This document is a comprehensive permit package from the U.S. Army Corps of Engineers, Port Tampa Bay, Florida Fish and Wildlife Conservation Commission, and the City of Tampa Police Department Marine Unit for the installation of forty-nine (49) waterway markers along the Hillsborough River, Seddon Channel, and Garrison Channel. The project involves installing new waterway markers with varying speed restriction signs (such as "Slow Speed Minimum Wake" and "Idle Speed No Wake") on single piles and bridge fenders, and removing four existing pile-supported markers. The original permit was issued on May 27, 2022, with an initial expiration date of May 31, 2024, and has now been extended to May 31, 2027.
The permit includes detailed environmental protections and compliance requirements, specifically addressing marine wildlife such as manatees, sea turtles, and smalltooth sawfish. The project spans multiple sections of townships and ranges in Hillsborough County, with marker locations ranging from Lowry Park to Davis Boulevard. Extensive conditions are outlined for construction activities, including speed restrictions for vessels, mandatory shutdown procedures if protected marine species are observed, reporting requirements for any collisions or injuries to marine life, and the need to use turbidity barriers and maintain erosion controls. The permit is issued under multiple regulatory frameworks, including the Rivers and Harbors Act, and requires coordination with various state and federal agencies.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
October 24, 2024
Regulatory Division West Permits Branch Tampa Permits Section
SAJ-2021-03260 (NWP-AMI)
City of Tampa Police Department, Marine Unit C/o Mark Maziarz 4400 W Tampa Bay Blvd.
Tampa, Florida 33614 Sent via email: mark.maziarz@tampagov.net
Dear Mr. Maziarz:
The U.S. Army Corps of Engineers (Corps) has completed the review of your application for a Department of the Army permit received on September 20, 2021. Your application was assigned file number SAJ-2021-03260. A review of the information and drawings provided indicates that the proposed work would result in the installation of “Slow Speed/Minimum Wake”, “Idle Speed/No Wake”, and/or “Resume Normal Safe Operation” signs, in an effort by the City of Tampa to improve safety within the Hillsborough River, the Seddon Channel, and the Garrison Channel. The waterway marker signs will be installed on a combination of new and existing pilings, as well as on existing structures, such as bridges, bridge fenders, and ramp structures. The proposed activity will require the installation of nine (9) new, 10-12-inch diameter, wooden pilings that will be jetted into place or installed via auger by barge/floating equipment at the following location coordinates:
Proposed Pilings Piling/Sign # Latitude Longitude Waterway
5 27.93677 -82.45665 Seddon Channel 6 27.93732 -82.4554 Seddon Channel
35 27.9602 -82.46905 Hillsborough River 42 27.96757 -82.4763 Hillsborough River 43 27.98092 -82.47625 Hillsborough River 44 27.98228 -82.47493 Hillsborough River 47 28.0098 -82.4648 Hillsborough River 48 28.0117 -82.46512 Hillsborough River 49 28.01327 -82.4647 Hillsborough River
DEPARTMENT OF THE ARMY
CORPS OF ENGINEERS, JACKSONVILLE DISTRICT
701 SAN MARCO BOULEVARD
JACKSONVILLE, FLORIDA 32207-8175
-2-
Nine (9) existing pilings will be permit as after-the-fact (ATF). The location coordinates for the existing pilings are as follows:
Existing Pilings
Piling/Sign # Latitude Longitude Waterway 1 27.9291 -82.45252 Seddon Channel 2 27.92967 -82.45128 Seddon Channel 3 27.93237 -82.45278 Seddon Channel 4 27.93193 -82.45397 Seddon Channel
17 27.94103 -82.44863 Garrison Channel 36 27.96195 -82.47195 Hillsborough River 37 27.96255 -82.47123 Hillsborough River 45 27.99497 -82.46548 Hillsborough River 46 27.99703 -82.46648 Hillsborough River
The activities subject to this permit are authorized pursuant to authorities under Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. § 403), and Section 14 of the Rivers and Harbors Act of 1899 (33 U.S.C. § 408). The project is located in the Seddon Channel, the Garrison Channel, and the Hillsborough River in Tampa, Florida. The project will begin on the south within the Seddon Channel at the Marjorie Park Marina (97 Columbia Drive) and will continue north within the Hillsborough River to Lowry Park (7525 North Boulevard) in Section 35, Township 28 South, Range 18 East, Tampa, Hillsborough County, Florida.
Your project, as depicted on the enclosed drawings (Enclosure 1), is authorized by Nationwide Permit (NWP) 1 (Aids to Navigation). This verification is valid until March 14, 2026. In order for this NWP authorization to be valid, you must ensure that the work is performed in accordance with the Nationwide Permit General Conditions, the Jacksonville District Regional Conditions, and the General and Project-Specific Special Conditions listed below. Furthermore, if you commence or are under contract to commence this activity before the date that the relevant NWP is modified or revoked, you will have 12 months from the date of the modification or revocation of the NWP to complete the activity under the present terms and conditions of this NWP. You can access the U.S. Army Corps of Engineers' (Corps) Jacksonville District's Regulatory Source Book webpage for links to view NWP information at:
https://www.saj.usace.army.mil/Missions/Regulatory/Source-Book/. Please be aware this Internet address is case sensitive and should be entered as it appears above. Once there, you will need to select “Nationwide Permits.” Among other things, this part of the Source Book contains links to the federal register containing the text of the pertinent NWP authorization and the associated NWP general conditions, as well as separate links to the regional conditions applicable to the pertinent NWP verification.
You must comply with all of the special and general conditions for NWP-1, including any project-specific conditions included in this letter and all conditions incorporated by reference as described above.
-3-
General Conditions:
1. The time limit for completing the work authorized ends on March 14, 2026.
2. You must maintain the activity authorized by this permit in good condition and in conformance with the terms and conditions of this permit. You are not relieved of this requirement if you abandon the permitted activity, although you may make a good faith transfer to a third party in compliance with General Condition 4 below. Should you wish to cease to maintain the authorized activity, or should you desire to abandon it without a good faith transfer, you must obtain a modification of this permit from this office, which may require restoration of the area.
3. If you discover any previously unknown historic or archeological remains while accomplishing the activity authorized by this permit, you must immediately notify this office of what you have found. We will initiate the Federal and state coordination required to determine if the remains warrant a recovery effort of if the site is eligible for listing in the National Register of Historic Places.
4. If you sell the property associated with this permit you must obtain the signature of the new owner on the attached transfer form (Enclosure 2) and forward a copy to this office to validate the transfer of this authorization.
5. You must allow a representative from this office to inspect the authorized activity at any time deemed necessary to ensure that it is being or has been accomplished in accordance with the terms and conditions of your permit.
Project Specific Special Conditions:
The following project specific special conditions are included with this verification:
Special Condition 1: Reporting Address: The Permittee shall submit all reports, notifications, documentation, and correspondence required by the general and special conditions of this permit to either (not both) of the following addresses:
a. For electronic mail (preferred): SAJ-RD-Enforcement@usace.army.mil (not to exceed 15 MB).
b. For standard mail: U.S. Army Corps of Engineers, Regulatory Division, Enforcement Section, P.O. Box 4970, Jacksonville, FL 32232-0019.
The Permittee shall reference permit number, SAJ-2021-03260 (NW-AMI), on all submittals.
-4-
Special Condition 2: Commencement Notification: Within 10 days from the date of initiating the work authorized by this permit, the Permittee shall submit a completed “Commencement Notification” form (Enclosure 3).
Special Condition 3: Turbidity Barriers: Prior to the initiation of any of the work authorized by this permit, the Permittee shall install floating turbidity barriers with weighted skirts that extend within one (1) foot of the bottom around all work areas that are in, or adjacent to, surface waters. The turbidity barriers shall remain in place and be maintained daily until the authorized work has been completed and turbidity within the construction area has returned to ambient levels. Turbidity barriers shall be removed upon stabilization of the work area.
Special Condition 4: Manatee Conditions: The Permittee shall comply with the “Standard Manatee Conditions for In-Water Work – 2011” (Enclosure 4).
Special Condition 5: Jacksonville District Programmatic Biological Opinion (JAXBO): Structures and activities authorized under this permit will be constructed and operated in accordance with all applicable PDCs contained in the JAXBO, based on the permitted activity. Johnson’s seagrass and its critical habitat were delisted from the Endangered Species Act on May 16, 2022. Therefore, JAXBO PDCs required to minimize adverse effects to Johnson’s seagrass and its critical habitat are no longer applicable to any project. Failure to comply with applicable PDCs will constitute noncompliance with this permit. In addition, failure to comply with the applicable PDCs, where a take of listed species occurs, would constitute an unauthorized take. The NMFS is the appropriate authority to determine compliance with the Endangered Species Act. The most current version of JAXBO can be accessed at the Jacksonville District Regulatory Division website in the Endangered Species section of the Sourcebook located at:
http://www.saj.usace.army.mil/Missions/Regulatory/SourceBook.aspx
JAXBO may be subject to revision at any time. The most recent version of the JAXBO must be utilized during the design and construction of the permitted work.
Special Condition 6: Proposed Species/Critical Habitat: The action falls within the range for the green sea turtle and the West Indian manatee, and proposed critical habitat for the species under the Endangered Species Act. If the final critical habitat is designated and the authorized work has not been completed, the Permittee is required to stop work and ask the Corps to re-evaluate the effects of the permitted action on the species and their critical habitat, and if needed, complete Section 7 consultation with the National Marine Fisheries Service, and the U.S. Fish and Wildlife Service to address potential impacts to green sea turtles and/or the West Indian Manatee and their critical habitat.
-5-
Special Condition 7: Cultural Resources/Historic Properties:
a. No spudding, anchoring, or excavation shall occur within the established 100-foot environmentally sensitive exclusion buffer set by the Corps of Engineers, as depicted in Enclosure 5 of the permit for and during the installation of piling/waterway marker no. 49.
b. No structure or work shall adversely affect, impact, or disturb properties listed in the National Register of Historic Places (NRHP), or those eligible for inclusion in the NRHP.
b. If, during permitted activities, items that may have historic or archaeological origin are observed the Permittee shall immediately cease all activities adjacent to the discovery that may result in the destruction of these resources and shall prevent his/her employees from further removing, or otherwise damaging, such resources. The applicant shall notify both the Florida Department of State, Division of Historical Resources, Compliance Review Section at (850)-245-6333 and the Corps, of the observations within the same business day (8 hours).
Examples of submerged historical, archaeological, or cultural resources include shipwrecks, shipwreck debris fields (such as steam engine parts, or wood planks and beams), anchors, ballast rock, concreted iron objects, concentrations of coal, prehistoric watercraft (such as log "dugouts"), and other evidence of human activity. The materials may be deeply buried in sediment, resting in shallow sediments or above them, or protruding into water. The Corps shall coordinate with the Florida State Historic Preservation Officer (SHPO) to assess the significance of the discovery and devise appropriate actions. Project activities shall not resume without verbal and/or written authorization from the Corps.
c. Additional cultural resources assessments may be required of the permit area in the case of unanticipated discoveries as referenced in accordance with the above Special Condition and, if deemed necessary by the SHPO or Corps, in accordance with 36 CFR 800 or 33 CFR 325, Appendix C (5). Based on the circumstances of the discovery, equity to all parties, and considerations of the public interest, the Corps may modify, suspend, or revoke the permit in accordance with 33 CFR Part 325.7. Such activity shall not resume on non-federal lands without written authorization from the SHPO for finds under his or her jurisdiction, and from the Corps.
d. In the unlikely event that unmarked human remains are identified on non-federal lands; they will be treated in accordance with Section 872.05 Florida Statutes. All work and ground disturbing activities within a 100-meter diameter of the unmarked human remains shall immediately cease and the Permittee shall immediately notify the medical examiner, Corps, and State Archaeologist within the same business day (8-hours). The Corps shall then notify the appropriate SHPO. Based on the circumstances of the discovery, equity to all parties, and considerations of the public interest, the Corps may modify, suspend, or revoke the permit in accordance with 33 CFR Part 325.7. Such activity shall not resume without written authorization from the SHPO and from the Corps.
-6-
Special Condition 8: Federal Channel Setback: The most waterward edge of the authorized project shall be constructed as verified by Navigation (CESAJ-PM-WC) and depicted in the Hillsborough River BRA Horizontal (X&Y) Survey (Enclosure 6).
Rationale: This special condition is required by CESAJ SOP No. 1145-2-3 dated 6 July 2020.
Special Condition 9: As-Built Certification with X-Y Coordinates: Within 60 days of completion of the authorized work or at the expiration of the construction window of this permit, whichever occurs first, the Permittee shall submit as-built drawings of the authorized work and complete the enclosed “As-Built Certification by Professional Engineer or Surveyor” form, (Enclosure 7) to the Corps. The drawings shall be signed and sealed by a registered professional engineer or a professional land surveyor confirming the actual location of all authorized work/structures with respect to the Federal channel and/or within the Federal easement and include the following:
a. A plan view drawing of the location of the authorized work footprint (as shown on the permit drawings) with an overlay of the work as constructed in the same scale as the attached permit drawings (8½-inch by 11-inch). The drawings shall include the X & Y State Plane coordination points of the most waterward point of the structure. The drawings shall include the dimensions of the structure, location of mean high water line (MHWL), depth of water (at mean low water) at the waterward end of the structure, and the distance from the waterward end of the structure to the near design edge of the Federal channel.
b. List of any deviations between the work authorized by this permit and the work as constructed. In the event the completed work deviates, in any manner, from the authorized work, describe on the As-Built Certification Form the deviations between the work authorized by this permit and the work as constructed. Clearly indicate on the as-built drawings any deviations that have been listed. Please note the depiction and/or description of any deviations on the drawings and/or As-Built Certification Form does not constitute approval of any deviations by the Corps.
c. The Department of the Army Permit number.
Special Condition 10: Assurance of Navigation and Maintenance: The Permittee understands and agrees that, if future operations by the United States require the removal, relocation, or other alteration, of the structures or work herein authorized, or if in the opinion of the Secretary of the Army or his authorized representative, said structure or work shall cause unreasonable obstruction to the free navigation of the navigable waters, the Permittee will be required, upon due notice from the U.S. Army Corps of Engineers, to remove, relocate, or alter the structural work or obstructions caused thereby, without expense to the United States. No claim shall be made against the United States on account of any such removal or alteration.
-8-
Enclosures (7)
1. Project Drawings, 11 pages
2. DA Permit Transfer Request Form, 1 page
3. Commencement Notification Form, 1 page
4. Standard Manatee Conditions for In-water Work 2011, 2 pages
5. Exclusion Buffer, 1 page
6. Hillsborough River X&Y Survey, 27 pages
7. As-Built Certification by Professional Engineer or Surveyor Form, 2 pages
Cc (w/ encls) Jay Reese, Tampa Police Department, Marine Unit, joseph.reese@tampagov.net Danielle Riffenburg, City of Tampa, Danielle.Riffenburg@tampagov.net
GFGFGFGF
GFGF
GFGFGFGF
Proposed Waterway Markers on Hillsborough River Map A Davis Islands Marina to Interstate 275 City of Tampa ¯800 0 800400 Feet
Harbour Island
E. Davis Blvd
Garrison Channel
See Map B
Selmon Expway
Seddon Channel
Sparkman Channel
Hillsborough Bay
Interstate 275
Kennedy Blvd (SR 60)
Cass Street
Laurel St
Platt Street
Davis Islands
Davis Islands Marina
N Bo ule va rd
5 678 9 10
1718 19
22 23
25 26
27 28
Legend #* Proposed Marker Locations (Piles) !. Proposed Marker Locations (Fenders) GF Proposed Marker Locations (Bridges) $+ Proposed Marker Locations (On Shore)
See Waterway Marker Data Form for signage details at each location.
Idle Speed No Wake Zone Slow Speed Minimum Wake Zone
ENCLOSURE 1 - SAJ-2021-03260
k3rdpami Highlight k3rdpami Highlight k3rdpami Highlight k3rdpami Highlight k3rdpami Highlight k3rdpami Highlight k3rdpami Highlight
Proposed Waterway Markers on Hillsborough River Map B Interstate 275 to south of Hillsborough Avenue City of Tampa ¯800 0 800400 Feet
N.
Bo ule va rd
See Map A
Dr. M.L. King Jr. Boulevard
See Map C
Columbus Drive
Flo rid a A ve nu e
Legend #* Proposed Marker Locations (Piles) !. Proposed Marker Locations (Fenders) GF Proposed Marker Locations (Bridges) $+ Proposed Marker Locations (On Shore)
See Waterway Marker Data Form for signage details at each location.
Idle Speed No Wake Zone Slow Speed Minimum Wake Zone
Int ers tat e 2
ENCLOSURE 1 - SAJ-2021-03260
k3rdpami Highlight k3rdpami Highlight k3rdpami Highlight
Proposed Waterway Markers on Hillsborough River Map C Hillsborough Avenue to Lowry Park City of Tampa ¯800 0 800400 Feet
Flo rid a A ve nu e
See Map B
Lowry Park
Hillsborough Avenue
Sligh Avenue
Ro me
Av en ue
Legend #* Proposed Marker Locations (Piles) !. Proposed Marker Locations (Fenders) GF Proposed Marker Locations (Bridges) $+ Proposed Marker Locations (On Shore)
See Waterway Marker Data Form for signage details at each location.
Idle Speed No Wake Zone Slow Speed Minimum Wake Zone
Int ers tat e 2
ENCLOSURE 1 - SAJ-2021-03260
Proposed Waterway Markers on Hillsborough River Map B Cass Street Bridge to Columbus Street Bridge City of Tampa Federal Channel Locations ¯800 0 800400 Feet
See Map A
Interstate 275
Columbus Drive
Cypress Street
Legend
#* Proposed Marker Locations (Piles)
!. Proposed Marker Locations (Fenders)
GF Proposed Marker Locations (Bridges)
$+ Proposed Marker Locations (On Shore)
See Waterway Marker Data Form for signage details at each location.
Idle Speed No Wake Zone
Slow Speed Minimum Wake Zone
Ricks's On The River
Marina
30 29
Federal Channel
ENCLOSURE 1 - SAJ-2021-03260
pr07 Typewritten Text Federal Channel Maps pr07 Typewritten Text pr07 Typewritten Text k3rdpami Highlight k3rdpami Highlight k3rdpami Highlight
GFGFGFGF
GF
GF
GFGFGFGF
Proposed Waterway Markers on Hillsborough River Map A Davis Islands Marina to Cass Street Bridge City of Tampa Federal Channel Locations ¯800 0 800400 Feet
Harbour Island
See Map B
Selmon Expway
Hillsborough Bay
Platt Street
Davis Islands
Davis Islands Marina
9 10
14 16
22 23
25 26
Legend
#* Proposed Marker Locations (Piles)
!. Proposed Marker Locations (Fenders)
GF Proposed Marker Locations (Bridges)
$+ Proposed Marker Locations (On Shore)
See Waterway Marker Data Form for signage details at each location.
Idle Speed No Wake Zone
Slow Speed Minimum Wake Zone
Federal Channel
ENCLOSURE 1 - SAJ-2021-03260
k3rdpami Highlight k3rdpami Highlight k3rdpami Highlight k3rdpami Highlight k3rdpami Highlight k3rdpami Highlight
::E:
a.
(Tl .;,j '<t .;,j-
(X) (\J
' " 0
' M
Ol
,II,
"CJ
'° J: u 4:
::E:
~ ·a +' a, A C Ol vi Ul u a, a.
(I)
..c u a, I Ul a, d a.
E a, I-
~ ·a a.
a, " '<t If) (Tl u
IL.
"'...J '<t 4:
(\J 1- (\J (/) (\J 4:
-□ '-U
OJ/
Ill •• :::ll:J
PLASTIC PILE CAP AND (4)
#10 X 1.5" STAINLESS STEEL
SCREWS OR PREAPPROVED EQUAL
--------3/8"x1.5" STAINLESS STEEL
LAG BOLTS AND LOCK WASHERS
4"x4"
NYLON FLAT WASHER
BETWEEN STAINLESS
SIGN
STEEL FASTENER JI AND ALUMINUM
__ ...,,_ __ --t---t---SPACER----..11
TYPE 304 3 4" STAINLESS STEEL BOLTS
NUTS, FLAT WASHERS, AND LOCK WASH_ER_S_.;.~---;-- -1-.
3/8"x1.5" STAINLESS STEEL.-==t:::::-
LAG BOLTS AND LOCK WASHERS
6" WHITE REFL
SECURED WITH
STAINLESS STE
MINIMUM 1" LA
MINIMUM 10" WOODEN
NON-SPLICED PILING
8"
6' - 9'
BOLTS MUST NOT
EXTEND MORE THAN
1" BEYOND NUT
AND WASHER
MEAN HIGH WATER SURF ACE
(VARIES BASED ON LOCATION)
VARIABLE BASED ON LOCATION
"""T"--.----.--....---.---..----,.-----.--1---.--1-......---.----.--....---.---..---+-,.-----.-- suBsTRATE
SURFACE
PBSJ
t::I.QIE;_
MINIMUMS:
8' WHEN SUBSTRATE IS SAND AND/OR SHELL
10 + WI-IEN SUBSTRATE IS MUD
1. ALL PILINGS MUST BE PRESSURE TREATED LUMBER (2.50 CCA FOR SALTWATER APPLICATIONS; 0.80
CCA, 0.80 ACQ, OR 1.0 ACZA FOR FRESHWATER APPLICATIONS.
2. ALL FRAMING FOR SIGNBOARD MUST BE PRESSURE TREATED LUMBER (0.60 CCA, 0.60 ACQ, OR 0.60 ACZA FOR SALTWATER APPICATIONS; 0.40 CCA, 0.40 ACQ, 0.40 ACZA, 0.21 CA OR 0.41 CBA FOR
FRESHWATER APPICATIONS).
3. BOLT HOLES BORED 1/8" LARGER THAN DIAMETER OF BOLT. ALL FASTENERS MUST BE VANDAL
PROOFED.
4. THE CONTRACTOR SHALL NOT IMPACT THE MESSAGE AREA OR REFLECTIVE SURFACES OF THE SIGN
WHEN DRIWNG HOLES IN THE SIGNS, OR SPLIT THE ENDS OF THE CROSSING TIMBERS
5. PLASTIC PILE CAP SHALL BE EQUAL TO THE TOP EDGE OF THE SIGN (±6") AND SHALL FIT PILING
NATURALLY WITHOUT HAVING TO MODIFY CAP IN ANY WAY.
6. SIGN(S) MUST BE CENTERED ON SINGLE PILE. NOT TO SCALE
Maintenance & Repair Work 3'x4'
Uniform Waterway Marker Plans Single Pile Sign Detail
ENCLOSURE 1 - SAJ-2021-03260
pr07 Rectangle pr07 Typewritten Text
MINIMUM 3'-0"
pr07 Typewritten Text pr07 Typewritten Text
DEPARTMENT OF THE ARMY PERMIT TRANSFER REQUEST
DA PERMIT NUMBER: SAJ-2021-03260 (NW-AMI)
When the structures or work authorized by this permit are still in existence at the time the property is transferred, the terms and conditions of this permit will continue to be binding on the new owner(s) of the property. Although the construction period for works authorized by Department of the Army permits is finite, the permit itself, with its limitations, does not expire.
To validate the transfer of this permit and the associated responsibilities associated with compliance with its terms and conditions, have the transferee sign and date below and mail to the U.S. Army Corps of Engineers, Enforcement Section, Post Office Box 4970, Jacksonville, FL 32232-0019 or submit via electronic mail to:
SAJ-RD-Enforcement@usace.army.mil (not to exceed 15 MB).
(TRANSFEREE-SIGNATURE) (SUBDIVISION)
(DATE) (LOT) (BLOCK)
___________________________________ (STREET ADDRESS)
(NAME-PRINTED)
(MAILING ADDRESS)
(CITY, STATE, ZIP CODE)
ENCLOSURE 2 - SAJ-2021-03260
COMMENCEMENT NOTIFICATION
Within ten (10) days of initiating the authorized work, submit this form to via electronic mail to saj-rd-enforcement@usace.army.mil (preferred, not to exceed 15 MB) or by standard mail to U.S. Army Corps of Engineers, Enforcement Section, P.O. Box 4970, Jacksonville, FL 32232-0019.
1. Department of the Army Permit Number: SAJ-2021-03260 (NWP-AMI)
2. Permittee Information:
Name: __________________________________________ Email: __________________________________________ Address: __________________________________________
Phone: __________________________________________
3. Construction Start Date: ______________________
4. Contact to Schedule Inspection:
Name: __________________________________________ Email: __________________________________________ Phone: __________________________________________
Signature of Permittee Printed Name of Permittee Date
ENCLOSURE 3 - SAJ-2021-03260
saj-mailto:saj-rd-enforcement@usace.army.mil
STANDARD MANATEE CONDITIONS FOR IN-WATER WORK
The permittee shall comply with the following conditions intended to protect manatees from direct project effects:
a. All personnel associated with the project shall be instructed about the presence of manatees and manatee speed zones, and the need to avoid collisions with and injury to manatees. The permittee shall advise all construction personnel that there are civil and criminal penalties for harming, harassing, or killing manatees which are protected under the Marine Mammal Protection Act, the Endangered Species Act, and the Florida Manatee Sanctuary Act.
b. All vessels associated with the construction project shall operate at "Idle Speed/No Wake” at all times while in the immediate area and while in water where the draft of the vessel provides less than a four-foot clearance from the bottom. All vessels will follow routes of deep water whenever possible.
c. Siltation or turbidity barriers shall be made of material in which manatees cannot become entangled, shall be properly secured, and shall be regularly monitored to avoid manatee entanglement or entrapment. Barriers must not impede manatee movement.
d. All on-site project personnel are responsible for observing water-related activities for the presence of manatee(s). All in-water operations, including vessels, must be shutdown if a manatee(s) comes within 50 feet of the operation. Activities will not resume until the manatee(s) has moved beyond the 50-foot radius of the project operation, or until 30 minutes elapses if the manatee(s) has not reappeared within 50 feet of the operation. Animals must not be herded away or harassed into leaving.
e. Any collision with or injury to a manatee shall be reported immediately to the Florida Fish and Wildlife Conservation Commission (FWC) Hotline at 1-888-404-3922. Collision and/or injury should also be reported to the U.S. Fish and Wildlife Service in Jacksonville (1-904-731-3336) for north Florida or Vero Beach (1-772-562-3909) for south Florida, and to FWC at ImperiledSpecies@myFWC.com
f. Temporary signs concerning manatees shall be posted prior to and during all in-water project activities. All signs are to be removed by the permittee upon completion of the project. Temporary signs that have already been approved for this use by the FWC must be used. One sign which reads Caution: Boaters must be posted. A second sign measuring at least 8 ½” by 11" explaining the requirements for “Idle Speed/No Wake” and the shut down of in-water operations must be posted in a location prominently visible to all personnel engaged in water-related activities. These signs can be viewed at MyFWC.com/manatee. Questions concerning these signs can be sent to the email address listed above.
ENCLOSURE 4 - SAJ-2021-03260
mailto:ImperiledSpecies@myFWC.com�
CAUTION: MANATEE HABITAT
All project vessels
IDLE SPEED / NO WAKE
When a manatee is within 50 feet of work all in-water activities must
SHUT DOWN
Report any collision with or injury to a manatee:
Wildlife Alert:
1-888-404-FWCC (3922)
cell * FWC or #FWC
ENCLOSURE 4 - SAJ-2021-03260
Legend µStreet Names World Transportation
Override 1
Override 1
Esri, HERE, iPC, University of South Florida, City of Tampa, Esri, HERE, Garmin, INCREMENT P, USGS, EPA, USDA, Esri, HERE, Garmin, iPC, State of Florida, Maxar, Microsoft
Map Created by: Adelyn Irlanda
Date: 10/24/2024
Coordinate System: WGS 1984 Web Mercator Auxiliary Sphere
0 0.02 0.04 0.07 mi
Map Center: 82.464367°W 28.013975°N
SAJ-2021-03260 - PILING/SIGN NO. 49
EXCLUSION/AVOIDANCE BUFFER
28.014641, -82.464141
28.013398, -82.463751
28.013682, -82.465023
28.01327, -82.4647
Legend Piling/sign No. 49
Exclusion/Avoidance Zone Points
Exclusion/Avoidance Zone (no spudding, anchoring, or excavation shall occur within this area)
ENCLOSURE 5 - SAJ-2021-03260
ENCLOSURE 6 - SAJ-2021-03260
AS-BUILT CERTIFICATION BY PROFESSIONAL ENGINEER
Submit this form and one set of as-built engineering drawings to the U.S. Army Corps of Engineers, Enforcement Section, P.O. Box 4970, Jacksonville, FL 32232-0019. For electronic mail saj-rd-enforcement@usace.army.mil (not to exceed 15 MB).
1. Department of the Army Permit Number: SAJ-2021-03260 (NW-AMI)
2. Permittee Information:
Name: _____________________________________________
Address: _____________________________________________
3. Project Site Identification (physical location/address):
4. As-Built Certification: I hereby certify that the authorized work, including any mitigation required by Special Conditions to the permit, has been accomplished in accordance with the Department of the Army permit with any deviations noted below. This determination is based upon on-site observation, scheduled, and conducted by me or by a project representative under my direct supervision. I have enclosed one set of as-built engineering drawings.
Signature of Engineer Name (Please type)
(FL, PR, or VI) Reg. Number Company Name
City State ZIP
(Affix Seal)
Date Telephone Number
ENCLOSURE 7 - SAJ-2021-03260
-2-
Date Work Started:____________________ Date Work Completed:______________________
Identify any deviations from the approved permit drawings and/or special conditions (attach additional pages if necessary):
ENCLOSURE 7 - SAJ-2021-03260
1101 Channelside Drive Tampa, Florida 33602-3612 P: 813.905.7678 800.741.2297 F:813.905.5109 www.porttb.com info@tampaport.com
May 27, 2022
City of Tampa – Police Department, Marine Unit Attn: Sergeant Mark Maziarz 4400 W. Tampa Bay Blvd.
Tampa, FL 33614 (Via Email: mark.maziarz@tampagov.net)
Reference: Port Tampa Bay (PTB) Minor Work Permit No. 22-007
Enclosed is the Tampa Port Authority, d/b/a Port Tampa Bay (PTB), minor work permit for which you made application. Please review this document and attachments carefully, paying particular attention to the stipulations and approved drawings. This permit is effective immediately.
However, work on your project may not begin until all other applicable local, state and federal authorizations have been obtained. This permit shall expire on the date indicated. This authorization will be valid until such time as it is amended, replaced, or revoked.
This permit authorizes the above named applicant, hereinafter referred to as the Permittee, to perform the described work on or adjacent to submerged lands of City of Tampa and/or Port Tampa Bay. This work shall be accomplished in accordance with the general and specific stipulations hereinafter defined.
Acceptance of this permit constitutes acceptance of all the attached stipulations and drawings.
Compliance with all stipulations is necessary for the permit to be considered valid. Should you have objections to any of these stipulations, you must file your objections, in writing, with this Authority within fourteen (14) days of the above date.
Sincerely, Christopher Cooley Christopher J. Cooley Director of Environmental Affairs
Enclosures
Cc: COT Parks & Rec Dept. – karla.price@tampagov.net SW_ERP@dep.state.fl.us; ERPAgencyCoordination@swfwmd.state.fl.us tampareg@usace.army.mil City of Tampa - dave.jennings@tampagov.net; monica.ammann@tampagov.net File (22-007) mailto:mark.maziarz@tampagov.net mailto:karla.price@tampagov.net mailto:SW_ERP@dep.state.fl.us mailto:AgencyCoordination@swfwmd.state.fl.us mailto:TAMPAREG@USACE.ARMY.MIL mailto:DAVE.JENNINGS@TAMPAGOV.NET
P E R M I T
MINOR WORK PERMIT NUMBER: 22-007
PERMITTEE: CITY OF TAMPA – POLICE DEPARTMENT, MARINE UNIT
ATTN: SERGEANT MARK MAZIARZ
4400 W. TAMPA BAY BLVD.
TAMPA, FL 33614
AGENT: CITY OF TAMPA PARKS & RECREATION DEPARTMENT
ATTN: KARLA PRICE
3402 W. COLUMBUS DR.
TAMPA, FL 33607
PROJECT DESCRIPTION: INSTALLATION OF FORTY-NINE (49) REPLACED,
RELOCATED, OR NEW IDLE/SLOW SPEED UNIFORM WATERWAY MARKERS ON
SINGLE PILES OR ATTACHED TO BRIDGE FENDERS, INCLUDING REMOVAL OF FOUR
(4) PILE SUPPORTED WATERWAY MARKERS PURSUANT TO PERMIT EXHIBITS AND
STIPULATIONS
PROJECT LOCATION: VARIOUS LOCATIONS BETWEEN LOWRY PARK AT NORTH
END (7525 N. BOULEVARD, TAMPA, FL) TO DAVIS BLVD.
BRIDGE AT SOUTH END AND TO BENEFICIAL DR. BRIDGE AT
WEST END OF PROJECT, TAMPA, FLORIDA
HILLSBOROUGH RIVER & SEDDON & GARRISON CHANNELS
Folio #290000-0006, 290000-0213, 290000-0191 & 290000-0214 Sections 25, 35 & 36, Township 28S, Range 18E Sections 1, 2, 11, 13, 14, 24, 25 & 26, Township 29S, Range 18E Section 19, Township 29S, Range 19E
DATE OF ISSUE: MAY 27, 2022
EXPIRATION DATE: MAY 31, 2024
AUTHORIZED SIGNATURE: Christopher Cooley
THIS NOTICE MUST BE CONSPICUOUSLY
DISPLAYED AT THE SITE OF WORK
PORT TAMPA BAY GENERAL PERMIT STIPULATIONS:
1. The proposed work shall be done in accordance with the approved drawings attached hereto as Exhibits. Any modification of this permitted project will require additional authorizations by Port Tampa Bay (PTB).
2. The Permittee shall notify Port Tampa Bay when work under this permit is initiated and shall further notify PTB when work under this permit has been completed. Port Tampa Bay staff reserves the right to inspect all work conducted pursuant to this permit to ensure compliance with these stipulations.
3. The enclosed Permit Notice Card must be conspicuously displayed at the project site once work on this project has been initiated and shall remain so displayed until the project has been completed. Within fifteen (15) days of completion of this project, the Permit Card must be returned to the Port Tampa Bay Environmental Department.
4. All work shall be accomplished so as to minimize the dispersion of silt and debris and the destruction of marine resources in public waters. All applicable water quality standards shall be maintained. Silt barriers will be employed, if necessary, to accomplish this. Construction materials, debris, or other trash will not be allowed to escape into the water, at anytime. Such materials are to be disposed of properly in an upland disposal facility, i.e. appropriate trash receptacles, etc.
5. The proposed work shall be done so as to prevent interference with the riparian or property rights of the adjacent property owners. This permit authorizes no invasion of private property or rights in property.
6. This permit conveys no title to land or water, and does not alter in any way the legal riparian rights of the
Permittee. Issuance of this permit does not constitute a binding determination of riparian boundaries, lines or rights.
7. The Permittee, in accepting this permit, agrees to comply with the provisions and conditions herein and assumes all responsibilities and liability and agrees to hold Port Tampa Bay harmless from any and all claims of damage arising out of operations conducted pursuant to this permit.
8. If the approved permit drawings and the attached Specific Stipulations contradict each other, then the Specific
Stipulations shall prevail.
9. The Permittee shall operate and maintain the authorized structure(s) in such a manner so as to prevent the creation of any navigation hazards, unauthorized source of air or water pollution, hazard to public health and safety, or so as to unduly interfere with the public’s use of the waterway.
10. Should the Permittee fail to comply with the stipulations of this permit, should a situation arise wherein it would be in the public interest, Port Tampa Bay reserves the right to revoke this permit upon written notice to the Permittee.
11. This permit does not relieve the Permittee from the requirement of permits from the U.S. Army Corps of
Engineers, Florida Department of Environmental Protection, Southwest Florida Water Management, Hillsborough County, individual municipalities within Hillsborough County, and/or other applicable agencies, as required. Ensure all conditions/stipulations of this PTB marine construction permit, and the State permit with the Corps authorizations shall be followed. In the instances where the conditions of these permits do not fully agree, comply with the most restrictive/conservative requirement(s).
12. This permit does not relieve the Permittee from the requirement of any applicable deed restrictions.
13. No authorization granted under this rule may be assigned or otherwise transferred without approval of the
Authority and payment of applicable transfer fees as set forth in Section III of Port Tampa Bay rules.
14. PTB shall not be responsible for any omissions or errors in information provided by owner, owner’s contractor or agent, or contained in the public records.
PORT TAMPA BAY
MINOR WORK PERMIT NO. 22-007
SPECIFIC STIPULATIONS
1. This marine construction permit authorizes the installation of forty-nine (49) idle/slow speed
Uniform Waterway Markers that are either new, replaced or relocated and removal of four (4) existing single-pile waterway markers at various locations that shall be single-pile supported signs or attached to bridge fenders, as depicted on Exhibits A-1 through A-12 of this permit and described on Exhibit B (Markers Information Table).
2. This minor work permit is issued by Port Tampa Bay (PTB) in accordance with Section 4.a.5.
of the Tampa Port Authority/Environmental Protection Commission (EPC) of Hillsborough County Interlocal Agreement dated June 23, 2009 since portions of the project area fall within commercial tidal lands, such as Garrison Channel and Seddon Channel.
3. Issuance of this marine construction permit is in accordance with the City of Tampa
Ordinance No. 2020-105, dated October 15, 2020, relating to the boating restrictions, pursuant to Exhibit C.
4. The Permittee shall coordinate with Notice to Mariners a minimum of 1 week prior to start of construction for this project. Ensure all navigation hazard information has been relayed to USCG Sector St. Petersburg for Notice to Mariners (NTM) marine radio broadcasts, including the locations of turbidity barrier deployments, and other potential navigation hazards to vessels transiting the marine construction site. To initiate NTM marine broadcasts, email the written NTM summary information to USCG Sector St. Petersburg at D07-SMB-Tampa- WWM@uscg.mil [including location(s), specifics concerning marine construction affecting navigation, names of any on-site construction vessels, planned start and end dates, name of point of contact(s) with telephone number(s), etc.]. For assistance in preparing a NTM summary, contact the USCG Sector St. Petersburg Command Duty Officer at (813) 918- 7282.
5. The Permittee and/or their authorized agent/contractor shall coordinate with CSX
Transportation, Inc. prior to any work occurring at the W. Cass Street bridge within a 50 foot buffer to the railroad tracks regarding a separate CSX Right-of-Entry or Non-Environmental Right-of-Entry authorization(s) if required by CSX staff. CSX permitting information for projects can be found online at csx.com/permitting or contacting their staff at (904) 279-3956.
6. The activity and any barges or other vessels used during the authorized marine construction activities must not interfere with navigation.
7. Continued uninterrupted recreational boat navigation within Hillsborough River channel, Garrison Channel, Seddon Channel and Hillsborough Bay shall be maintained during construction activities. Furthermore, any barge based work shall be conducted during tide conditions when appropriate water depths are present to prevent impacts to any submerged
(PTB #MWP 22-007: Specific Stipulations, Page 1 of 3) mailto:D07-SMB-Tampa-WWM@uscg.mil aquatic resources during movement to/from or within the project area and must not impeded public navigation.
8. All construction material and equipment staging area(s) shall occur only in uplands on the City of Tampa’s property or on the floating barge, as necessary. No storage or stockpiling of tools and materials within wetlands or other surface waters is allowed.
9. Turbidity curtains and any other necessary erosion control device resources shall be utilized to prevent water quality violations. Turbidity curtains must remain in place until all sediments have settled out of the water column.
10. All in-water marine construction activities shall be limited to daylight hours only.
11. Ensure compliance with Conditions 1 through 3 of Exhibit D (EPC of Hillsborough County review letter dated April 14, 2022]. Contact EPC’s Wetland Division, Ms. Laura Castillo, at 813-627-2600, extension 1357 for additional information.
12. The installation of baithouses, storage shelters, gazebos, screen porches, living quarters or other non-water dependent structures is not authorized.
13. This permit does not authorize any dredge or fill activity.
14. Additional pilings or any other structure(s) extraneous are not authorized.
15. Be advised, the proposed activity may require a building permit from the City of Tampa as the structure is within the City limits. Please call (813) 274-3100 for further information on the permitting process. If the plans approved by this permit change as a result of the City of Tampa review, a revision to this permit will be required.
16. In acceptance of this permit, the Permittee and/or their authorized agent specifically acknowledges and covenants that they shall:
a. Obtain additional authorizations as necessary for any proposed modification(s) of this permitted project which may be required by the PTB Environmental Department, U.S.
Army Corps of Engineers (USACOE Application No. SAJ-2021-03260) and Florida Fish and Wildlife Conservation Commission (FWC), per Exhibit E (FWC Permit No. FUWM- 21-019, issued on August 30, 2021).
b. Ensure all conditions/stipulations of this permit, and the conditions of the USACOE, and FWC permits referenced in Specific Stipulation above are followed. In instances where these permits do not fully agree, either comply with the most restrictive/conservative requirement(s) or submit proposed revisions, as necessary. Failure to comply with the conditions of these permits is a violation that may result in enforcement action being initiated against Permittee and/or their designated marine contractor(s) involved in the violation.
(PTB #MWP 22-007: Specific Stipulations, Page 2 of 3)
17. In acceptance of this permit, the Permittee and/or their authorized agent specifically acknowledges and covenants that:
a. The Hillsborough River is considered sovereign submerged lands. The portion of
Hillsborough River that falls within the limits of the City of Tampa is owned by the City of Tampa, pursuant to City/Port Authority Property Exchange S-1 Area recorded in Official Records Book 20407, Page 871 and Section II.A.3.a. of the PTB Submerged Lands Management Rules (Rules). Contact City of Tampa’s Real Estate Department staff at (813) 274-8845 for more information.
b. The proposed work shall be done so as to prevent interference with the riparian or property rights of the adjacent property owners. This authorization does not allow an invasion of the private property of other property owners or rights in the property of adjacent parcels.
c. This authorization conveys no title to land or water, and does not alter in any way the legal riparian rights of the property owner. Issuance of this authorization does not constitute a binding determination of riparian boundaries, lines, or rights.
d. The applicant/property owner, in accepting this authorization, agrees to comply with the provisions and conditions herein and assumes all responsibilities and liability and agrees to hold Port Tampa Bay harmless from any and all claims of damage arising out of operations conducted pursuant to this authorization.
e. PTB shall not be responsible for any omissions or errors in information provided by owner, owner’s contractor or agent, or contained in the public records.
18. Specific Conditions For Marine Protected Species. The Permittee must comply with the following manatee, sea turtle, and smalltooth sawfish protection conditions during all marine construction authorized by this permit:
a. Ensure all conditions of Exhibit F (FDEP’s Standard Manatee Conditions for In-Water
Work dated 2011) are followed during all phases of marine construction or vessel activity authorized by this permit. Contact the FDEP Southwest District Office in Tampa, Florida at 813-470-5700 for additional information.
b. Ensure all conditions of Exhibit G [National Marine Fisheries Service (NMFS) Sea Turtle and Smalltooth Sawfish Construction Conditions dated March 23, 2006] are followed during all phases of marine construction authorized by this permit. Contact the NMFS Southeast Regional Office in St. Petersburg, Florida at 727-570-5301 for additional information.
