CN-370000-PL352-T16CO4.pdf
PDF 762 KB Posted
- Contract number
- PL352
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form (Change Order No. 4) issued by the Florida Department of Environmental Protection (FDEP) for Task Assignment Number 16 PL352, dated November 1, 2017. The contractor is F4 TECH, represented by Mark Milligan, with Jim Singleton serving as the FDEP Contract Manager. The change order was approved by Teresa T. Johnson (Budget Representative), David A Clark (Deputy Secretary), and Bob Wilson (Secretary).
The change order increases total contract funding by $1,292,317.00, raising the task amount from $3,700,000.00 to $4,992,317.00 to support Hurricane Irma cleanup and restoration activities under Mission #5071. The contractor will provide on-call professional and technical services including ongoing scoping, project administration, debris removal and monitoring, meeting coordination, preparation of scope of work documents, and emergency response assistance. Debris removal activities must address public interest objectives such as eliminating threats to life and safety, preventing property damage, supporting economic recovery, and mitigating risk through removal of substantially damaged structures. The contractor operates on a time and materials basis with payment based on hourly rates identified in Attachment B of the contract, supplemented by fixed per-unit implementation costs approved by FDEP. Monthly invoices are submitted upon completion and acceptance of deliverables, which include meeting minutes, monthly progress reports, and Hurricane Irma monitoring documentation. The task assignment term runs from execution through June 30, 2018, with travel reimbursement authorized in accordance with Florida Statutes Section 112.061 and Florida Department of Environmental Protection travel policies.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OOO-012 (Effective 10-13-2017) Page 1 of 4
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
Required Signatures: Adobe Signature
Task Assignment Number: __________________ Date: _______________ Change Order No.______________
Contractor Name: _________________________________________________________________
Contractor Representative: __________________________________________________________
DEP Contract Manager: _________ ___________
Description of Change (Use additional sheets if necessary):
Change in Task Amount
Item Cost Reimbursement Fee Schedule Total Original Task Amount:
Task amount prior to this change order:
Net increase/decrease in task amount:
Task amount with all change orders:
Change in Task Time
Original task completion date:
Completion date prior to this change:
Net increase/decrease in task period:
Completion date with all change orders:
16 PL352 11/1/2017 4
F4 TECH
Mark Milligan 850-309-3940
Jim Singleton 850-245-3085
Increased total funding $1,292,317.00 (from $3,700,000.00 to $4,992,317.00) for Hurricane Irma cleanup and restoration. Mission #5071
$0.00 $100,000.00 $100,000.00
$0.00 $3,700,000.00 $3,700,000.00
$0.00 +$1,292,317.00 +$1,292,317.00
$0.00 $4,992,317.00 $4,992,317.00
June 30, 2018 June 30, 2018 None June 30, 2018
OOO-012 (Effective 10-13-2017) Page 2 of 4
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
Change in Funding Information
Budget Entity Project # Grant # Org Code Fund Special Category
Object Code
EO Amount
Total:
CONTRACTOR FLORIDA DEPARTMENT OF
ENVIRONMENTAL PROTECTION
Contract Manager Date Contract Manager Date
APPROVED:
Budget Representative Date
Deputy Secretary Date
Secretary Date cc: Procurement Section (MS93) Bureau of Finance & Accounting (MS78) - 2 copies
37500300 SL002 FD073 3750-0100-999 423001 080039-16 139900 QK 529,838
37500300 SL002 FD073 3750-0100-999 423001 080039-17 139900 QK 515,255
37500300 SL002 FD073 3750-0100-999 423001 088130-15 139900 QK 183,559
37500300 SL002 FD073 3750-0100-999 423001 088130-16 139900 QK 63,665
1,292,317
Mark Milligan Digitally signed by Mark Milligan Date: 2017.11.08 08:20:56 -05'00'
Jim Singleton Digitally signed by Jim Singleton Date: 2017.11.08 08:03:57 -05'00'
Teresa T. Johnson Digitally signed by Teresa T.
Johnson Date: 2017.11.08 09:30:30 -05'00'
David A Clark Digitally signed by David A Clark Date: 2017.11.08 16:04:45 -05'00'
Bob Wilson Digitally signed by Bob Wilson Date: 2017.11.08 14:58:41 -05'00'
DEP Contract PL352, Task Assignment 16 Change Order 4, Page 3 of 4
PL352 TASK ASSIGNMENT 16
CHANGE ORDER 4
TASK DESCRIPTION
On-call Services, Ongoing Scoping, and Project Administration
1. TASK DESCRIPTION: The Department may, at any time during the period of this Task Assignment, utilize the Contractor for the following services, actions, and/or duties:
A. The Contractor agrees its staff will be available to the Department in an “on call” type relationship, where the Contractor provides professional or technical services to the Department as-needed to meet Department goals. This may include the use of subcontractors where necessary., B. Meet with Department staff to discuss topics relevant to the overall success of the Contract such as potential proposals, task assignments, and projects. Work may include meeting preparation, attendance, post-meeting assignments, preparation of meeting minutes, and travel. The Department has the ability to set various meeting location(s) around the State, and well as to utilize video, web, or tele-conferences with the Contractor.
