Summary of Task Assignment Change Order
This is a Task Assignment Change Order Form (Change Order No. 2) issued by the Florida Department of Environmental Protection (DEP) for contract PL352 with F4 TECH, dated September 12, 2018. The change order modifies Task Assignment 17 under the existing contract, with Mark Milligan serving as the contractor representative and Jim Singleton as the DEP Contract Manager. The document reflects an amendment to increase funding and extend the completion timeline for on-call services, ongoing scoping, and project administration activities.
The change order increases the task funding from $150,000.00 to $300,000.00, representing a net increase of $150,000.00 in the Fee Schedule component. The funding is allocated from organizational code 3750-0500-000 under Budget Entity 37500300, Special Category 080039/18 for Fiscal Year 18. The original task completion date of June 30, 2018 was previously extended to June 30, 2019 under Change Order 1; this Change Order 2 maintains the June 30, 2019 completion date with no additional time extension. Services covered include on-call professional and technical services, meeting support, scope of work preparation, special projects and data requests, emergency response activities, debris removal and restoration following natural disasters, and project administration. Deliverables include meeting minutes, monthly progress reports, and other written reports as assigned. Payment is structured on a time and materials basis with hourly rates and fixed costs per unit, subject to monthly invoicing and performance reviews.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .