Complete Project Bid Doc-6.05.24.pdf
PDF 901 KB Posted
- Solicitation number
- 2110985
- Issued by
- Cattaraugus County, New York
About this file
This document contains the contract documents for the proposed Olean Creek Levee Reconstruction and Sewer Replacement project to be bid on by prospective contractors for the City of Olean Department of Public Works. The project involves improvements to the levee structure and replacement of a 15" sanitary sewer main in Olean, New York. Sealed bids will be received until 1:30 PM on Thursday, July 11, 2024, at which time they will be publicly opened and read. There will be a pre-bid meeting on site on Monday, July 1 from 10-11 AM. Bids must be submitted on the prescribed Proposal Form and accompanied by a Certified Check or Bid Bond for not less than 5% of the bid amount. The successful bidder will be required to provide a Performance Bond and a one-year Guarantee Bond.
The contract does not specify any service-disabled veteran, minority, women, disadvantaged, or other business set-asides. The City of Olean reserves the right to reject any and all proposals. Payment will be made monthly based on work completed with 10% retainage until final completion and acceptance. Contractors and subcontractors must pay the prevailing wage rate as per New York State Labor Law.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BO5.1.pdf | ||
| 2024.07.02 - Olean Sewer Replacement & Levee Restoration.pdf | ||
| Addendum No. 17.docx | DOCX document | |
| 2024.06.06 - Plans & Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DOCUMENTS
FOR THE PROPOSED:
Olean Creek Levee Reconstruction
And Sewer Replacement
BID OPENING:
Thursday, July 11TH, 2024 @ 1:30 PM
CITY OF OLEAN
Municipal Building
P.O. BOX 668
Olean, NY 14760
DEPARTMENT OF PUBLIC WORKS
BRAD CAMP, WATER & SEWER SUPERINTENDENT
TABLE OF CONTENTS
Notice to Bidders Page 3
Notice to Contractors / Scope Page 4
Receipt of Addenda Page 5
Lump Sum Bid Proposal Page 7
Bid Bond Page 8
Non-Collusive Bidding Certification Page 9
Reference Sheet Page 10
Legal Status Information Page 11
General Specifications Page 12
Contract Agreement Page 26
NOTICE TO PROSPECTIVE BIDDERS
Olean Creek Levee Reconstruction
And Sewer Replacement
The City of Olean Department of Public Works is seeking bids for improvements to the levee structure and the replacement of a 15” sanitary sewer main in Olean. Sealed bids will be received at the Office of the Director of Public Works; Room 206 of the Olean Municipal Building, 101
East State Street, Olean, NY, 14760 until 1:30 pm, Thursday, July 11, 2024, at which time they will be publicly opened and read aloud inside the Olean Municipal Building, Room 211.
Bidder information, plans and specifications may be obtained from the Olean Municipal
Building, Public Works Department, Room 206, 1010 East State Street, Olean, NY 14760, mailed or emailed as requested, by calling (716) 376-5650 or emailing dpwadmins@cityofolean.org.
There will be an onsite pre-bid meeting for this project on Monday July, 1 from 10-11am on the levee behind 639 N. Union St. Ext. Please contact Brad Camp, Water & Sewer Superintendent with questions at (716) 376-5659 or bcamp@cityofolean.org
Bids must be submitted on the prescribed Proposal Form and must be accompanied by a
Certified Check or Bid Bond for not less than five (5) percent of the gross amount of bid. Each bidder shall submit their bid in a sealed envelope marked on the outside thereof: “Levee and
Sewer Reconstruction”.
A Bond for the full amount of the Contract will be required of the successful Bidder to secure faithful performance of the Contract and for the payment of all persons performing labor or furnishing materials in connection therewith. A Bond in a similar amount will be required as guarantee of the work for one year after completion.
An executed Non-Collusive Bidding Certification shall accompany each proposal. Failure to provide this certification will result in not having the bid read. No Bidder may withdraw his bid for a period of 45 days after opening. The City of Olean reserves the right to reject any and all proposals, to waive technicalities, or re-advertise if the best interest of the City of Olean will be served thereby.
Under New York State Labor Law, contractors and subcontractors must pay the prevailing rate of wage and supplements (fringe benefits) to all workers under a public work contract. To access the PDF file of the prevailing rate schedule, click on https://apps.labor.ny.gov/wpp/publicViewProject.do?method=showIt&id=1569316 or you may find it online at the NYSDOL website utilizing the Prevailing Rate Case Number, which is PRC#
2024006217.
FRANK CAPUTO, CITY CLERK
DEPARTMENT OF PUBLIC WORKS
THE CITY OF OLEAN IS AN EQUAL OPPORTUNITY PROVIDER AND EMPLOYER.
mailto:dpwadmins@cityofolean.org mailto:bcamp@cityofolean.org https://apps.labor.ny.gov/wpp/publicViewProject.do?method=showIt&id=1569316
NOTICE TO CONTRACTORS
There will be a pre-bid meeting for this project on Monday, July 1st at 10am on the levee behind 639 N. Union St. Extension. Please contact Brad Camp, Water & Sewer Superintendent with any questions at (716) 376-5659 or bcamp@cityofolean.org
Background: The City of Olean experienced a failure of its sanitary sewer infrastructure when in March of 2023, a portion of the 15” sanitary sewer collapsed within the east bank levee structure of the Olean Creek.
Observations: The following conditions have been observed at the site.
a. There has been a sinkhole observed on both the inboard and outboard side of the levee that has been filled and temporarily patched with flowable fill.
b. The sanitary sewer main is completely collapsed and material isn’t able to be conveyed from the manhole, through the 101’ CMP section, and into the gate valve structure.
c. Prior to bypass pumping being established, there were sewer backups experienced by users on West St. Since bypass pumping has been established there have been no reported cases of sewer related issues.
Project Scope and Understanding: Please see that attached technical specifications.
Manufactured Materials: All manufactured materials furnished for the work shall be new, of good quality, and shall be accompanied by the manufacturer’s certification of conformance to the specifications. When materials are rejected, they shall be immediately removed from the site. In most cases only one brand or make of material, device or equipment is specified. Other brands or makes may be regarded as equal. Final acceptance of products not specified will be in the opinion of the Engineer in Charge. NO substitute for the named brands shall be ordered or installed without the approval of the Engineer in Charge who shall be the judge of equality.
Submittals: Before construction is started on any portion of the work, all shop and/or placing drawings pertaining to the portion of work shall have been submitted and approved by the Engineer in Charge.
Shop drawings include all drawings, diagrams, illustrations, brochures, catalog cut sheets, schedules and other data which are prepared by the contractor, subcontractor manufacturer, supplier or distributor and which illustrate the equipment or some portion of the work.
The Engineer in Charge may designate additional required shop drawings or material submittals. Shop drawings shall be submitted in a timely manner and in order to expedite approval or critical submittals, the Contractor should indicate on his submittal, his order of preference for the review, approval and return of shop drawings. All pages of submissions shall be properly identified to indicate location and function.
Publications in the form of catalogs and data sheets shall be marked to clearly define the specific product offered. The Engineer in Charge’s shop drawing review does not relieve the contractor from responsibility for deviations from contract documents unless he has, in writing, called the Engineer in Charge’s attention to a specific deviation requested at the time of submission. Nor does the approval of a shop drawing relieve them from responsibility for errors in the submission, for quality of materials and workmanship, nor for the other deviation from other requirements of the contract documents.
Under New York State Labor Law, contractors and subcontractors must pay the prevailing rate of wage and supplements (fringe benefits) to all workers under a public work contract. To access the PDF file of the prevailing rate schedule, click on https://apps.labor.ny.gov/wpp/publicViewProject.do?method=showIt&id=1569316 or you may find it online at the NYSDOL website utilizing the Prevailing Rate Case Number, which is PRC# 2024006217.
THE CITY OF OLEAN IS AN EQUAL OPPORTUNITY PROVIDER AND EMPLOYER.
TDD 711
mailto:bcamp@cityofolean.org https://apps.labor.ny.gov/wpp/publicViewProject.do?method=showIt&id=1569316
ACKNOWLEDGMENT OF RECEIPT OF ADDENDA
The undersigned acknowledges receipt of the following addenda to the subject project (if none, state “NONE”):
Addendum No. __________ Dated_______________
Receipt is hereby acknowledged for all addenda listed above.
Signature of Bidder ______________________________ Date________________
The undersigned having familiarized himself or themselves with the existing conditions of the project area affecting the cost of the work and with the Contract Documents and Plans, hereby submit the above bid for the proposed ________________________ in the City of Olean.
Dated: _________________________
Legal Name of Person, Firm or Corporation
By: ________________________________
Title: _______________________________
Street/Box number: ___________________
City State Zip
Lump Sum Bid Proposal
For the Olean Creek Levee Reconstruction and Sewer Replacement
The undersigned having familiarized themselves with the requirements of the proposal affecting the cost of the materials supplied and with the Contract Documents and Specifications, hereby submit the above lump sum bid for the proposed Olean Creek Levee Reconstruction and Sewer
Replacement project in the City of Olean.
Dated: _______________________________
Legal Name or Person, Firm or Corporation
By: ___________________________________
Title: __________________________________
Street or Box Number
City State Zip
Alt-1
TOTAL AMOUNT OF BID WRITTEN IN WORDS (BASE BID + ALT-1):____________________________________________
TOTAL BASE + ALT-1:____________________________________________
All work included in Alt-1 per plans and specifications: TOTAL ALT-1 BID
TOTAL AMOUNT OF Alt-1 BID WRITTEN IN WORDS (Alt-1 BID)
TOTAL AMOUNT OF BASE BID WRITTEN IN WORDS (BASE BID)
Item # Alternate Construction
Item #
All work included in Base Bid per plans and specifications:
Construction
TOTAL BASE BID
BID BOND
Accompanying this proposal is a Certified Check, Bid Bond, cash for the amount of
$_________________________; (5% of the total bid). In case this proposal shall be accepted by the Council, and the undersigned shall fail to execute the Contract, the moneys represented by such shall be regarded as liquidated damages and shall be forfeited and become the property of the City, otherwise to be returned to the depositor.
On acceptance of this proposal for said work, the undersigned does or do hereby bind himself or themselves to enter into a written Contract within 7 days of the date of notice of award, with the City, and to comply in all respect in relation to bond for faithful performance of the terms of said Contract.
Dated: _____________________________
Legal name of person or corporation
By_________________________________
The P.O. address of the bidder is:
_________________________________ (Street)
_________________________________ (City and Zip Code)
NON-COLLUSIVE BIDDING CERTIFICATION
BY SUBMISSION OF THIS BID OR PROPOSAL, THE BIDDER CERTIFIES THAT:
[1] This bid or proposal has been independently arrived at without collusion with any other bidder or with any competitor or potential competitor.
[2] This bid or proposal has not been knowingly disclosed and will not be knowingly disclosed, prior to the opening of bids or proposals for this project, to any other bidder, competitor or potential competitor.
[3] No attempt has been or will be made to include any other person, partnership or corporation to submit or not to submit a bid or proposal.
[4] The person signing this bid or proposal certifies that he fully informed himself regarding the accuracy of the statements contained in this certification, and under the penalties of perjury, affirms the truth thereof, such penalties being applicable to the bidder a well as to the person signing in its behalf.
BIDDER: ____________________________________
BY: ________________________________________
TITLE: ______________________________________
DATE: ______________________________________
REFERENCE SHEET
The apparent low bidder is required to complete this form providing three references of past performance. References should involve projects and/or service situations of similar size, scope and character of work to this Bid. References must have had dealings with the Bidder within the last thirty-six (36) months. The City reserves the right to establish the responsibility of the
Bidder before the actual award of the Bid and/or Contract. Completion of the Reference Form is required.
BIDDER’S NAME: _____________________________________________________________
DATE FILED: _________________________________________________________________
REFERENCE’S NAME: _________________________________________________________
ADDRESS: ___________________________________________________________________
TELEPHONE: _________________________ CONTACT PERSON: _____________________
REFERENCE’S NAME: _________________________________________________________
TELEPHONE: _________________________ CONTACT PERSON: _____________________
REFERENCE’S NAME: ________________________________________________________
TELEPHONE: ___________________________ CONTACT PERSON: ___________________
LEGAL STATUS INFORMATION
To Facilitate correct drawing and execution of contract, bidder shall supply full information concerning legal status:
FIRM NAME: _________________________________________________________________
PRINCIPAL OFFICE:
Street __________________________________________________________________
City, State, Zip ___________________________________________________________
Area Code _________________ Telephone _________________________
LOCAL OFFICE:
Street
City, State, Zip ___________________________________________________________
Area Code _________________ Telephone _________________________
CONTRACT TO BE SENT TO: Principal Office ______ Local Office ______
CHECK ONE: Corporation _______ Partnership _______ Individual _______
(Incorporated under the Laws of the State of _________________________________)
(If foreign corporation, state if authorized to do business in the State of New York:
Yes _______ No _______ Not Applicable _______)
TRADE NAMES: ____________________________________________________________
NAME AND ADDRESS OF PARTNERSHIP:
NAME, TITLE AND ADDRESS OF PERSON AUTHORIZED TO SIGN CONTRACT ON
BEHALF OF
BIDDER:
Name: __________________________________________________________________
Title: ________________________________________________________________
Address: ________________________________________________________________
PLEASE TYPE OR PRINT
GENERAL SPECIFICATIONS
The Standard Specifications for Construction and Materials of the New York State Department of
Transportation, Design and Construction Division, Dated May 1, 2016 are hereby made a part of these specifications as hereby amended or modified.
1.1 DEFINITION AND TERMS
Whenever the following abbreviations or terms are used, the intent and meaning shall be interpreted as follows:
Certificate of Compliance. A certificate provided by the manufacturer, producer or supplier of a product indicating actual results of test or analysis covering elements of the specification requirements and validated by certification.
Completion Date. The calendar date shown in the proposal on or before which the work contemplated under the contract shall be completed.
Contract Time. The number of calendar days shown in the proposal representing the time allowed for the completion of the work contemplated in the contract.
City. The City of Olean, its officers, and employees.
Council. The Common Council of the City of Olean.
Engineer. The Director of Public Works of the City of Olean or his authorized representative.
1.2 BIDDING REQUIREMENTS
1.2.1 Contents of Proposal Forms.
This form will state the location and description of the contemplated work and will show the estimate of the various quantities and kind of work to be performed or material furnished and will have a schedule of items for which unit bid prices are invited. The proposal form will state the time in which the work must be completed, the amount of the proposal guarantee and the date and hour after which proposals will no longer be received.
1.2.2 Interpretation of Quantities in Bid Schedule.
A schedule of quantities of work to be done or materials to be furnished is given in the proposal form.
Itemized quantities of work are to be considered as approximates and for the comparison of bids only.
The City does not expressly nor by implication agree that the actual quantities involved will correspond therewith; nor shall the bidder plead misunderstanding or deception because of such estimated quantities as to the character, location, or other conditions pertaining to the work. Payment to the contractor will be made for the actual quantities only of the work performed or materials furnished in accordance with the contract and it is understood that the scheduled quantities of work to be done or materials to be furnished may each be increased or diminished without in any way invalidating the bid.
