About this file

This document is a draft cost estimate for the Spalding County Parks Trail System project. The project involves various improvements along Kentucky Avenue & Haskell Ward Drive, North 3rd Street, Thurman Avenue & West Avenue, Cherry Street, and Orange Street & North 12th Street, including tree removal, mailbox relocation, grading, retaining walls, concrete sidewalks, crosswalk striping, and storm drainage work. The total estimated construction cost is $500,293.75, which includes a 10% contingency.

The cost estimate provides detailed line items for the various work components, including unit quantities, unit prices, and extended totals. General conditions, payment/performance bonds, and survey work are also included in the estimate. The project appears to be funded through state and/or local sources, but no specific funding information is provided. No other details are given regarding the solicitation process, timeline, or contract term.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item Description Unit Quantity Unit Price Item Total

GENERAL

1. GENERAL CONDITIONS (8%) LS 1 $32,600.00 $32,600.00

2. PAYMENT AND PERFORMANCE BONDS (3.5%) LS 1 $14,300.00 $14,300.00

3. CONSTRUCTION STAKING (LAYOUT) BY REGISTERED SURVEYOR LS 1 $5,000.00 $5,000.00

4. AS-BUILT SURVEY PLAN BY REGISTERED SURVEYOR LS 1 $3,500.00 $3,500.00

$55,400.00

KENTUCKY AVENUE & HASKELL WARD DRIVE

5. TREE REMOVAL EA 8 $1,500.00 $12,000.00

6. MAILBOX RELOCATION EA 5 $200.00 $1,000.00

7. GRADING/SOIL EXPORT CY 60 $75.00 $4,500.00

8. BLOCK RETAINING WALL SF 524 $25.00 $13,100.00

9. 4" THICK CONCRETE SIDEWALK SF 5,649 $5.00 $28,245.00

10. HANDICAP RAMP W/ DETECTABLE WARNING PAD EA 7 $400.00 $2,800.00

11. THERMOPLASTIC CROSSWALK STRIPING, 10 IN, WHITE LF 245 $2.50 $612.50

$62,257.50

NORTH 3RD STREET

12. CONCRETE CURB REMOVAL INCL. OFF-SITE DISPOSAL LF 460 $5.00 $2,300.00

13. 4" THICK CONCRETE SIDEWALK SF 2,449 $5.00 $12,245.00

14. REMOVE AND REPLACE 4' CHAIN LINK FENCE LF 460 $30.00 $13,800.00

15. REMOVE AND REPLACE 6' WIDE CHAIN LINK DOUBLE SWING GATE EA 1 $500.00 $500.00

16. IN PLACE FILL CY 4,370 $5.00 $21,850.00

$50,695.00

THURMAN AVENUE & WEST AVENUE

17. TREE REMOVAL EA 16 $1,500.00 $24,000.00

18. CLEARING LS 1 $3,500.00 $3,500.00

19. MAILBOX/SIGN RELOCATION EA 7 $200.00 $1,400.00

20. GRADING/SOIL EXPORT CY 24 $75.00 $1,800.00

21. 4" THICK CONCRETE SIDEWALK SF 10,016 $5.00 $50,080.00

22. 60" HDPE STORM PIPE LF 100 $180.00 $18,000.00

23. 60" HEADWALL EA 2 $5,500.00 $11,000.00

24. PEDESTRIAN BRIDGE COMPLETE LS 1 $20,000.00 $20,000.00

25. REMOVE & REPLACE 4' BLACK VINYL COATED CHAIN LINK FENCE LF 145 $45.00 $6,525.00

26. REMOVE & REPLACE 4' CHAIN LINK FENCE LF 235 $30.00 $7,050.00

27. BLOCK RETAINING WALL SF 776 $25.00 $19,400.00

28. THERMOPLASTIC CROSSWALK STRIPING, 10 IN, WHITE LF 430 $2.50 $1,075.00

$163,830.00

SPALDING COUNTY PARKS TRAIL SYSTEM

COST ESTIMATE

North 3rd Street Subtotal =

Thurman Avenue & West Avenue Subtotal =

DECEMBER 5, 2018

General Subtotal =

Kentucky Avenue & Haskell Ward Drive Subtotal =

REVISED 12/05/2018

Item Description Unit Quantity Unit Price Item Total

CHERRY STREET

29. CLEARING AC 0.70 $5,000.00 $3,500.00

30. MAILBOX/SIGN RELOCATION EA 4 $200.00 $800.00

31. IN PLACE FILL CY 1,200 $5.00 $6,000.00

32. 4" THICK CONCRETE SIDEWALK SF 9,175 $5.00 $45,875.00

$56,175.00

ORANGE STREET & NORTH 12TH STREET

33. TREE REMOVAL EA 4 $1,500.00 $6,000.00

34. REMOVE & REPLACE 4' CHAIN LINK FENCE LF 192 $30.00 $5,760.00

34. MAILBOX/SIGN RELOCATION EA 8 $200.00 $1,600.00

35. GRADING/SOIL EXPORT CY 1,500 $25.00 $37,500.00

36. 4" THICK CONCRETE SIDEWALK SF 3,119 $5.00 $15,595.00

$66,455.00

$454,812.50

37. CONTINGENCY $45,481.25 $45,481.25

$500,293.75TOTAL CONSTRUCTION =

10.00%

TOTAL CONSTRUCTION =

Cherry Street Subtotal =

Orange Street & North 12th Street Subtotal =

REVISED 12/05/2018