPS | C&M | 2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M E | DA05 HSM2501137012 | INFLUENT WETWELL DASFB08D109002, HOIST, RAW PUMPING STATION, WET WELL, TAG DA-05 | YALE | 1 TON | ||||||
| DE | DA03 HSE2501136813 | DASFB03D109001, HOIST, BLOWER BUILDING, TAG DA-03 | YALE | 1 TON | ||||||
| DE | DA 02 HSM2509020204 | DASFB02D109002, HOIST 2, SCREENING GRIT BLDG, TAG DA-02 | YALE | 1TON | ||||||
| D E | DA04 HSE2501131825 | PUMP STATION MOTOR ROOM DASFB08D109001, HOIST, RAW PUMPING STATION, PUMP ROOM, TAG DA-04 | R&M SPACEMASTER | 2 TON | ||||||
| D E | DA06 HSE2501136692 | SOLIDS BUILDING DASFB06D109001, HOIST, SOLIDS BUILDING, TAG DA-06 | R&M SPACEMASTER | 1 TON | ||||||
| D E | DA 01 | DASFB02D109001, HOIST 1, SCREENING GRIT BLDG, TAG DA-01 | R&M SPACEMASTER | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| ME | AP01 HSM2501136343 | PUMP ROOM APWPB01D109001, HOIST, PUMP ROOM, TAG AP-01, AIR PARK WPS | BUDGIT | 2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| M E | GS 01 HSE2501130037 | PUMP ROOM GSWPB01D109001, HOIST, PUMP ROOM, TAG GS-01, GOSHEN ROAD WPS | DEMAG | 4 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| D E | LS 01 HSE2501133388 | PUMP ROOM LSSPB01D109001, HOIST, PUMP ROOM, TAG LS-01, LITTLE SENECA WWPS | ROBBINS-MYERS | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| DM | PO 10 HSE2501137352 | E/M SHOP POWFB46D109001, HOIST, E/M SHOP, TAG PO-10 | YALE | 15 TON | ||||||
| ME | PO 04 HSM2509020139 | SURGE TANK BUILDING POWFB31D109001, HOIST 1, SURGE TANK BUILDING, TAG PO-04 | BUDGIT | 2 TON | ||||||
| ME | PO 05 HSM2509020145 | SURGE TANK BUILDING POWFB31D109002, HOIST 2, SURGE TANK BUILDING, TAG PO-05 | BUDGIT | 2TON | ||||||
| ME | PO 16 HSE2501135781 | UV BUILDING PUMP ROOM POWFB55D109002, HOIST, EAST UV BUILDING, TAG PO-16 | ACCO-WRIGHT | 5 TON | ||||||
| ME | PO 17 HSE2501136358 | UV BUILDING PUMP ROOM POWFB56D109001, HOIST, WEST UV BUILDING, TAG PO-17 | ACCO-WRIGHT | 5 TON | ||||||
| ME | PO 15 HSE2501137347 | UV BUILDING PUMP ROOM POWFB55D109001, HOIST, UVE-JC-1845 EAST UV BUILDING ROOF, TAG PO-15 | ACCO-WRIGHT | 5 TON | ||||||
| ME | PO 07 HSE2501138788 | CHLORINE BUILDING POWFB41D109001, HOIST, CHLORINE BUILDING, TAG PO-07 | SHAW BOX | 2 TON | ||||||
| MM | PO 01 HSM2501133315 | HEAD HOUSE EAST OIL BAY BAYPOWFB01D109001, HOIST, EAST OIL BAY, HEADHOUSE, TAG PO-01 | D.ROUND &SON | 1 1/2 TON | ||||||
| DE | PO 14 HSE2501136909 | RAW PUMP STATION # 2 (MOTOR ROOM) POWFB50D109002, HOIST, SCREEN ROOM, RAW WATER PS 2, TAG PO-14 | SHEPARD-NILES | 30/5 TON | ||||||
| DE | PO 13 HSE2501130544 | RAW PUMP STATION # 2 (SCREEN ROOM) POWFB50D109001, HOIST, MOTOR ROOM, RAW WATER PS 2, TAG PO-13 | SHEPARD-NILES | 30/5 TON | ||||||
| DE | PO-06 HSE2501131038 | WATER PUMPING STATION POWFB40D109001, HOIST, FINISHED WATER PS, MAIN ZONE, TAG PO-06 | MAR-LIFT | 15 TON | ||||||
| ME | PO 08 HSE2501137352 | HIGH ZONE PUMPING STATION MEZZANINE POWFB45D109001, HOIST 1, HIGH ZONE PS, MAIN ZONE, TAG PO-08 | ACCO-WORK RATED | 7 1/2 TON | ||||||
| HE | PO-20 HSE2501130266 | POWFB63D109001, HOIST, WEST INTERMEDIATE PS PUMP ROOM, TAG PO-20 | 2 TON | |||||||
| DE | PO 09 HSE2501139241 | HIGH ZONE PUMPING STATION POWFB45D109002, HOIST 2, HIGH ZONE PS, MAIN ZONE, TAG PO-09 | ACCO-WORK RATED | 20 TON | ||||||
| ME | PO 18 HSE2501131140 | WEST UV BUILDING POWFB56D109002, HOIST, UVE-JC-2845 WEST UV BUILDING ROOF, TAG PO-18 | R&M | 5 TON | ||||||
| DE | PO 23 HSE2501137352 | INTAKE CLAM SHELL POWFINTKCRNCLSH, HOIST, INTAKE RAKE, TAG PO-23 | SHEPARD-NILES | 2 TON | ||||||
| DM | PO 2 HSM2509020150 | HEAD HOUSE WW4 PUMP ROOM POWFB01D109003, HOIST, WASHWATER 4, HEADHOUSE, TAG PO-03 | CHESTER | 10 TON | ||||||
| PORTABLE HOIST | PO-24 HSM2501135461 | POWFSNBCBC10010, PORTABLE HOIST, TAG PO-24 | 1 TON | |||||||
| PORTABLE HOIST | PO-25 HSM2501138635 | POWFSNBCBC20011, PORTABLE HOIST, TAG PO-25 | 1 TON | |||||||
| PORTABLE HOIST | PO-26 HSM2501134774 | POWFSNBCBC30010, PORTABLE HOIST, TAG PO-26 | 1 TON | |||||||
| PORTABLE HOIST | PO-27 HSM2501137450 | POWFSNBCBC40011, PORTABLE HOIST, TAG PO-27 | 1 TON | |||||||
| MM | PO 11 HSE2501135021 | SOLIDS BUILDING POWFB47D109001, HOIST, M-11-1 BELT FILTER PRESS ROOM, TAG PO-11 | YALE-MIDGET | 1/2 TON | ||||||
| MM | PO 28 HSM2501139466 | FERRIC CHLORIDE BLDG POWF01246, HOIST, FERRIC VAULT, TAG PO-28 | CM | 1 TON | ||||||
| HE | PO 19 HSE2501135901 | POWFB62D109001, HOIST, EAST INTERMEDIATE PS PUMP ROOM, TAG PO-19 | VITAL | 3 TON | ||||||
| ME | PO | E/M SHOP | YALE | 1/2 TON | ||||||
| HE | PO 20 HSE2501130266 | POWFB63D109001, HOIST, WEST INTERMEDIATE PS PUMP ROOM, TAG PO-20 | 2 TON | |||||||
| HE | PO-21 HSE2501130406 | AIR SCOUR BLOWER BLDG POWFB66D109001, HOIST 1, AIR SCOUR BLOWER BUILDING, TAG PO-21 | MODEL#MDT02 | 2 TON | ||||||
| HE | PO-22 HSE2501130215 | AIR SCOUR BLOWER BLDG POWFB66D109002, HOIST 2, AIR SCOUR BLOWER BUILDING, TAG PO-22 | YALE | 2TON | ||||||
| BM | PO- | E/M SHOP OIL | WRIGHT | 1/2 TON | ||||||
| ME | PO 02 HSE2501135779 | HEADHOUSE WW 1,2,3 PUMP ROOMS POWFB01D109002, HOIST, WASHWATER 1, 2 & 3, HEADHOUSE, TAG PO-02 | D.ROUND &SON | 5 TON | ||||||
| ME | PO 12 HSE2501133295 | SOLIDS BUILDING POWFB47D109002, HOIST, SOLIDS HANDLING BUILDING, TAG PO-12 | YALE | 1 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| DE | WH-01 HSE2501132824 | WHEATON PUMPING STATION WHWPB01D109001, HOIST, PUMP ROOM, TAG WH-01, WHEATON WPS | SHAW BOX | 5 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| E | CT-01 HSE2501136565 | JIB #1 CTSPB01D109001, HOIST, JIB CRANE 1, TAG CT-01, CRYSTAL ROCK WWPS | LODE STAR | 1/2 TON | ||||||
| E | CT-02 HSE2501130802 | JIB #2 CTSPB01D109002, HOIST, JIB CRANE 2, TAG CT-02, CRYSTAL ROCK WWPS | LODE STAR | 1/2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| E | FD-01 HSE2501139346 | ABOVE MOTORS FDSPB01D109001, HOIST, MOTOR ROOM, TAG FD-01, FREEDOM HILL WWPS | DAYTON | 1/2 TON | ||||||
| E | FD-02 HSE2501132923 | ABOVE PUMPS FDSPB01D109002, HOIST, PUMP ROOM, TAG FD-02, FREEDOM HILL WWPS | HARRINGTON | 1/2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| E | HM-01 HSE2501134512 | ABOVE MOTORS HMSPB01D109001, HOIST, PUMP ROOM, TAG HM-01, HOYLES MILLS WWPS | HARRINGTON | 1 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| E | KF-01 HSE2501132932 | ABOVE PUMPS KFSPB01D109001, HOIST, PUMP ROOM, TAG KF-01, KING FARM WWPS | HARRINGTON | 2 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| ME | NH-01 HSE2501132277 | PUMP ROOM NHSPB01D109001, HOIST, PUMP ROOM, TAG NH-01, NATIONAL HARBOR WWPS | YALE | 3 TON | ||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| ME | AC-01 HSM2501135088 | INSIDE TANK ACETWSTKD109001, HOIST, INSIDE TANK, TAG AC-01, ACCOKEEK ELEVATED TANK | HARRINGTON | 2 TON | |||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00
| $0.00 | ||||||||||
| TOTAL A: | TOTAL A: | TOTAL A: | TOTAL A: | TOTAL A: | $0.00 | |||||
| TOTAL B: | TOTAL B: | TOTAL B: | TOTAL B: | TOTAL B: | $0.00 | |||||
| Section A: Total cost for Annual Inspection and recommended maintenance (PM) | ||||||||||
| Section B: Total Cost For Load Test | All Inclusive Regular Rates (Per Hour) | |||||||||
| Section C: Additional Work | ||||||||||
| Labor Classification : Additional Work | Estimated Hours | |||||||||
| Crane Service Technician | 1500 | $0.00 | ||||||||
| Crane Helper | 1000 | $0.00 | ||||||||
| Engineer/ Non-Destructive Testing | 500 | $0.00 | ||||||||
| Total Section C: | $0.00 |
TOTAL BID: (SECTION A,B AND C) $0.00
A. Anacostia Depot Listed below are the definitions for the abbreviations used in the Type column
D E = Dual Rail- Electric Crane /Hoist M E = Monorail-Electric Crane/Hoist WSSC Crane/Hoists Inspections and Corrective Service Pricing Page M M = Monorail- Manual Crane/Hoist JIB E =Jib-Electrical Crane/Hoist JIB M = Manual Crane/ Hoist H E = Hook-Electric Crane/Hoist B M = Bridge-Manual Crane/Hoist H M = Hook-Manual Crane/Hoist
Total A: Anacostia Depot B. Lower Anacostia Pumping Station #2
C. CENTRAL AVENUE WATER PUMPING STATION
D. HILL ROAD PUMPING STATION
E. HYATTSVILLE WASTEWATER PUMPING STATION
F. LYTTONVILLE DEPOT
G. ROCK CREEK STORAGE FACILITY
TOTAL B : LOWER ANACOSTIA PUMPING STATION #2
TOTAL C: CENTRAL AVENUEWATER PUMPING STATION
D. HILL ROAD WATER PUMPING STATION
TOTAL D: HILL ROAD WATERPUMPING STATION
E. HYATTSVILLE WASTEWATER PUMPING STATION
TOTAL E: HILL ROAD WATERPUMPING STATION
F. LYTTONSVILLE DEPOT
TOTAL F:LYTTONSVILLE DEPOT
TOTAL G: ROCK CREEK STORAGE FACILITY
H. COLMAR MANOR WASTEWATER PUMPING STATION
TOTAL H: COLMAR MANOR WASTEWATER PUMPING STATION
I. PARKWAY WATER RESOURCE RECOVERY FACILITY
TOTAL I :PARKWAY WATER RESOURCE RECOVERY FACILITY
J.PUMPKIN HILL WASTEWATER PUMPING STATION
TOTAL J: PUMPKIN HILL WASTEWATER PUMPING STATION
K. HORSEPEN WASTEWATER PUMPING STATION
TOTAL K: HORSEPEN WASTEWATER PUMPING STATION
L. BOWIE WATER PUMPING STATION
V. BRIGHTON DAM
Q. ROCKY GORGE DAM (T.DUCKET DAM)
TOTAL : ROCKEY GORGE DAM (T. DUCKET DAM)
R:COLESVILLE WATER PUMPING STATION
Y. GREEN BRANCH WASTEWATER PUMPING STATION
TOTAL ANNUAL INSPECTION (SECTION A )
TOTAL REQUIRED LOAD TEST (SECTION B)
Payment Discount Offered (Please choose one) :
_____________1%- 20 DAYS
---------------------2%- 15 DAYS
_____________NET 30
COMPANY'S NAME:
COMPANY'S ADDRESS
CONTACT NAME ________________________________________________________________________
CONTACT PHONE NUMBER___________________________________________________________________
CONTACT FAX NUMBER______________________________________________________________________
CONTACT EMAIL ADDRESS___________________________________________________________________
D. HILL ROAD PUMPING STATION
L. BOWIE WATER PUMPING STATION
TOTAL L: BOWIE WATER PUMPING STATION
M. BEDFORD WASTEWATER PUMPING STATION
TOTAL M: BEDFORD WASTE WATER PUMPING STATION
F. LYTTONSVILLE DEPOT
V. BRIGHTON DAM
N. SOUTH LAUREL WATER PUMPING STATION
TOTAL N: SOUTH LAUREL WATER PUMPING STATION
O. PATUXENT WATER TREATMENT PLANT
Total O: PATUXENT WATER FILTRATION PLANT
P. ROCKY GORGE WATER PUMPING STATION
P.ROCKY GORGE WATER PUMPING STATION
TOTAL N: ROCKY GORGE WATER PUMPING STATION
TOTAL R: COLESVILLE WATER PUMPING STATION
S: NORBECK WATER PUMPING STATION
S:NORBECK WATER PUMPING STATION
Y. GREEN BRANCH WASTEWATER PUMPING STATION
TOTAL S:NORBECK WATER PUMPING STATION
S: NORBECK WATER PUMPING STATION
S: NORBECK WATER PUMPING STATION
S:NORBECK WATER PUMPING STATION
S: NORBECK WATER PUMPING STATION
T:OLNEY WASTEWATER PUMPING STATION
Y. GREEN BRANCH WASTEWATEPUMPING STATION
TOTAL T:OLNEY WASTEWATER PUMPING STATION
U. REDDY BRANCH WASTEWATER PUMPING STATION
Y. GREEN BRANCH WASTEWATER PUMPING STATION
TOTALU: REDDY BRANCH WASTEWATER PUMPING STATION
V. BRIGHTON DAM
V. BRIGHTON DAM
Y. GREEN BRANCH WASTEWATER PUMPING STATION
TOTAL V. BRIGHTON DAM
W. CONSOLIDATED LAB FACILITY
Y. GREEN BRANCH WASTEWATER PUMPING STATION
TOTAL V. CONSOLIDATED LAB FACILITY
X: MILL BRANCH WASTEWATER PUMPING STATION
Y. GREEN BRANCH WASTEWATER PUMPING STATION
Z. WESTERN BRANCH WATER RESOURCE RECOVERY FACILTY
TOTAL Z: WESTERN BRANCH WATER RESOURCE RECOVERY FACILTY
AA: PISCATAWAY WATER RESOURCE RECOVERY FACILITY
TOTAL AA: PISCATAWAY WATER RESOURCE RECOVERY FACILITY
