This is a Standard Form of Agreement between the City of Meriden, Connecticut and a contractor for the refurbishment of the Pool Filtration System at Hubbard Park. The project involves comprehensive replacement of existing filtration infrastructure, including pressure testing existing lines, removing the current filter system, and installing new equipment designed to meet a 680 gallons per minute requirement with a six-hour turnover pool flow design. Specific deliverables include new main drain sumps with 10-inch schedule 40 PVC piping, 8-inch schedule PVC wall inlets/returns piping, a new pump and strainer, high-pressure sand horizontal filters, and Bray valves with stainless steel stems. A mandatory pre-bid meeting is scheduled for December 3, 2025, at 10:00 a.m. at the project site (999 West Main Street, Meriden, Connecticut), with written questions due by December 10, 2025, at 4:00 p.m. Final bids must be submitted no later than 11:00 a.m. on December 17, 2025, through the City's eProcurement Portal. Substantial completion is required by August 31, 2025, with final completion and readiness for payment due within 15 days thereafter.

The contract price is a lump sum amount of $2,243,250.00, with potential unit price work as detailed in the bid documents. Liquidated damages are assessed at $250.00 per day for delays beyond the substantial completion date and final completion date. Progress payments will be made monthly based on applications submitted by the contractor and certificates issued by the engineer, with five percent retainage applied until substantial completion. A bid bond requirement of 10 percent of the bid amount and mandatory 100 percent performance and labor/material payment bonds are required. Bidders must possess three specific Connecticut state licenses: Swimming Pool Builder, Swimming Pool Plumber, and Home Improvement Contractor. Comprehensive insurance coverage of $1,000,000 in General Liability and $1,000,000 in Umbrella/Excess Liability is required, with the City of Meriden named as an Additional Insured. Local preference under Meriden City Code Section 3-14 is available for city-based businesses submitting bids within 10 percent of the lowest bid. Minority business enterprises are encouraged to participate and must submit a Bidder Contract Compliance Monitoring Report addressing nondiscrimination policies and affirmative action plans. Certified payroll documentation for prevailing wage compliance is required monthly with each progress payment requisition.

View the file

Other files

File Type Posted
B026-33_Hubbard_Park_Pool_Filtration_System_(Addendum_#1_Revision).pdf PDF
B026-33_Hubbard_Park_Pool_Filtration_System_(Addendum_#1_Revision).pdf PDF
B026-33_Hubbard_Park_Pool_Filtration_System.pdf PDF
Prevailing_Wage_Info_Packet.pdf PDF
Professional_Serv_Agreement-Sample.pdf PDF
Sample_Payment_Bond.pdf PDF
Construction_Contract-Sample.pdf PDF
Professional_Serv_Agreement-Sample.pdf PDF
Sample_Performance_Bond.pdf PDF
CHRO.pdf PDF
Prevailing_Wage_Info_Packet.pdf PDF
CHRO.pdf PDF
Sample_Performance_Bond.pdf PDF
CHRO.pdf PDF
Construction_Contract-Sample.pdf PDF
Sample_Performance_Bond.pdf PDF
Sample_Payment_Bond.pdf PDF
Prevailing_Wage_Info_Packet.pdf PDF
Professional_Serv_Agreement-Sample.pdf PDF
Sample_Payment_Bond.pdf PDF
EJCDC_General_&_Supplemental.pdf PDF
School_Insurance.pdf PDF
HOLD_for_prevailing_wage.docx DOCX document
General_Insurance.pdf PDF
School_Insurance.pdf PDF
HOLD_for_prevailing_wage.docx DOCX document
School_Insurance.pdf PDF
General_Insurance.pdf PDF
EJCDC_General_&_Supplemental.pdf PDF
General_Insurance.pdf PDF
EJCDC_General_&_Supplemental.pdf PDF
HOLD_for_prevailing_wage.docx DOCX document
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STANDARD FORM OF AGREEMENT

BETWEEN OWNER AND CONTRACTOR

ON THE BASIS OF A STIPULATED PRICE

B025-XX –

THIS AGREEMENT is dated as of the _________ day of August 2025 by and between the City of Meriden, 142 East Main Street Meriden, CT 06450 hereinafter called OWNER and hereinafter called CONTRACTOR.

OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows:

Article 1. WORK.

CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows:

The Project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows:

Article 2. ENGINEER.

The Project has been designed by ABC- DEF Corporation who is hereinafter called ENGINEER and who is to act as Owner’s representative, assume all duties and responsibilities and has the rights and authority assigned to

ENGINEER in the Contract Documents in connection with completion of the Work in accordance with the contract documents.

Article 3. CONTRACT TIMES.

3.1 The Work will be substantially completed by August 31, 2025, after the date when the Contract Times commence to run as provided in paragraph 2.03 of the General Conditions, and completed and ready for final payment in accordance with paragraph 14.07B of the General Conditions by 15 days after the date when the

Contract Times commence to run.

3.2 Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the Work is not completed within the times specified in paragraph

3.1 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. They also recognize the delays, expense and difficulties involved in proving the actual loss suffered by OWNER if the Work is not completed on time. Accordingly, instead of requiring any such proof, OWNER and

CONTRACTOR agree that as liquidated damages for delay (but not as a penalty) CONTRACTOR shall pay

OWNER Two Hundred Fifty Dollars ($250.00) for each day that expires after the time specified in paragraph

3.1 for Substantial Completion until the Work is substantially complete. After Substantial Completion, if

CONTRACTOR shall neglect, refuse or fail to complete the remaining Work within the time specified in paragraph 3.1 for completion and readiness for final payment or any proper extension thereof granted by

OWNER, CONTRACTOR shall pay OWNER Two Hundred Fifty Dollars ($250.00) for each day that expires after the time specified in paragraph 3.1 for completion and readiness for final payment.

Standard Form of Agreement: Page 2

Article 4. CONTRACT PRICE.

OWNER shall pay CONTRACTOR for completion of the Work in accordance with the Contract Documents an amount in current funds equal to the sum of the amounts determined pursuant to paragraphs 4.1 and 4.2 below:

4.1. For all Work, other than Unit Price Work, a Lump Sum of:

Figures $2,243,250.00

Written Two million, two hundred forty-three thousand, two hundred fifty dollars.

All specific cash allowances are included in the above price and have been computed in accordance with 11.02 of the General Conditions;

Plus

4.2. For all Unit Price Work, an amount equal to the sum of the established unit price for each separately identified item of Unit Price Work times the estimated quantity of that item as indicated in this paragraph 4.2:

UNIT PRICE WORK

ESTIMATED UNIT TOTAL

NO. ITEM UNIT QUANTITY PRICE ESTIMATED

TOTAL OF ALL UNIT PRICES:

Written Figures

As provided in paragraph 11.03 of the General Conditions estimated quantities are not guaranteed, and determinations of actual quantities and classification are to be made by ENGINEER as provided in paragraph

9.07 of the General Conditions. Unit prices have been computed as provided in paragraph 11.03C of the

General Conditions.

(The Bid may be attached. Any attachments and/or exhibits attached should be listed in Article 8).

If adjustment prices for variations from stipulated Base Bid quantities have been agreed to, insert appropriate provisions.

Article 5. PROGRESS PAYMENTS.

5.1 Based upon applications for Payment submitted to the Engineer by the Contractor and

Certificates for Payment issued by the Engineer, the Owner shall make progress payments on account to the Contractor as provided below and elsewhere in the Contract

Documents.

5.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month.

Standard Form of Agreement: Page 3

5.3 Each Application for Payment shall be based upon the Schedule of Values submitted by the Contractor in accordance with the Contract Documents. The Schedule of Values shall allocate the entire Contract Sum among the various portions of the Work and be prepared in such form and supported by such data to substantiate its accuracy as the

Engineer may require. This Schedule, unless objected to by the Engineer, shall be used as a basis for reviewing the Contractor’s Applications for Payment.

5.4 Applications for Payment shall indicate the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment.

5.5 Subject to the provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:

5.6.1 Take that portion of the Contract sum properly allocable to completed work as determined by multiplying the percentage completion of each portion of the Work by the share of the total Contract

Sum allocated to that portion of the work in the Schedule of Values, less retainage of five percent (5 percent). Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute may be included as provided in appropriate sections of the General Conditions even though the

Contract Sum has not yet been adjusted by Change Order.

5.6.2 Add that portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction (or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing) less retainage of five percent (5 percent).

5.6.3 Subtract the aggregate of previous payments made by the Owner; and

5.6.4 Subtract amounts, if any, for which the Engineer has withheld or nullified a Certificate for Payment as provided in Paragraph 14.02.B.5 of the General Conditions.

5.7 The progress payment amount determined in accordance with Paragraph 5.6 shall be further modified under the following circumstances;

(Not applicable)

5.7.1 Add, upon Substantial Completion of the Work, a sum sufficient to increase the total payments to ninety-five percent (95) of the Contract Sum, less such amounts as the

Engineer shall determine for incomplete Work and unsettled claims; and

5.7.2 Add, if final completion of the Work is thereafter materially delayed, through no fault of the Contractor, additional amounts payable in accordance with Paragraph 14.08 of the

General Conditions.

Standard Form of Agreement: Page 4

5.8 Reduction or limitation of retainage, if any shall be as follows:

(Not applicable)

5.9 Progress payment requisitions are due monthly on last day of the month for work completed during the contract period. Requisitions are to be sent to the Architect/Engineer and/or City of

Meriden Department responsible for management/administration of the contracted work.

Certified Payroll for construction contracts that require State of Connecticut Prevailing Wage

Determinations are required for each week of work by the Contractor and any or all the

Contractor’s Subcontractors and are due monthly with each requisition. One hard copy and one electronic copy shall be sent to the Architect/Engineer and the City of Meriden Purchasing

Department. No progress payments will be issued to the Contractor without accompanying

Certified Payroll.

For federally funded construction contracts with Davis Bacon Wage Determinations, Certified

Payroll for all employees of the Contractor and any or all of the Contractor’s Subcontractors are required to be submitted weekly to the Architect/Engineer and to the City of Meriden Purchasing

Department. One hard copy and one electronic copy shall be sent to the Architect/Engineer and the City of Meriden Purchasing Department. Employees on the construction site will be interviewed by City of Meriden Staff and/or City of Meriden subcontracted Project

Management/Clerk-of-the-Works/Owner’s Representatives for Davis Bacon compliance. No progress payments will be issued to the Contractor without accompanying Certified Payroll.

Article 6. INTEREST.

No interest shall be due or paid on any monies not paid when due.

Article 7. CONTRACTOR’S REPRESENTATIONS.

In order to induce OWNER to enter into this Agreement CONTRACTOR makes the following representations:

7.1. CONTRACTOR has examined and carefully studied the Contract Documents including the Addenda listed in paragraph 8 and the other related data identified in the Bidding Documents including “technical data.”

7.2. CONTRACTOR has visited the site and become familiar with and is satisfied as to the general, local and site conditions that may affect cost, progress, performance or furnishing of the Work.

7.3. CONTRACTOR is familiar with and is satisfied as to all federal, state and local Laws and Regulations that may affect cost, progress, performance and furnishing of the Work.

7.4. CONTRACTOR has carefully studied all reports of explorations and tests of subsurface conditions at or contiguous to the site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the site (except Underground Facilities) which have been identified in the

Supplementary Conditions as provided in paragraph 4.02 of the General Conditions. CONTRACTOR accepts the determination of the extent of the “technical data” contained in such reports and drawings upon which

CONTRACTOR is entitled to rely. CONTRACTOR acknowledges that such reports and drawings are not

Contract Documents and may not be complete for Contractor’s purposes. CONTRACTOR acknowledges that

OWNER and ENGINEER do not assume responsibility for the accuracy or completeness of information and

Standard Form of Agreement: Page 5 data shown or indicated in the Contract Documents with respect to Underground Facilities at or contiguous to the site. CONTRACTOR has obtained and carefully studied assumes responsibility for having done so) all such additional supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and Underground Facilities) at or contiguous to the site or otherwise which may affect cost, progress, performance or furnishing of the Work or which relate to any aspect of the means, methods, techniques, sequences and procedures of construction to be employed by CONTRACTOR and safety precautions and programs incident thereto. CONTRACTOR does not consider that any additional examinations, investigations, explorations, tests, studies or data are necessary for the performance and furnishing of the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the contract Documents.

7.5. CONTRACTOR is aware of the general nature of work to be performed by OWNER and others at the site that relates to the Work as indicated in the Contract Documents.

7.6. CONTRACTOR has correlated the information known to CONTRACTOR, information and observation obtained from visits to the site, reports and drawings identified in the Contract Documents and all additional examinations, investigations, explorations, tests, studies and data with the Contract Documents.

7.7. CONTRACTOR has given ENGINEER written notice of all conflicts, errors, ambiguities or discrepancies that CONTRACTOR has discovered in the Contract Documents and the written resolution thereof by

ENGINEER is acceptable to CONTRACTOR, and the Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

Article 8. CONTRACT DOCUMENTS.

The Contract Documents, which comprise the entire agreement between OWNER and CONTRACTOR concerning the Work, consist of the following:

8.1. This Agreement.

8.2. General Conditions and Supplemental General Conditions.

8.3. Notice of Award – Attachment A

8.4. Performance, Payment, and other Bonds – Attachment B.

8.5. Insurance certificate – Attachment C

8.6. Contractor’s Bid Proposal, Non-Collusive Bid Statement, Bidder’s Qualification Statement, St of CT Forms that are applicable - Attachment D

8.7. Connecticut Department of Labor – Wage and Workplace Standards Division.

8.8. “By Reference”: The complete Specifications as included in the bidding documents bearing the title.

8.9. “By Reference”: List of Drawings: Sheet No’s. ___ through ___ included in the bidding documents.

The above documents are on file in the City of Meriden’s Purchasing Department.

Standard Form of Agreement: Page 6

8.10. Addenda numbers _____.

(Those addenda which pertain exclusively to the bidding process need not be listed.)

8.11. The following which may be delivered or issued after the Effective Date of the Agreement and are not attached hereto: All-Written Amendments and other documents amending, modifying or supplementing the

Contract Documents pursuant to paragraphs 3.04 and 3.05 of the General Conditions.

There are no Contract Documents other than those listed above. The Contract Documents may only be amended, modified or supplemented as provided in paragraphs 3.04 and 3.05 of the General Conditions.

Article 9. MISCELLANEOUS.

9.1. Terms used in this Agreement which are defined in Article I of the General Conditions will have the meanings indicated in the General Conditions.

9.2. No assignment by a party hereto of any rights under or interests in the Contract Documents will be binding on another party hereto without the written consent of the party sought to be bound; and, specifically but without limitation, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents.

9.3. OWNER and CONTRACTOR each binds itself, its partners, successors, assigns and legal representatives to the other party hereto, its partners, successors, assigns and legal representatives in respect to all covenants, agreements and obligations contained in the Contract Documents.

9.4. Any provision or part of the Contract Documents held to be void or unenforceable under any Law or

Regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon

OWNER and CONTRACTOR, who agree that the Contract Documents shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision.

9.5 OTHER PROVISIONS.

WITNESS WHEREOF, the parties hereto have affixed their names and seals.

THE CITY OF MERIDEN CONTRACTOR:

Brian P. Daniels, City Manager

Duly Authorized Duly Authorized

Date: ________________________ Date: __________________________