About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (DEP) for contract PL352 with F4 TECH (FORETECH Consulting, Inc.). The change order is dated December 18, 2017, and represents the third modification to the task assignment. The contractor is represented by Mark Milligan, and the DEP contract manager is Jim Singleton. The document modifies an existing indefinite delivery vehicle contract for resource management projects requiring evaluation, cost provision, and implementation services.
Change Order No. 3 extends the contract completion date by six months to June 30, 2018, and increases total funding from $12,000,000.00 to $12,650,000.00, representing a net increase of $650,000.00. The contract is structured as an all-inclusive fixed cost per unit and/or time and materials basis for services encompassing project evaluation and documentation development, fixed cost project implementation, post-implementation management, and project coordination. The original task amount was $5,000,000.00, with the task amount prior to this change order at $12,000,000.00. Funding sources are allocated across three organizational codes with amounts of $182,743.00, $221,858.00, and $245,399.00. The contractor may utilize subcontractors with a markup of up to five percent, and all costs must be approved by the DEP Task Manager or Contract Manager, with monthly invoicing based on hourly rates and fixed implementation costs.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .