This document package comprises Task Assignment Change Orders and supporting correspondence for contract HW559, issued by the Florida Department of Environmental Protection (FDEP) to Wood Environment & Infrastructure Solutions, Inc. The contract pertains to operation and maintenance (O&M) activities at the Ponte Vedra Cleaners facility (ERIC_5404) located in Ponte Vedra Beach, St. Johns County, Florida. The documents include Change Orders 3 and 4, negotiation summaries, and utility billing records from Beaches Energy Services, with project management oversight provided by FDEP Contract Manager Crystal Posey and contractor representative Ron White.

The task assignment (DC006G) covers quarterly O&M documentation, semi-annual reporting, and utility cost reimbursement for the facility. Change Order 3, dated June 2019, authorized additional utility costs totaling $770.00 for June 2019 activities, extending the completion date to August 30, 2019. Change Order 4, finalized September 30, 2019, reduced utility costs to actual invoiced amounts and extended the final completion date to November 30, 2019 to allow additional time for review and invoicing. The cumulative task cost across all change orders is $19,003.11, consisting of $16,540.57 in fixed price services, $2,482.64 in cost reimbursement, and a $60 utilities handling fee. Deliverables include FDEP-approved quarterly O&M documentation with field notes and logs, semi-annual O&M reports, ADaPT/GIS electronic submissions, and utility invoices covering the period December 2018 through June 2019.

View the file

Other files

File Type Posted
CN-370000-HW559-A2.pdf PDF
CN-370000-HW559-A3.pdf PDF
CN-370000-HW559-A5.pdf PDF
CN-370000-HW559-A6.pdf PDF
CN-370000-HW559-BF05BCO1.pdf PDF
CN-370000-HW559-BF05ECO1.pdf PDF
CN-370000-HW559-BF06B.pdf.crdownload CRDOWNLOAD file
CN-370000-HW559-BF06BCO1.pdf PDF
CN-370000-HW559-BF06C.pdf PDF
CN-370000-HW559-BF07B.pdf PDF
CN-370000-HW559-BF07D.pdf PDF
CN-370000-HW559-BF09BCO1.pdf PDF
CN-370000-HW559-BF4F.pdf PDF
CN-370000-HW559-BF591A.pdf PDF
CN-370000-HW559-BF594B.pdf PDF
CN-370000-HW559-BF594C-1.pdf PDF
CN-370000-HW559-BF594C.pdf PDF
CN-370000-HW559-BF59C.pdf PDF
CN-370000-HW559-BF7BCO2.pdf PDF
CN-370000-HW559-BF8A.pdf PDF
CN-370000-HW559-CSS04C.pdf PDF
CN-370000-HW559-CSS04D.pdf.crdownload CRDOWNLOAD file
CN-370000-HW559-CSS05C-3.pdf PDF
CN-370000-HW559-CSS05C.pdf PDF
CN-370000-HW559-CSS06C.pdf PDF
CN-370000-HW559-CSS09B.pdf PDF
CN-370000-HW559-CSS12A-1.pdf PDF
CN-370000-HW559-CSS12A.pdf PDF
CN-370000-HW559-CSS16A-1.pdf PDF
CN-370000-HW559-CSS16A.pdf PDF
CN-370000-HW559-CSS17A-1.pdf PDF
CN-370000-HW559-CSS17A-2.pdf PDF
CN-370000-HW559-CSS17A.pdf PDF
CN-370000-HW559-CSS18A-2.pdf PDF
CN-370000-HW559-CSS19A.pdf PDF
CN-370000-HW559-CSS20A.pdf PDF
CN-370000-HW559-CSS21A.pdf PDF
CN-370000-HW559-CSS22A.pdf PDF
CN-370000-HW559-CSS23C.pdf PDF
CN-370000-HW559-CSS24A.pdf PDF
CN-370000-HW559-CSS25A.pdf PDF
CN-370000-HW559-CSS26B.pdf PDF
CN-370000-HW559-CSS27A.pdf PDF
CN-370000-HW559-CSS28A.pdf PDF
CN-370000-HW559-CSS28B.pdf PDF
CN-370000-HW559-DC006D.pdf PDF
CN-370000-HW559-DC006E.pdf PDF
CN-370000-HW559-DC008D.pdf PDF
CN-370000-HW559-DC02A.pdf PDF
CN-370000-HW559-DC02BCO5.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number: HW559 Task Assignment #: DC006G

Change Order #: 4

Deliverables:

Deliverable Deliverable Due Date Subtask 2: FDEP approval of documentation of quarterly O&M activities including field notes and O&M logs (submitted electronically)

Completed

Subtasks 1 and 3: FDEP approval of documentation of quarterly O&M activities including field notes and O&M logs AND Semi- Annual O&M Report (submitted electronically along with one hard copy) AND ADaPT/GIS electronic deliverables

Completed

Submittal of utility invoices (December 2018 to February 2019) Completed

Submittal of utility invoices (March to June 2019) Completed

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

Subtask 2: FDEP approval of documentation of quarterly O&M activities (December 2018 to February 2019) including field notes and O&M logs (submitted electronically); Previously Invoiced

$5,816.89

Subtasks 1 and 3: FDEP approval of documentation of quarterly O&M activities (March to May 2019) including field notes and O&M logs AND Semi-Annual O&M Report (submitted electronically along with one hard copy) AND ADaPT/GIS electronic deliverables

$10,583.68

Subtask 4: FDEP approval of utility invoices for 3 months (December 2018 to February 2019); Utilities (Cost Plus Fixed Fee) = not to exceed $1,213.28; Utilities Handling Fee = $60;

Previously Invoiced

$1,273.28

Subtask 5: FDEP approval of utility invoices for 3 months (March to June 2019); Utilities (Cost Plus Fixed Fee) = not to exceed $1,269.26; Utilities Handling Fee = $60; Previously Invoiced

$1,329.26

TOTAL COST $19,003.11

BWC TAFORM 01_18

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Noah Valenstein Secretary

Memorandum

TO:

FROM:

SUBJECT:

DATE:

HW559 Contract Negotiation File Ponte Vedra Cleaners

ERIC_5404

Crystal Posey, Project Manager

Negotiation Summary

HW559 DC006G TACO 4

September 30, 2019

This Task Assignment Change Order authorizes a reduction in the utility costs for Subtask 5 to the actual invoiced amount and extends the completion date to allow additional time for review and invoicing, as requested in the attached Wood memo, dated September 27, 2019.

The total task amount with all change orders is $19,003.11 and the task completion date is now November 30, 2019.

Wood may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment.

Posey, Crystal

From: White, Ron D. <ron.white@woodplc.com> Sent: Friday, September 27, 2019 11:06 AM To: Posey, Crystal Cc: Peck, Renee L Subject: RE: DC006G ST3 Report/Deliverable - Request for Date Extension

Crystal

I meant to mention, could you please copy Renee on the email if the TACO is sent today? I will not be here after lunch

Thanks Ron

Ron White, P.G.

Associate Geologist 1441 Maclay Commerce Drive, Suite 102 Tallahassee, Florida 32312 Direct: +1 (850) 298-7715 Mobile: +1 (850) 443-2341 www.woodplc.com

From: White, Ron D.

Sent: Friday, September 27, 2019 11:03 AM To: Posey, Crystal <Crystal.Posey@FloridaDEP.gov> Cc: Peck, Renee L <renee.peck@woodplc.com> Subject: DC006G ST3 Report/Deliverable ‐ Request for Date Extension

Good morning Crystal

The TA for this task expires on Monday 9/30/19. Since this report is still in the review process by FDEP, and to allow time to address comments and submit an invoice for the work, Wood respectfully requests a date extension for this TA to allow time to complete these tasks. The deliverable for this task was submitted on June 30, 2019.

Thanks Ron

Ron White, P.G.

Associate Geologist 1441 Maclay Commerce Drive, Suite 102 Tallahassee, Florida 32312 Direct: +1 (850) 298-7715 Mobile: +1 (850) 443-2341 www.woodplc.com