Document Summary

This is a Task Assignment Notification Form for contract HW559, issued by the Florida Department of Environmental Protection (FDEP) to AMEC Environment & Infrastructure for a CERCLA Site Inspection at Duval Plating & Supply located at 2161 Commonwealth Avenue, Jacksonville, Duval County, Florida. The document package includes a cost proposal dated March 10, 2017, with project management led by Jim McCarthy and Ron White (Principal Engineer/Scientist). The task assignment encompasses four subtasks: Project Management (SubTask 1), Logistics (SubTask 2), Site Inspection Fieldwork (SubTask 3), and Site Inspection Report (SubTask 4).

The total contract value is fixed at $20,643.08 with no fee schedule, cost reimbursement, or additional fixed fees. The invoice schedule allocates $13,681.99 for Subtasks 2 and 3 (Logistics and Site Inspection Fieldwork) and $6,961.09 for Subtasks 1 and 4 (Project Management and Site Inspection Report). The scope of work includes soil sampling of 11 borings with 22 samples and concrete coring, installation of 4 temporary monitoring wells with abandonment, groundwater sampling, and survey work. The cost estimate includes 150 total labor hours across multiple technical staff categories, travel expenses, subcontractor costs for direct push technology drilling ($2,680.00) and sample containers ($272.20), laboratory shipping ($586.00), and field equipment rental. The final deliverable is a Site Inspection Report due August 15, 2017, with the task execution period extending through August 22, 2017.

View the file

Other files

File Type Posted
CN-370000-HW559-A9.pdf PDF
CN-370000-HW559-BF005E.pdf PDF
CN-370000-HW559-BF007B.pdf PDF
CN-370000-HW559-BF01A.pdf PDF
CN-370000-HW559-BF05BCO2.pdf PDF
CN-370000-HW559-BF06BCO2.pdf PDF
CN-370000-HW559-BF06CCO1.pdf PDF
CN-370000-HW559-BF11B.pdf PDF
CN-370000-HW559-BF593B.pdf PDF
CN-370000-HW559-BF594A.pdf PDF
CN-370000-HW559-BF594DC3.pdf PDF
CN-370000-HW559-BF7BCO3.pdf PDF
CN-370000-HW559-BF8ACO2.pdf PDF
CN-370000-HW559-BF8BCO3.pdf PDF
CN-370000-HW559-CSS-23B.pdf PDF
CN-370000-HW559-CSS-24A.pdf PDF
CN-370000-HW559-CSS-25B.pdf PDF
CN-370000-HW559-CSS010A.pdf PDF
CN-370000-HW559-CSS04D.pdf PDF
CN-370000-HW559-CSS07B.pdf PDF
CN-370000-HW559-CSS10C.pdf PDF
CN-370000-HW559-CSS15A.pdf PDF
CN-370000-HW559-CSS15B.pdf PDF
CN-370000-HW559-CSS15BC1.pdf PDF
CN-370000-HW559-CSS20A-1.pdf PDF
CN-370000-HW559-CSS24A-1.pdf PDF
CN-370000-HW559-CSS29A.pdf PDF
CN-370000-HW559-DC007H.pdf PDF
CN-370000-HW559-DC009B.pdf PDF
CN-370000-HW559-DC02BCO2.pdf PDF
CN-370000-HW559-DC02BCO3.pdf PDF
CN-370000-HW559-DC02FCO1.pdf PDF
CN-370000-HW559-DC02FCO2.pdf PDF
CN-370000-HW559-DC02G.pdf PDF
CN-370000-HW559-DC02HCO2.pdf PDF
CN-370000-HW559-DC02i.pdf PDF
CN-370000-HW559-DC03B.pdf PDF
CN-370000-HW559-DC04BC02.pdf PDF
CN-370000-HW559-DC05A.pdf PDF
CN-370000-HW559-DC06A.pdf PDF
CN-370000-HW559-DC06B.pdf PDF
CN-370000-HW559-DC06GCO4.pdf PDF
CN-370000-HW559-DC06HCO2.pdf PDF
CN-370000-HW559-DC06J.pdf PDF
CN-370000-HW559-DC06JCO2.pdf PDF
CN-370000-HW559-DC06KCO2.pdf PDF
CN-370000-HW559-DC07BCO1.pdf PDF
CN-370000-HW559-DC08ACO2.pdf PDF
CN-370000-HW559-DC08C.pdf PDF
CN-370000-HW559-DC08DCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

McCarthy, Jim

From: White, Ron D. <Ron.White@amecfw.com> Sent: Friday, March 10, 2017 1:25 PM To: McCarthy, Jim Subject: Duval Plating Draft Work Plan & Cost Proposal Attachments: Duval Plating SI CP.pdf; Duval Plating SI WP Draft 3.10.17.docx; 2017-03-09_SIW_FIG-1.pdf;

2017-03-10_SIW_FIG-2.pdf; 2017-03-10_SIW_FIG-3.pdf; 2017-03-10_SIW_FIG-4.pdf

Jim

Please find attached the draft SI work plan and the cost proposal for Duval Plating. I have also attached the proposed figures

I will be in the office next Monday & Tuesday next week and will be out Weds thru Friday on Spring Break. Let me know if you have any questions

Thanks

Ron

Ronald D. White, P.G. | Associate Scientist

AMEC Foster Wheeler plc 2533 Greer Road, Suite 6 Tallahassee, Florida 32308 O 850.656.1293 D 850.298.7715 M 850.443.2341 E ron.white@amecfw.com amecfw.com

This message is the property of Amec Foster Wheeler plc and/or its subsidiaries and/or affiliates and is intended only for the named recipient(s). Its contents (including any attachments) may be confidential, legally privileged or otherwise protected from disclosure by law. Unauthorised use, copying, distribution or disclosure of any of it may be unlawful and is strictly prohibited. Amec Foster Wheeler plc, its subsidiaries and affiliates assume no responsibility to persons other than the intended named recipient(s) and do not accept liability for any errors or omissions which are a result of email transmission. If you have received this message in error, please notify us immediately by reply email to the sender and confirm that the original message and any attachments and copies have been destroyed and deleted from your system.

FDEP COST ESTIMATE - HW559

Contractor: Amec Foster Wheeler

Date: 3/10/2017

Task #: SubTask 1

Site: Duval Plating & Supply SubTask 2

Activity/Phase: SubTask 3 Site Inspection Fieldwork

Project Manager: Jim McCarthy / RonWhite SubTask 4 Site Inspection Report

SubTask 5

Totals 1 2 3 4 5

Labor Rate Category

$43.59 Project Manager 13 13.2

$36.45 Program Manager 0 0 0 0 0

$43.59 Project Manager 0 0 0 0 0

$63.28 Consulting Eng/Sci EB 2 0 0 2 0

$43.59 Principal Eng/Sci RW 60 8 24 28 0

$43.59 Senior Scientist 0 0 0 0 0

$42.79 Senior Engineer 0 0 0 0 0

$28.44 Project Engineer 0 0 0 0 0

$24.49 Project Scientist 0 0 0 0 0

$26.00 Project Scientist 0 0 0 0 0

$22.60 Staff Scientist PB 32 0 24 8 0

$35.63 Technical Editor 0 0 0 0 0

$24.59 Construction Supervisor 0 0 0 0 0

$18.78 O&M Specialist 0 0 0 0 0

$25.53 Drafter 12 0 0 12 0

$27.54 Senior Technician PC 27 3 24 0 0

$25.57 Senior Technician 0 0 0 0 0

$17.63 Project Assistant RP 3 1 0 2 0

$14.02 Field Technician 0 0 0 0 0

$22.61 Project Accountant 0 0 0 0 0

$23.87 Contracts/Purchasing AB 1 1 0 0 0

$12.15 Clerical 0 0 0 0 0

$17.63 Word Processing 0 0 0 0 0

Total Hours 150 13 13 72 52 0

Direct Labor $5,165.84 $573.98 $472.84 $2,249.52 $1,869.50 $0.00

Overhead 111.08% $5,738.22 $637.58 $525.23 $2,498.77 $2,076.64 $0.00

Gen & Admin 8.36% $431.86 $47.98 $39.53 $188.06 $156.29 $0.00

Fringe 35.00% $1,808.04 $200.89 $165.49 $787.33 $654.33 $0.00

Total Labor $13,143.96 $1,460.43 $1,203.09 $5,723.68 $4,756.76 $0.00

Other Direct Costs $258.30 $28.70 $23.64 $112.48 $93.48 $0.00

Travel

Vehicle Rental $388.00 $0.00 $388.00 $0.00 $0.00

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00

Air Fare $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $546.00 $0.00 $546.00 $0.00 $0.00

Total Travel $934.00 $0.00 $934.00 $0.00 $0.00

Subcontractor (Equipment Procurement)

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00

Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00

Drilling (Non-conventional) $2,680.00 $0.00 $2,680.00 $0.00 $0.00

Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00

Surveying $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00

Sample Containers $272.20 $0.00 $272.20 $0.00 $0.00

Subcontractor Subtotal $2,952.20 $0.00 $2,952.20 $0.00 $0.00

Handling Fee $295.22 $0.00 $295.22 $0.00 $0.00

Total Subcontractor Cost $3,247.42 $0.00 $3,247.42 $0.00 $0.00

Project Management

Logistics

CERCLA Site Inspection

REV: 02/11 AMEC Page 1

FDEP COST ESTIMATE - HW559

Contractor: Amec Foster Wheeler

Date: 3/10/2017

Task #: SubTask 1

Site: Duval Plating & Supply SubTask 2

Activity/Phase: SubTask 3 Site Inspection Fieldwork

Project Manager: Jim McCarthy / RonWhite SubTask 4 Site Inspection Report

SubTask 5

Totals 1 2 3 4 5

Project Management

Logistics

CERCLA Site Inspection

Laboratory

Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $586.00 $0.00 $586.00 $0.00 $0.00

Total Laboratory $586.00 $0.00 $586.00 $0.00 $0.00

Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00

Expendables $65.00 $0.00 $65.00 $0.00 $0.00

Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Other) $1,094.00 $0.00 $1,094.00 $0.00 $0.00

Total Field Expenses $1,159.00 $0.00 $1,159.00 $0.00 $0.00

Subtotal $19,328.68 $1,489.13 $1,226.73 $11,762.58 $4,850.24 $0.00

Completion Fee $1,314.40 $146.04 $120.31 $572.37 $475.68 $0.00

Total Estimated Cost $20,643.08 $1,635.17 $1,347.04 $12,334.95 $5,325.92 $0.00

REV: 02/11 AMEC Page 2

SITE :

SUBTASK 2

DATE: 3/10/2017

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager

Consulting Eng/Sci

Principal Eng/Sci

Senior Scientist RW 8

Senior Engineer

Project Engineer

Project Scientist

Staff Engineer

Staff Scientist

Technical Editor

Construction Supervisor

O&M Specialist

Drafter

Senior Technician PC 3

Engineering Tech

Project Assistant (RP) 1

Field Technician

Project Accountant (AB) 1

Contracts/Purchasing

Clerical

Word Processing

13TOTAL LABOR

Project Invoicing

Decon, equipment staging

Duval Plating & Supply

Logistics

Project setup / Purchase Orders with Subcontractors

Planning/coordination, Utility Locates, Scribe Setup

SITE : Duval Plating & Supply

SUBTASK 3 Site Inspection Fieldwork

DATE: 3/10/2017

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Principal Scientist RW

RW

RW

RW Survey TOC & GW survey

RW

RW 24

Staff Scientist PB

PB

PB

PB Survey TOC & GW survey

PB 24

Senior Technician PC

PC

PC

PC Survey TOC & GW survey

PC 24

EQUIPMENT ITEM RATE COSTING UNIT USAGE TOTALS

MW Installation Kit $737.20 week 0 $0.00

$184.30 day 1 $184.30

Shallow GW Sampling Kit $834.20 week 0 $0.00

$208.55 day 1 $208.55

Soil Sampling Kit $834.20 week 0 $0.00

(thru concrete) $208.55 day 1 $208.55

Hand Augers $33.00 week 0 $0.00

$8.25 each 22 $181.50

Peristaltic Pump $116.40 week 0 $0.00 extra pump $29.10 day 1 $29.10

HDPE Tubing $0.25 per foot 0 $0.00

Teflon Tubing $1.95 per foot 100 $195.00

Silicon Tubing $2.00 per foot 10 $20.00

GPS $101.00 week 0 $0.00

$25.25 day 1 $25.25

Level and Rod $167.00 week 0 $0.00

$41.75 day 1 $41.75

$1,094.00

Round trip travel to Jacksonville, Florida

Soil sampling 11 borings (22 samples) & concrete coring

Install 4 temporary micro-wells & abandonment

GW Sampling - 4 monitoring wells

Scribe

Round trip travel to Jacksonville, Florida

TOTAL LABOR

Soil sampling 11 borings (22 samples) & concrete coring

Install 4 temporary micro-wells & abandonment

GW Sampling - 4 monitoring wells

Install 4 temporary micro-wells & abandonment

GW Sampling - 4 monitoring wells

Soil sampling 11 borings (22 samples) & concrete coring

Round trip travel to Jacksonville, Florida

TOTAL EQUIPMENT

PPE Level D H&S $28.00 (3 person x 2 days) 6 TOTAL PPE $168.00

VEHICLE TYPE RATE UNIT USAGE

Automobile $272.00 week 0 $0.00

$68.00 day 0 $0.00

$420.00 week 0 $0.00

2 vans $97.00 day 4 $388.00

Truck $420.00 week 0 $0.00

$97.00 day 0 $0.00

$388.00

PER DIEM STAFF RATE UNIT USAGE

motel 3 $110.00 day 1 $330.00 meal 3 $36.00 day 2 $216.00 motel $110.00 day 0 $0.00 meal $36.00 day 0 $0.00

$546.00

SHIPPING ITEM RATE COSTING UNIT UNITS

Small - 0 to 25 LBS (for cooler return) $35.00 2 Day 4 $140.00

Large - 25 to 50 LBS Samples to lab $104.00 Overnight 4 $416.00

Ice $5.00 per cooler 6 $30.00

TOTAL SHIPPING $586.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Probe Domain DPT Well Installation $2,680.00

AEL Sample Containers $272.20

TOTAL $2,952.20

SUPPLIES ITEM RATE COSTING UNIT UNITS TOTALS

Expendables $32.50 per day 2 $65.00

$0.00 lump $0.00

$0.00 each $0.00

TOTAL SUPPLIES $65.00

TOTAL VEHICLE

TOTAL PER DIEM

Equipment Van

SITE : Duval Plating & Supply

SUBTASK 4 Site Inspection Report

DATE: 3/10/2017

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE HOURS

Prog. Manager 28

Principal Eng/Sci 2

Sr. Eng/Sci

Contracts/Purchasing

Eng/Sci/Geol 8

Project Accountant

Sr. Technician (PC)

Technician/Draftsperson 12

Associate Eng/Sci

Clerical/Word Processing

Project Assistant 2

TOTAL LABOR 52

WORK DESCRIPTION

Prepare SIR, data entry, revise two drafts

Review SIR

Format and edit report, prepare .PDF copy of report

Prepare logs and tables for SIR

Prepare figures