BB: SWAN CREEK WASTEWATER PUMPING STATION
TOTAL BB: SWAN CREEK WASTEWATER PUMPING STATION
BB: SWAN CREEK WASTEWATER PUMPING STATION
CC: FORT FOOTE WASTEWATER PUMPING STATION
TOTAL CC: FORT FOOTE WASTEWATER PUMPING STATION
BB: SWAN CREEK WASTEWATER PUMPING STATION
DD: BROAD CREEK WASTEWATER PUMPING STATION
TOTAL DD: BROAD CREEK WASTEWATER PUMPING STATION
BB: SWAN CREEK WASTEWATER PUMPING STATION
EE: FOREST HEIGHTS WASTEWATER PUMPING STATION
TOTAL EE: FOREST HEIGHTS WASTEWATER PUMPING STATION
BB: SWAN CREEK WASTEWATER PUMPING STATION
FF: TEMPLE HILLS GARAGE
TOTAL FF: TEMPLE HILLS GARAGE
BB: SWAN CREEK WASTEWATER PUMPING STATION
GG: SENECA WATER RESOURCE RECOVERY FACILITY
TOTAL :GG SENECA WATER RESOURCE RECOVERY FACILTY
HH: GAITHERSBURG DEPOT
TOTAL HH: GAITHERSBURG DEPOT
HH: GAITHERSBURG DEPOT
II: CLOPPER ROAD WASTEWATER PUMPING STATION
TOTAL II: CLOPPER ROAD WASTEWATER PUMPING STATION
HH: GAITHERSBURG DEPOT
JJ:NEELSVILLE WATER PUMPING STATION
TOTAL JJ:NEELSVILLE WATER PUMPING STATION
HH: GAITHERSBURG DEPOT
LL: BRINKS ROAD WATER PUMPING STATION
TOTAL LL: BRINKS ROAD WATER PUMPING STATION
HH: GAITHERSBURG DEPOT
MM: CEDAR HEIGHTS WATER PUMPING STATION
TOTAL MM: CEDAR HEIGHTS WATER PUMPING STATION
HH: GAITHERSBURG DEPOT
NN: DAMASCUS WATER RESOURCE RECOVERY FACILITY
OO: AIR PARK WATER PUMPING STATION
OO: AIR PARK WATER PUMPING STATION
TOTAL OO: AIR PARK WATER PUMPING STATION
HH: GAITHERSBURG DEPOT
PP : GOSHEN ROAD WATER PUMPING STATION
TOTAL PP : GOSHEN ROAD WATER PUMPING STATION
HH: GAITHERSBURG DEPOT
QQ: LITTLE SENECA WASTE WATER PUMPING STATION
RR: POTOMAC WATER TREATMENT PLANT
TOTAL :RR POTOMAC WATER TREATMENT PLANT
SS: WHEATON WATER PUMPING STATION
TOTAL SS: WHEATON WATER PUMPING STATION
BB: SWAN CREEK WASTEWATER PUMPING STATION
TT:CRYSTAL ROCK WASTEWATER PUMPING STATION
TOTAL TT:CRYSTAL ROCK WASTEWATER PUMPING STATION
UU: FREEDOM HILL WASTEWATER PUMPING STATION
VV: HOYLES MILLS WASTEWATER PUMPING STATION
TOTAL VV: HOYLES MILLS WASTEWATER PUMPING STATION
BB: SWAN CREEK WASTEWATER PUMPING STATION
WW. KING FARM WASTEWATER PUMPING STATION
TOTAL WW. KING FARM WASTEWATER PUMPING STATION
BB: SWAN CREEK WASTEWATER PUMPING STATION
XX: NATIONAL HARBOR WASTEWATER PUMPING STATION
TOTAL XX: NATIONAL HARBOR WASTEWATER PUMPING STATION
BB: SWAN CREEK WASTEWATER PUMPING STATION
YY: FORT WASHINGTON ELEVATED WATER TANK
X: MILL BRANCH WASTEWATER PUMPING STATION
TOTAL: Y. GREEN BRANCH WASTEWATER PUMPING STATION
TOTAL NN: DAMASCUS WATER RESOURCE RECOVERY FACILITY
HH: GAITHERSBURG DEPOT
TOTAL UU: FREEDOM HILL WASTEWATER PUMPING STATION
BB: SWAN CREEK WASTEWATER PUMPING STATION
TOTAL QQ: LITTLE SENECA WASTE WATER PUMPING STATION
HH: GAITHERSBURG DEPOT
TOTAL YY: FORT WASHINGTON ELEVATED WATER TANK
H. COLMAR MANOR WASTEWATER PUMPING STATION
U. REDDY BRANCH WASTEWATER PUMPING STATION