About this file

This is an electrical scope of work document for the Columbia School District in Michigan, outlining specifications for providing electrical power to athletic facilities. The project involves installing 110V electrical service to dugouts and a scoreboard, with varsity dugouts receiving two outlets each and all other dugouts receiving one outlet. The scope requires field verification of locations and dimensions with district representatives, installation of wire, conduit, dual plugs, boxes, and covers at all dugout locations, furnishing of all necessary permits and inspections, underground conduit installation from electrical panels to dugout locations, and complete trench backfilling. The contractor must coordinate with interfacing trades and comply with site drawings for all power installations.

Additional requirements include restoration of disturbed landscape areas with a minimum of four inches of topsoil and seed, mandatory notification to MISS DIG (811) at least three working days prior to construction commencement, investigation and protection of existing utilities with responsibility for any damage caused by contractor operations, and implementation of all required state and local erosion control measures. The contractor bears full responsibility for underground utility line backfill meeting surface requirements, compliance with site plan specifications for new concrete, and restoration of all landscape areas affected by construction activities.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Columbia School District

Bid Categories 02-26-01: Electrical

SCOPE SPECIFIC INCLUSIONS:

Provide Power to dugouts and scoreboard including but not limited to the following scope items:

1. Field verify location, layout, and dimensions with Columbia Central School District representative.

2. Perform, furnish and install 110V wire, conduit, dual plugs, boxes, and covers at all dugout locations. Varsity dugouts get two plugs and all others get one plug.

3. Provide all permits and inspections for this scope of work.

4. Provide continuous coordination with interfacing trade subcontractor work or other contractor categories as required to accomplish the work of this category.

5. Furnish and install complete power as indicated on site drawing.

6. Furnish and install conduit underground from panels to dugout locations.

7. Reference site plan for new concrete at location.

8. Provide all backfill of trenches for underground utility lines associated with this work scope. Backfill must meet the requirements for the above ground surfaces.

9. All disturbed landscape / grass areas shall be restored by the contractor by installing a minimum of 4” of topsoil and seed.

10. Contractor shall call MISS DIG (811) a minimum of three working days prior to the start of construction

11. Contractor shall investigate extent and location of existing utilities, and shall be responsible for protection and restoration of same if damaged as a result of the contractor’s operations

12. Contractor shall provide and maintain all erosion control measures required by the state and local governing authorities.