C. Prepare written scope of work documents, proposals, and other supporting documents for new projects and supporting tasks.
D. Conduct special projects/tasks, respond to data and information requests, and prepare reports requested by the Department.
E. Administer and coordinate the services, actions, and/or tasks that support the management and completion of overall contract requirements.
F. Assist with emergency response activities as needed.
G. Assist with debris removal and restoration activities as a result of Hurricane Irma:
a. Debris includes but is not limited to vegetative debris, construction and demolition debris, sand, mud, silt, gravel, rocks, boulders, and vehicle and vessel wreckage.
b. Debris removal must be in the public interest and based on:
i. Eliminating immediate threat to lives, public health and safety;
ii. Eliminating immediate threats of significant damage to improved public or private property;
iii. Ensuring economic recovery of the affected community to the benefit of the community at large, or
iv. Mitigating risk to life and property by removing Substantially Damaged structures and associated structures and appurtenances.
c. Monitoring - Debris removal should include efforts to report debris types, quantities, reduction methods, and pickup and disposal locations. Contractor shall monitor all subcontracted debris operations at both loading and disposal sites and compile documentation such as load/dump tickets, monitoring reports, and photographs. GPS/GIS locations should also be provided.
2. DELIVERABLES: The Contractor will submit the following deliverables to the Department:
A. Meeting minutes. For each in-person, or conferenced meeting conducted F4 shall provide the Department with written documentation of meeting events in a format pre-approved by the Task or Contract Manager.
B. Monthly project progress reports. For each month, the Contractor shall prepare and produce a written report in narrative form which will document the status of all ongoing work related to the overall project / Contract.
C. Other written reports and electronic data supporting services assigned by the Department, i.e.- Hurricane Irma monitoring reports.
DEP Contract PL352, Task Assignment 16 Change Order 4, Page 4 of 4
3. TRAVEL: The Contractor shall be authorized to travel in order to support the services, actions, and tasks described above. Pursuant to Paragraph 8.A.4 of the subject contract, each traveler will complete a DEP Voucher for Reimbursement of Travel Expenses form and submit with receipts.
Reimbursement will be made in accordance with Section 112.061, Florida Statues (F.S.). The Contractor understands that no allowances shall be made for meals when travel is confined to the city or town of the official headquarters or immediate vicinity (within 15 miles of the city or town of the official headquarter) of the contracted personnel.
4. PERFORMANCE MEASURES: Each deliverable shall be reviewed by the DEP Task or Contract Manager to ensure that work was performed as specified above. This includes reports which will guide the implementation of the system.
5. FINANCIAL CONSEQUENCES: No payment will be made for unsatisfactory deliverables. In the event that a deliverable is deemed unsatisfactory, the Contractor shall re-perform the services needed for submittal of a satisfactory deliverable, at no additional cost to the Department within 15 consecutive days. If a satisfactory deliverable is not submitted within the specified time frame, the Department may, in its sole discretion, terminate the Contract for failure to perform, or implement other remedies as detailed in Section 12 of the Contract (PL352). The Department reserves the right to terminate any portion or all of a Task Assignment upon notice to Contractor.
6. COST: The Contractor shall conduct the work outlined herein on a time and materials basis for an initial amount not to exceed $4,992,317.00. In the event that costs are anticipated to exceed the identified amount, the Department will be notified as soon as possible in order to consider a change order.
Current Wage Rates for the Contractor are identified in Attachment B, Response Form of the Contract.
Any additional proposed costs must be reviewed and approved by the DEP Task or Contract Manager.
7. PAYMENT:
The Contractor shall submit itemized invoices to the Department on a monthly basis (unless otherwise agreed upon in advance for project implementation only) upon completion and acceptance of each task as identified in the Deliverables. Invoiced amounts will be based on the number of hours worked multiplied by the rates identified in Attachment B, Response Form of the Contract, as well as fixed rate per unit implementation cost(s) as approved by the Department.
Partial payments for work implemented shall be available to the Contractor. The amount of work accomplished and payment amount to invoice shall be measured or estimated by the DEP Field Representative and the Contractor, documented with signatures, and submitted as a part of the monthly Performance and Cost Report.
Payment will be made pursuant to Paragraphs 7, 8, and 9 of the Contract and any applicable addenda thereto.
Per Section 8, Invoicing Requirements, No. 9 (Retainage) of the Contract, the Department reserves the right to establish and apply Retainage on a Task Assignment.
8. REIMBURSABLES: Specific requirements concerning reimbursable items are detailed in at least three (3) areas of the Contract:
A. Paragraph 8;
B. Attachment B (Response Form); and C. Attachment F (Contract Payment Requirements).
9. TERM: This task assignment shall begin upon execution and terminate June 30, 2018, unless the Department earlier terminates contract PL352 or this task assignment.
| TA16 CO4 - PL352 signature page v2 |
| TA16 CO4 - PL352 v2 |