CN-370000-PL352-T8CO1.pdf
PDF 1 MB Posted
- Contract number
- PL352
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection for contract PL352. The change order, dated December 1, 2016, modifies Task Assignment 8 between the Department and contractor F4 TECH, represented by Mark Milligan. The contract manager for the Department is Jim Singleton. The change order was approved by Budget Representative Johnson TT and Contractual Authority Clark G.
The change order increases funding for on-call services, ongoing scoping, and project administration from $150,000 to $325,000, representing a net increase of $175,000. Services include on-call staff availability for professional and technical support, discussion of contract-relevant topics, preparation of scopes of work and proposals, conduct of special projects and data requests, and administration of contract requirements. Deliverables include meeting minutes, monthly project progress reports from July 2016 through June 2017, and other written reports as assigned. Travel costs are capped at $5,000 and reimbursable expenses are limited to those outlined in the contract's Attachment B and F. Payment is made on a time and materials basis upon completion and acceptance of deliverables, with invoices submitted monthly. The task completion date remains June 30, 2017. Funding is allocated through Organization Code 3710-1000-000 with Object Code 139900 and Budget Entity 37100400 for fiscal year 080811/16.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .