COE Public Safety Siding Upgrades - Addendum 5.pdf
PDF 173 KB Posted
- Solicitation number
- S-KE0010-00000916
- Issued by
- Lane County, Oregon
About this file
This document is an Addendum for the City of Eugene's Public Safety Facilities Siding Upgrades project. The addendum provides information on the anticipated timeline for the project, stating that active on-site work may begin as early as May 1, 2022, with the work expected to be Substantially Complete by August 31, 2022. The project includes the removal and replacement of exterior siding, windows, and associated flashings and trim on a portion of the existing Public Safety Training Building and existing Fire Station #2 in Eugene, Oregon, which falls under the jurisdictions of Lane County and the City of Eugene.
The contract opportunity is an Invitation to Bid (ITB) issued by the City of Eugene for the Public Safety Facilities Siding Upgrade project. The ITB does not provide any additional details on pricing terms, set asides, incumbents, funding requirements or sources, or other salient information beyond the project scope and timeline.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PIVOT Architecture 44 West Broadway Suite 300 Eugene, OR 97401 t.541.342.7291 f.541.342.1535 pivotarchitecture.com
ADDENDUM 05
Project: City of Eugene Public Safety Facilities Siding Upgrades
Date: November 12, 2021
From: Larry Banks
To: Interested Bidders
This Addendum modifies the Contract Documents and includes changes to the Project Manual, Specifications, and Drawings as follows:
General Information
1. The owner wishes to highlight the anticipated timeline for the project, as stated in Section 01 11 00 Summary of Work:
1.11 TIME OF COMPLETION
A. It is expected that the Work will be performed during Spring / Summer 2022. Active on-site work may begin as early as May 1, 2022, and the Work shall be Substantially Complete by August 31, 2022.
B. Limited access to the work area may be granted prior to May 1, 2022 for the purposes of site verification and field measurements as needed to prepare submittals and order materials.
C. Achieve Final Completion within 30 calendar days after Substantial Completion.
Changes to the Project Manual
2. none
Changes to the Drawings
3. none
End of Addendum #5