1.2.3 Examination of Plans, Specifications, Special Provisions and Site of Work.
The bidder is required to examine carefully the work site, the proposal form, plans, specifications, supplemental specifications, special provisions and contract forms for the work contemplated. The submission of a proposal shall be considered conclusive evidence that the bidder has made such examination and is satisfied as to all the conditions and contingencies.
1.2.4 Preparation of the Proposal.
The bidder shall submit his proposal on the form furnished by the City. The proposal shall be executed properly and shall clearly specify a unit price in dollars and cents, in numerals, for each item listed therein, and shall also show in numerals in the column provided for that purpose the products of the respective unit prices and quantities and the total amount of the bid obtained by adding the amounts of the several items. In case of a conflict between a unit bid price and the corresponding extended amount, or in the absence of an extended amount, the unit bid price shall govern. All writing shall be with ink or typewriter, except the signature of the bidder, which shall be written with ink.
1.2.5 Proposal Guarantee
No proposal will be considered unless it is accompanied by a Certified Check payable to the City of
Olean for any amount not less than five (5) percent of the total sum bid, which check shall be duly certified by an incorporation bank or trust company, or in lieu of such certified check the bid is accompanied by a bid bond running to the City of Olean and executed by the bidder as principal and by a duly incorporated company authorized to guarantee the performance of contracts and to do business in the
State of New York as surety, in the penal amount of not less than five (5) percent of the bid conditioned that if the bid is accepted, the principal named in such bond will, whenever required, enter into a written contract for a performance of the work or improvement mentioned in such bid in accordance with terms and conditions as provided in the plans and specifications.
1.2.6 Delivery of Proposals.
Each proposal shall be, together with the proposal guarantee, in a sealed envelope, so marked as to indicate the name of the project to which it applies, and the name and address of the contractor. Proposals will be received at the place and until the hour on the date designated in the advertisement. When sent by mail, the sealed proposal marked as indicated above shall be enclosed in an additional envelope.
Proposals sent by mail, submitted in person or otherwise delivered must be in the hands of the official conducting the letting by the hour on the date designated in the advertisement. Proposals received after the time designated will be returned to the bidder unopened.
1.2.7 Withdrawal of Proposals.
Any bid may be withdrawn prior to the above scheduled time for the opening of bids or authorized postponement thereof.
1.2.8 Public Opening of Proposals.
Proposals will be opened and read publicly at the time and place indicated in the advertisement. Only the grand total amount of each proposal will be read. Bidders or their authorized agents are invited to be present.
1.2.9 Competency of Bidders.
Each bidder shall furnish, if requested by the engineer, satisfactory evidence of his financial ability, adequacy of plant, equipment and organization, prior experience, and any other pertinent and material facts requested.
1.2.10 Disqualification of Bidders.
Anyone or more of the following causes may be considered as sufficient for rejection of the bid(s):
- More than one proposal for the same work from an individual, partnership or corporation under the same name or different names.
- Evidence of collusion among bidders.
- Lack of responsibility as shown by past work for the City.
- Non-compliance with terms of previous or existing contracts.
- Uncompleted work which, in the judgment of the engineer, might hinder or prevent the prompt completion of additional work if awarded.
- Uncompleted work on which the actual time used has exceeded the contract time set therefore, or on which the performance or progress is not satisfactory in the judgment of the engineer.
1.3 AWARD AND EXECUTION OF CONTRACT
1.3.1 Consideration of Proposals.
The proposals received will be compared on the basis of the summation of the products of the quantities of work listed and the contract unit prices offered In case of discrepancy between the gross sum shown in the proposal and that obtained by adding the products of the quantities of work and the unit prices, the unit prices shall govern and any errors found in said products and summation shall be corrected.
The right is reserved to reject any or all proposals, to waive technicalities, to re-advertise for bids or to proceed to do the work otherwise, if in the judgment of the Council, the best interest of the City will be served thereby.
1.3.2 Award of Contract.
The award of contract, if it be awarded, will be to the lowest responsible bidder whose proposal complies with all the requirements necessary to render it formal.
Should no award be made within 45 days after the date of opening of proposals, the lowest responsible bidder may, upon the expiration of such period, request in writing that the award be made within a stipulated time, not less than ten (10) days exclusive of Sundays and holidays, after the date of the request. Should no award be made within the time so stipulated the bidder shall thereby be relieved of its obligation to execute a contract and contract bond.
1.3.3 Cancellation of Award.
The Council reserves the right to cancel the award of any contract at any time before the execution of said contract by all parties without liability against the City.
1.3.4 Return of Proposal Guarantee.
The proposal guarantees of all except the lowest responsible bidder will be returned promptly after the proposals have been checked and tabulated.
The proposal guarantee of the lowest responsible bidder will be returned as soon as the contract, contract bond, and other documents required to be filed by him have been properly executed and submitted in proper form to the City; provided, however, that in the event no award is made within the extended time stipulated by the lowest responsible bidder, as provided under Subsection 1.3.2 his proposal guarantee will be returned promptly upon expiration of such extended time.
1.3.5 Requirement of Contract Bond.
The successful bidder, at the time of submitting the contract for execution by the City, shall deposit with the City a good and sufficient surety bond for the full amount of the contract, such bond to be approved by the City, and to be executed by the bidder as principal and by a duly incorporated company authorized to guarantee the performance of contracts and to do business in the State of New York as surety conditioned for the faithful and complete performance of such contract in strict compliance with the plans and specifications, and also for the payment of all materials and services rendered in the execution of the contract and that any person or corporation furnishing such materials or rendering such services may maintain an action to recover for the same against the obligors in the bond, as though such person or corporation was named therein, provided the action is brought within one year of the time the cause of action accrued.
The contractor shall guarantee the work for a period of one year from the date of its completion and shall deposit with the City a good and sufficient surety bond for the full amount of the contract, such bond to be approved by the City, and to be executed by the contractor as principal and by a duly incorporated company authorized to guarantee such work, and to do business in the City of Olean as surety conditioned of said contractor will, at his own cost and expense, replace any work which has become defective.
The contractor shall replace any work during said guarantee as directed by the Engineer whenever and wherever required, and in the manner specified within five (5) days after written notice to that effect is served upon him, and in the event the contractor fails or refuses to comply with such notice, then the sureties of said bond will be notified and directed to proceed with such correction, such of said bond will be notified and directed to proceed with such correction, such notices to be served personally, or mailed to the last known address.
The contractor shall notify the engineer at least one day before making such corrections.
1.3.6 Execution of the Contract.
The contract shall be executed by the bidder and the contract bond shall be executed by the principal and the sureties and both shall be presented to the City within ten (10) days after the date of notice of the award of contract.
1.3.7 Failure to Execute Contract.
Failure on the part of the successful bidder to execute a contract and an acceptable contract bond, as provided in Subsection 1.3.6, will, at the discretion of the Council, be just cause for the annulment of the award and the forfeiture of the proposal guarantee to the City, not as a penalty but in payment of liquidated damages sustained as a result of such failure.
1.4 SCOPE OF WORK
1.4.1 Intent of Plans and Specifications.
The intent of the plans and specifications is to provide for the construction, execution, and completion of a complete work or improvement which the contractor undertakes to do in full compliance with the plans, specifications, supplemental specifications, special provisions and contract. The contractor shall perform all items of work covered and stipulated in the proposal and perform altered and extra work, all in accordance with the lines, grades, typical sections, dimensions given, and shall furnish, unless otherwise provided in the contract, all materials, implements, machinery, equipment, tools, supplies, transportation and labor necessary to the prosecution and completion of the work.
1.4.2 Increased or Decreased Quantities.
It is agreed and understood that the quantities of any items of work shown on the plans or in the proposals are subject to increase or decrease during the progress of the work. The engineer reserves the right to increase or decrease the quantities of any items of work as may be considered necessary or desirable to satisfactorily complete the construction. The quantity of any item(s) may vary without limitation or revision in the contract unit price due to such variation, and the actual quantity will be paid for at the contract unit price, or as otherwise specifically provided in the specifications, special provision or contract change order.
1.4.3 Omitted Items.
The right is reserved to omit from the work any item or portion thereof found unnecessary to the improvement and such omission shall not operate to waive any condition of the contract nor to invalidate any of the provisions thereof.
1.4.4 Extra Work.
In connection with the work covered by the contract, the Engineer may, at any time during its progress, order other work or materials incidental thereto. All such work and materials that do not appear in the proposal or contract as a specific item accompanied by a unit price and which are not included under the price bid for other items in the contract, shall be designated as Extra Work whenever it is deemed necessary or desirable by the engineer to complete the project as originally contemplated or as subsequently altered.
1.4.5 Barricades, Warning Signs and Flagmen.
The contractor shall furnish, erect and maintain traffic control devices and facilities, including flagging and guidance service in accordance with the provisions as set forth in the maintenance and protection of traffic unit item specification. Such work shall be measured and paid for as provided in said unit item.
All traffic control devices shall, unless otherwise specified, conform to the latest revision of Pad 350, Maintenance and Construction Traffic Control of the Manual of Uniform Traffic Control Devices of the
State Traffic Commission of the State of New York.
The contractor will be held responsible for all damages to the work due to failure of barricades, signs, lights, flagmen, and watchmen to protect it and, whenever evidence of such damage is found prior to acceptance, the Engineer may order the damaged portion immediately removed and replaced by the contractor at the contractor's own cost and expense.
1.4.6 Final Cleanup.
Upon completion of the work and before acceptance and final payment will be made, the contractor shall remove from the right-of-way, and to the extent he is responsible therefore from the adjacent property, all surplus and discarded materials, rubbish and temporary structures and leave the right-of-way in a neat and presentable condition. The contractor shall restore, at his own cost and expense, all existing work or work completed under previous contracts which has been damaged by his operations, in conformity with the specifications for the item or items involved.
1.5 CONTROL OF THE WORK.
1.5.1 Authority of the Engineer.
Work shall be done to the satisfaction of the engineer. He shall decide questions which arise as to quality and acceptability of the materials furnished, work performed, rate or progress of the work, interpretation of the plans and specifications, acceptable fulfillment of the contract, compensation and disputes and mutual rights between contractors under the specifications. He shall determine the amount and quantity of work performed and materials furnished, and his decision and estimate shall be final. The Contractor shall be responsible for compliance with pertinent local, State, and Federal regulations.
1.5.2 Conformity with Plans and Specifications.
All work performed and all materials furnished shall be in reasonably close conformity with the lines, grades, cross sections, dimensions and material requirements shown in the plans or indicated in the specifications. It shall be finished to produce quality work and appearance within limits of precision reasonably expected of good construction.
The contractor shall take no advantage of any apparent error or omission in the plan and specifications and the Engineer shall be permitted to make such corrections and interpretations as may be deemed necessary for the fulfillment of the intent of the plans and specifications.
1.5.3 Cooperation of the Contractor.
The contractor shall give the work the constant attention necessary to facilitate the progress thereof and shall cooperate with the engineer and with other contractors and utilities on or near the work in every way possible. The contractor shall have at all times during the progress of construction a competent superintendent or designated representative capable of reading and thoroughly understanding the plans and specifications, as his agent on the work, who can receive instruction from the engineer or his authorized representative. The superintendent or designated representative shall have full authority to execute the orders or directions of the engineer without delay and to supply promptly such materials, tools, plant, equipment and labor as may be required to properly perform the work.
1.5.3.A If at any time during the construction or reconstruction of any street, sewer project, water transmission line or project of this nature, a contractor completely abandons the work on a given street or area whether due to prior commitments or equipment breakdown, the contractor shall upon the direction of the engineer on the job, provide at the contractor's expense, ingress or egress for all residents to and from their respective properties. This shall include keeping the street itself completely passable and providing access in and out of each and every driveway.
1.5.4 Construction Stakes.
The engineer will furnish and set the construction survey stakes or reference points necessary to establish the alignment, slopes and profile grade for the work. These stakes and marks shall constitute the field control by and in accordance with which the contractor shall govern and execute the work. The contractor shall furnish free of charge additional stakes and other material necessary to the prosecution of the work after the work has started. The contractor shall be responsible for the preservation of all stakes and marks, and if any survey stakes or marks have been carelessly or willfully destroyed or disturbed by the contractor, the cost to the City of replacing them may be charged against him and be deducted from the payment of the work.
1.5.5 Inspection.
All materials and each part of detail of the work shall be subject at all times to inspection by the engineer or his authorized representative. Such inspection may include mill, plant, field, or shop inspection. The engineer or his representatives shall be allowed access to all parts of the work, and shall be furnished with such information and assistance by the contractor as is required to make a complete and detailed inspection.
1.5.6 Removal of Unacceptable Work.
Unacceptable work whether the result of poor workmanship, use of defective materials, damage through carelessness, or any other cause, found to exist prior to the final acceptance of the work, shall be immediately removed and acceptably replaced or otherwise satisfactorily corrected by and at the expense of the contractor.
1.5.7 Final Acceptance.
The engineer will make an inspection of the work included in the contract as soon as practicable after notification by the contractor that such work has been completed and final cleaning up performed. After corrections, if any are needed or made, the engineer will make a final inspection. After this final inspection, the engineer will, if fully satisfied with the work, notify the contractor in writing of his final acceptance. This final acceptance shall in no way reduce or absolve the obligations of the contractor under his one-year guarantee as provided in Subsection 1.3.5.
1.6 CONTROL OF MATERIALS.
1.6.1 Source of Supply and Quality.
The specifications contemplate the use of new, high quality materials throughout the work, except as may specifically be provided elsewhere in the specifications or on the plans.
In the case of materials obtained or produced from natural deposits, either commercially or by the contractor, the contractor shall obtain the engineer's preliminary approval of the source. The contractor shall furnish samples as required, representative of the material proposed for the work, in sufficient time to permit testing as necessary to establish a basis for approval. Such samples shall be obtained under the observation of, and with methods approved by the engineer.
1.6.2 Plant Inspection.
The engineer may undertake the inspection of materials at the plant, if he deems it necessary or desirable, or he may designate another agency for that purpose.
In the event plant inspection is undertaken, the following conditions shall be met:
- The engineer shall have the cooperation and assistance of the contractor and producer.
- The contractor shall give the engineer sufficient advance notice of production schedule to permit making necessary arrangements.
- Adequate safety measures shall be provided and maintained.
1.6.3 Samples and Tests.
To ascertain if materials comply with contract requirements, samples shall, at the discretion of the engineer, be taken at the source or at the job destination, and as often as the engineer deems it advisable or necessary. The contractor shall furnish without charge all samples required by the engineer and shall afford such facilities as may be required for collecting and forwarding them.
In lieu of making tests, the engineer may, at his discretion in the case of commercial products, accept the manufacturer's certified report of test or analysis or a certificate of compliance.
All tests shall be made in accordance with the methods described and designated herein or in the contract.
Unless otherwise designated, references to various standard specifications and test methods shall be understood to mean the specifications or test method, which is current on the date of advertisement for bids.
1.6.4 Defective Materials.
All materials which are not in reasonable close conformity with the requirements of the specifications shall be considered defective and shall be rejected. Rejected materials shall be removed from the site of the work unless otherwise permitted by the engineer.
1.7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
1.7.1 Laws to be Observed.
The contractor shall at all times observe and comply with all Federal and State Laws and administrative rules, local laws, ordinances and regulations which, in any manner, affect the conduct of the work and the safety of all workers, inspectors and the public at large.
1.7.2 Patented Materials, Devices and Processes.
It is mutually agreed and understood that without exception contract prices are to include all royalties and costs arising from patents, trademarks, and copyrights in any way involved in the work. The contractor and surety shall in all cases indemnify and save harmless the City from any and all claims for infringement by reason of the use of any patented device, design, material, or process to be involved in the contract and shall indemnify the City for any costs, expenses and damages which it may be obliged to pay, by reason of any such infringement at any time during the prosecution or after the completion of the work.
1.7.3 Public Convenience and Safety.
The contractor shall avoid as far as possible the maintenance of any condition which might be deemed at law to be an 'attractive nuisance'. Where such condition is unavoidable or where apparent or potential hazards occur incident to his conduct of the work, he shall maintain a property watch or provide other reasonable safeguards. The contractor and his surety shall be responsible for all damage, bodily injury, or death arising through his negligence either in maintaining an attractive nuisance or otherwise.
Fire hydrants shall be accessible at all times to the Fire Department. No material or other obstructions shall be placed within five feet of a hydrant.
1.8 PROSECUTION AND PROGRESS
1.8.1 Subletting or Assignment of Contract.
The contractor shall not sublet, transfer, assign or otherwise dispose of the contract or any portion thereof or of his right, title, or interest therein, without written consent of the City. Consent to sublet any portion of the contract shall not be construed to relive the contractor of any responsibility for the fulfillment of the contract or to release the contractor of his liability under the contract and bond.
1.8.2 Prosecution of the Work.
Unless otherwise provided in the special provisions, the contractor shall not begin the work to be performed under the contract before receiving written notification from the engineer to do so, and shall thereupon begin the work within ten days after the date of such written notice.
1.8.3 Character of Workmen.
The contractor shall at all times employ sufficient supervision and labor for prosecuting the several classes of work to full completion in the manner and time required by the contract.
Any person employed by the contractor or by any subcontractor who, in the opinion of the engineer, does not perform his work in a proper and skillful manner or is intemperate or disorderly shall, at the written request of the engineer, be removed forthwith by the contractor or subcontractor employing such person, and shall not be employed again in any portion of the work without the approval of the engineer.
1.8.4 Methods and Equipment.
The contractor shall provide and furnish the machinery, equipment and tools necessary to perform the work. These shall be in such condition and of such capacity as will produce work of satisfactory quality and complete it within the contract time.
1.8.5 Determination and Extension of Contract Time for Completion.
The time for completion of the work contemplated under the contract will be specified in the proposal either as a specific number of calendar days including Sundays and holidays, or as a given calendar date on or before which the work shall be completed. It is understood that the completion of the work within the time as specified is an essential part of the contract.
Contract time will be extended in an amount as is mutually agreed upon by the engineer and the contractor on the basis of contract change orders involving alterations in the contract affecting the prosecution of the work or involving extra or additional work.
Should the contractor find it impossible to complete the work on or before the time for completion as specified in the contract, or extended as set forth above, he may, at least ten (10) days prior to the date of completion as specified in the contract, make a written request to the Council for an extension of time, setting forth therein the reasons which he believes will justify the granting of his request. If the Council finds that the work was delayed because of conditions beyond the control of the contractor, it may grant an extension of time for completion in such amount as it finds to be warranted and justified.
1.8.6 Liquidated Damages.
Should the contractor fail to complete the work within the time agreed upon in the contract or within such extra time as may have been allowed by extensions, there shall be deducted from any monies due or that may become due the contractor, for each and every calendar day, including Sundays and holidays, that the work shall remain uncompleted a sum of $1,000.00.
1.9 MEASUREMENT AND PAYMENT
1.9.1 Measurement of Quantities.
The completed work will be measured for final payment by the engineer, as specified for the various items elsewhere in these specifications, to determine the quantities of such items of work performed, except when agreements have been made providing for compensation on the basis of plan quantities or when contract change orders have been executed providing for other methods of measurement. The methods of measurement and computations to be used in determination of quantities of material furnished and of work performed under the contract will be those methods generally recognized as conforming to good engineering practice. The contractor will be paid for the actual amount of work performed in accordance with the contract, as shown by the final measurements or upon the basis of plan quantities.
1.9.2 Partial Payments
Partial payments based on the value of the work performed or materials furnished, at contract or agreed unit or lump sum prices, will be made to the contractor as the work progresses, except that partial payments will not be made as long as the contractor fails to comply with any order given him by the engineer in accordance with the contract.
At least once each month the engineer will make and estimate of the quantities of work performed and the value thereof at contract or agreed unit or lump sum prices. The engineer may, upon presentation by the contractor receipted bills, freight bills or other satisfactory evidence of payment, include in the estimate prepared for partial payment the value of non-perishable materials which are to form a part of the completed work, produced or purchased, and delivered and stored in the vicinity of the work at such location where they will be available for ready incorporation into the work. The amounts paid for such materials shall go to reduce the amount of other partial or final payments due the contractor for the work performed as the materials are incorporated into the completed work.
From the total amount of the estimate there shall be deducted an amount equal to five (5) percent of the total amount of such estimate to be retained by the City until after completion of the entire contract and final acceptance of the work.
1.9.3 Acceptance and Final Payment.
When the project has been finally accepted as provided in Subsection 1.5.7, Final Acceptance, the engineer will prepare the final estimate of the quantities of the various classes of work performed. After review of such final estimate by the contractor, he will be paid the entire sum found to be due after deducting all previous payments and all amounts to be deducted under the provisions of the contract. All prior partial estimates and payments shall be subject to correction in the final estimate and payment.
1.9.4 Claims for Adjustment in Compensation.
Should the contractor deem that an adjustment in compensation is due him for work or materials not clearly covered in the contract or not ordered by the engineer as extra work, he shall notify the engineer in writing of his intention to make claim for such adjustment before he proceeds with the work involved in such claim.
Should the contractor fail to give the engineer written and timely notice of his intention of claim, an adjustment in compensation as herein before provided, and to afford the engineer the opportunity to investigate any changed conditions claimed before they are unduly disturbed, he thereby expressly waives such claim.
1.9.5 Payment to Contractor.
All material and work covered by partial payments made shall thereupon become the sole property of the owner, but this provision shall not be construed as relieving the contractor from sole responsibility for the care and protection of materials and work upon which payments have been made or the restoration of any damaged work, or as a waiver of the right of the owner to require fulfillment of all terms of the contract.
OWNER'S RIGHT TO WITHHOLD CERTAIN AMOUNTS AND MAKE APPLICATION THEREOF:
The contractor agrees that he will indemnify and save the owner harmless from all claims growing out of the lawful demands of subcontractors, laborers, workmen, mechanics, materialmen and furnishers of machinery and parts thereof, equipment, power tools, and all supplies, including commissary, incurred in the furtherance of the performance of this contract. The contractor shall, at the owner's request, furnish satisfactory evidence that all obligations of the nature hereinabove designated have to be paid, discharged, or waived. If the contractor fails to do so, then the owner may, after having served written notice on the said contractor, either pay unpaid bills, of which the owner has written notice, direct or withhold from the contractors unpaid compensation a sum of money deemed reasonably sufficient to pay any and all such lawful claims until satisfactory evidence is furnished that all liabilities have been duly discharged whereupon payment to the contractor shall be resumed, in accordance with the terms of this contract, but in no event shall the provisions of this sentence be construed to impose any obligation upon the owner to either the contractor or his surety.
In paying any unpaid bills for the contractor, the owner shall be deemed the agent of the contractor, and any payment so made by the owner, shall be considered as a payment made under the contract by the owner to the contractor, and the owner shall not be liable to the contractor for any such payment made in good faith.
1.9.6 Acceptance of Final Payment as Release.
The acceptance by the contractor of final payment shall be and shall operate as a release to the owner of all claims and all liability to the contractor for all things done or furnished in connection with this work and for every act and neglect of the owner and other relating to or arising out of this work. No payment, however, final or otherwise, shall operate to release the contractor or his sureties from any obligation under this contract or the Performance and Payment Bond.
The engineer shall have authority to make changes in quantities so that the units involved will fit actual existing conditions, otherwise no changes in the work shall be made without having prior written approval of the owner, without invalidating the contract, the owner acting only through the engineer, may order extra work or make changes by altering, adding to, or deducting from the work, the contract sum being adjusted accordingly. All the work of the kind bid upon shall be paid for at the unit price stipulated in the proposal. Any claim for extension of time caused thereby shall be adjusted at the time of ordering such change. Extra work not included in the contract unit prices shall be paid for as specified below:
(A) An agreed lump sum.
(B) The actual cost of:
1. Labor, including foreman;
2. Materials entering permanently into the work;
3. The ownership or rental cost of construction plant and equipment during the time of use on the extra work;
4. Power and consumable supplies for the operation of power equipment;
5. Insurance;
6. Social Security and old age and unemployment contributions;
To the cost under (B) there shall be added a fixed fee to be agreed upon but not to exceed fifteen (15) percent of the estimated cost of the work. The fee shall be compensation to cover the cost of supervision, overhead, bond, profit and any other general expenses.
No claim for extra work or cost shall be allowed unless the same was done in pursuance of a written order of the engineer.
1.9.7 Insurance Requirements.
Prior to award of contract the successful bidder shall supply copies of insurance certificates as follows:
1) Insurance covering claims under workers compensation, disability benefit and other similar employee benefit acts, against himself/herself or any of them, or by anyone for whose acts any of them may be liable.
2) Contractor's General Liability Insurance.
Each Occurrence $ 1,000,000
Damage to Rented Premises (each occurrence) $ 1,000,000
Medical Expense (any one person) $ 5,000
Personal & Adv. Injury $ 1,000,000
General Aggregate $ 2,000,000
Products - Comp/Op Agg $ 2,000,000
3) Automobile Liability Insurance:
Combined Single Limit (each accident) $ 1,000,000
4) Excess/Umbrella…
This is the start of the file's text. The full file is on GovTribe.