(PTB MWP #22-007: Specific Stipulations, Page 3 of 3) jjulien Text Box
TPA/PTB MINOR WORK
PERMIT #22-007
EXHIBIT A-1
TPA/PTB MINOR WORK
EXHIBIT A-2
TPA/PTB MINOR WORK
EXHIBIT A-3
TPA/PTB MINOR WORK
EXHIBIT A-4
TPA/PTB MINOR WORK
EXHIBIT A-5
TPA/PTB MINOR WORK
EXHIBIT A-6
TPA/PTB MINOR WORK
EXHIBIT A-7
TPA/PTB MINOR WORK
EXHIBIT A-8
TPA/PTB MINOR WORK
EXHIBIT A-9
TPA/PTB MINOR WORK
EXHIBIT A-10
TPA/PTB MINOR WORK
EXHIBIT A-11
TPA/PTB MINOR WORK
EXHIBIT A-12
TPA/PTB MINOR WORK
EXHIBIT B (Pg. 1 of 4)
TPA/PTB MINOR WORK
EXHIBIT B (Pg. 2 of 4)
TPA/PTB MINOR WORK
EXHIBIT B (Pg. 3 of 4)
TPA/PTB MINOR WORK
EXHIBIT B (Pg. 4 of 4)
TPA/PTB MINOR WORK
EXHIBIT C (Pg. 1 of 9)
TPA/PTB MINOR WORK
EXHIBIT C (Pg. 2 of 9)
TPA/PTB MINOR WORK
EXHIBIT C (Pg. 3 of 9)
TPA/PTB MINOR WORK
EXHIBIT C (Pg. 4 of 9)
TPA/PTB MINOR WORK
EXHIBIT C (Pg. 5 of 9)
TPA/PTB MINOR WORK
EXHIBIT C (Pg. 6 of 9)
TPA/PTB MINOR WORK
EXHIBIT C (Pg. 7 of 9)
TPA/PTB MINOR WORK
EXHIBIT C (Pg. 8 of 9)
TPA/PTB MINOR WORK
EXHIBIT C (Pg. 9 of 9)
COMMISSION
Mariella Smith CHAIR Pat Kemp VICE-CHAIR Harry Cohen Ken Hagan Gwendolyn “Gwen” W. Myers Kimberly Overman Stacy White
DIRECTORS
Janet D. Lorton EXECUTIVE DIRECTOR Elaine S. DeLeeuw ADMIN DIVISION Sam Elrabi, P.E. WATER DIVISION Rick Muratti, Esq. LEGAL DEPT Reginald Sanford, MPH AIR DIVISION Steffanie L. Wickham WASTE DIVISION Sterlin Woodard, P.E. WETLANDS DIVISION
Environmental Excellence in a Changing World Environmental Protection Commission - Roger P. Stewart Center
3629 Queen Palm Drive, Tampa, FL 33619 - (813) 627-2600 - www.epchc.org
April 14, 2022
Jackie Julien (Sent via Email) Port Tampa Bay jjulien@tampaport.com Post Office Box 2192 Tampa, Florida 33601
SUBJECT: PORT TAMPA BAY (PTB) PERMIT APPLICATION #22-007 /
EPC REVIEW # 74533 / INSTALLATION OF FORTY-NINE (49) UNIFORM
WATERWAY MARKERS AT VARIOUS LOCATIONS WITHIN
HILLSBOROUGH RIVER, SEDDON CHANNEL & GARRISON CHANNEL
IN TAMPA, FL / APPLICATION RECEIVED BY EPC ON APRIL 1, 2022 /
PARTS OF FOLIO #290000-0006, 290000-0213, 290000-0191, & 290000-0214/
STR – 25, 35, & 36-28S-18E AND STR – 1, 2, 11, 14, 13, 24, 25, & 26-29S-18E AND
STR 19-29S-19E; WITHIN CITY OF TAMPA
Dear Ms. Julien:
An environmental review has been conducted for the above described project by the staff of the Wetlands Division of the Environmental Protection Commission (EPC) of Hillsborough County.
Based on this review and site inspection conducted April 11, 2022, staff has determined that the project to install forty-nine (49) uniform waterway markers at various locations within the City of Tampa, including single piles, bridge fenders and other methods, as proposed, should not constitute or create deleterious impacts to the natural resources of Hillsborough County;
therefore, this agency does not object to the proposed project subject to the following conditions:
1. All work must be conducted as proposed and in the location indicated by the plans received on April 1, 2022. Any proposed changes or adjustments must be reviewed and authorized by EPC staff prior to their implementation.
2. All efforts must be undertaken to prevent any erosion or turbid water from being discharged offsite into wetlands and/or waters of the County. Turbid discharges that exceed 29 NTU's (Nephelometric Turbidity Units) above background levels are a violation pursuant to Chapter 1-5, the EPC Water Quality Rule. The erosion or discharge of sediments into wetlands is a violation of Chapter 1-11, the EPC Wetland Rule. Silt screens or other methods of erosion/turbidity control may be required. It is the responsibility of the owner/developer to insure the installation of adequate erosion control barriers prior to the commencement of any site work. These erosion control devices must be maintained in good condition throughout the construction process and mailto:jjulien@tampaport.com jjulien Text Box
TPA/PTB MINOR WORK
EXHIBIT D (Pg. 1 of 2)
PTB File #22-007 City of Tampa Police Department - Marine Unit April 14, 2022
Environmental Excellence in a Changing World until all loose soils have stabilized/settled. It is strongly recommended that all erosion control devices be regularly inspected during construction and modified if conditions warrant.
3. All wetland vegetation, including but not limited to mangroves, must be preserved during all construction of the permitted activity including removal of existing navigation markers. No mangrove removal is allowed. Any additional trimming or alteration of mangroves would require separate review by the EPC, pursuant to Chapter 1-14, Mangrove Trimming and Preservation, Rules of the EPC. This request may be submitted to the EPC through the Mangrove Trimming application or the WEA10-Notice of Exempt Activities in Wetlands form obtained from the EPC website at www.epchc.org. Contact the EPC Wetlands Division at 813-627-2600 for questions.
INFORMATIONAL COMMENTS:
• Please be advised that this approval applies only to the development proposal as submitted, and in no way does it provide EPC approval to any other aspect of the review process. In addition, this approval does not imply exemption from obtaining all proper permits from other governmental agencies.
• It is recommended that no dredging, filling, clearing or scouring occur except for the settings of the navigational aids. If pilings are to be installed by jetting, then the water pump must be shut off when not in use to avoid unnecessary disturbance to the water body.
• Please note that this letter only represents the recommendations of the EPC to the Port
Tampa Bay (PTB). The PTB will issue the actual permit. In the event these conditions are not incorporated in the PTB permit, the proposed activity may require a separate authorization from the Executive Director of the EPC.
If you have any questions or concerns regarding this application, please call me by phone at
(813) 627-2600 ext. 1357 or by e-mail at castillol@epchc.org.
Sincerely, Laura Castillo
Environmental Scientist Wetlands Division Environmental Protection Commission of Hillsborough County lmc/cb ec: Barbara Baity – bbaity@tampaport.com Karla…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .