This document is a Task Assignment Notification Form under Florida Department of Environmental Protection (FDEP) Contract No. HW559, issued to Wood Environment and Infrastructure Solutions, Inc. (Wood), a contractor providing environmental services to the state. The task assignment pertains to well abandonment activities at the Mr. Dryclean site located at 700 Blanding Boulevard, Orange Park, Clay County, Florida (ERIC Site #4259). David Meyers, P.G., serves as the DEP Contract Manager, with Ron White representing Wood as the contractor representative. The assignment was executed on May 13, 2021, and is authorized under the WCP indefinite delivery contract vehicle.
The task assignment authorizes Wood to conduct well abandonment activities and prepare a Well Abandonment Report in accordance with Wood's scope of work and cost estimate revised on May 12, 2021. The work encompasses three subtasks: Project Management, Well Abandonment Activities (oversight of 11 micro-wells and three MAGS wells including concrete pad removal and restoration), and preparation of a Well Abandonment Report. Field notes with photographs are due June 30, 2021, with the final Well Abandonment Report due August 27, 2021. The total task assignment value is $4,978.93 on a fixed-price basis, with no retainage, cost reimbursement, or fee schedule components. Invoice payments are contingent upon FDEP approval of deliverables: $4,080.58 upon approval of field work documentation (Subtask 2) and $898.35 upon approval of the Well Abandonment Report and project management (Subtasks 1 and 3). Well abandonment activities will be performed by RNA Consulting Group, a licensed well driller, as a subcontractor to Wood.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW559
D000 NADC007H
Wood Environment and Infrastructure
Ron White
850-245-8945David Meyers, P.G.
ERIC_4259
Mr. Dryclean
700 Blanding Blvd, Orange Park, Clay County
Well Abandonment
This Task Assignment authorizes Wood to conduct well abandonment activities at the Mr. Dryclean site and prepare a Well Abandonment Report, in accordance with the Wood scope of work and cost estimate form received on April 20, 2020, revised and resubmitted by Wood on May 12, 2021.
Field Notes w/ Photographs, Well Abandonment Report
06/30/2021
08/27/2021
$ 4,978.93 $ 0.00 $ 0.00 $ 0.00
$ 0.00
David S. Meyers Digitally signed by David S. Meyers Date: 2021.05.13 09:52:17 -04'00'
David S. Meyers Digitally signed by David S. Meyers Date: 2021.05.13 09:52:38 -04'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2021.05.13 11:13:17 -04'00'
Digitally signed by Geoffrey Schaefer Date: 2021.05.14 10:36:02 -04'00'
$ 4,978.93
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtask 2: Documentation of completion of field work including field notes and photos. 06/18/2021
Subtask 1 and 3: Well Abandonment Report; Project Management 06/30/2021
FDEP approval of Documentation of completion of field work including field notes and photos - Subtask 2 $ 4,080.58
FDEP approval of Well Abandonment Report; Project Management - Subtask 1 and 3 $ 898.35
$ 4,978.93
HW559
DC007H
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Noah Valenstein Secretary
Memorandum
TO: HW559 Contract File FROM: David Meyers, Project Manager SUBJECT: Mr. Dryclean; DC007H; Well Abandonment DATE: May 12, 2021
This Task Assignment authorizes Wood to conduct well abandonment activities at the Mr.
Dryclean site and prepare a Well Abandonment Report, in accordance with the Wood scope of work and cost estimate form received on April 20, 2020, revised and resubmitted by Wood on May 12, 2021.
Revisions led to a cost increase of $207.67. Labor and subcontractor costs have been reviewed and are appropriate. The cost associated with this Task Assignment is $4,978.93, with a Period of Performance date of 8/27/2021.
ATTACHMENT A
COST ESTIMATE SPREADSHEETS &
SUCONTRACTOR QUOTES
FDEP COST ESTIMATE - HW559 - Original Contractor: Wood E&IS
Date: 4/21/2020 (rev. 5/12/21)
Task #: HW559 - DC007H SubTask 1
Site: SubTask 2 Activity/Phase: SubTask 3 Well Abandonment Report
Project Manager: Crystal Posey (FDEP) / Ron White (Wood) SubTask 4 6090180019 SubTask 5
Totals 1 2 3 4 5 Labor Rate Category
$48.12 Project Manager 2 1.5 $36.45 Program Manager 0 0 0 0 0 $46.94 Project Manager 0 0 0 0 0 $55.49 Consulting Eng/Sci GS 0 0 0 0 0 $46.94 Principal Scientist RW 1 0 1 0 0 $43.59 Senior Scientist 0 0 0 0 0 $42.79 Senior Engineer 0 0 0 0 0 $28.44 Project Engineer 0 0 0 0 0 $22.83 Staff Scientist NS 15 15 0 0 0 $28.85 Project Scientist AH 5 0 5 0 0 $19.23 Staff Scientist ZL 0 0 0 0 0 $35.63 Technical Editor 0 0 0 0 0 $24.59 Construction Supervisor 0 0 0 0 0 $18.78 O&M Specialist 0 0 0 0 0 $25.53 Drafter GB 2 0 2 0 0 $28.37 Senior Technician 0 0 0 0 0 $25.57 Senior Technician 0 0 0 0 0 $19.28 Project Assistant RP 0 0 0 0 0 $14.02 Field Technician 0 0 0 0 0 $22.61 Project Accountant 0 0 0 0 0 $28.57 Contracts/Purchasing 0 0 0 0 0 $12.15 Clerical 0 0 0 0 0 $18.16 Word Processing 0 0 0 0 0
Total Hours 25 2 15 8 0 0 Direct Labor $657.79 $73.09 $342.45 $242.25 $0.00 $0.00
Overhead 111.08% $730.67 $81.19 $380.39 $269.09 $0.00 $0.00 Gen & Admin 8.36% $54.99 $6.11 $28.63 $20.25 $0.00 $0.00 Fringe 35.00% $230.23 $25.58 $119.86 $84.79 $0.00 $0.00 Total Labor $1,673.68 $185.97 $871.33 $616.38 $0.00 $0.00
Other Direct Costs $32.88 $3.65 $17.12 $12.11 $0.00 $0.00 Travel
Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $97.00 $97.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $2,705.00 $2,705.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00
Permits $0.00 $0.00 $0.00 $0.00 $0.00 Private Utility Locate $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 Subcontractor Subtotal $2,705.00 $2,705.00 $0.00 $0.00 $0.00 Handling Fee $270.50 $270.50 $0.00 $0.00 $0.00 Total Subcontractor Cost $2,975.50 $2,975.50 $0.00 $0.00 $0.00
Project Management
Well Abandonment Activities Well Abandonment Mr. Dryclean
REV: 02/11 Wood Page 1
FDEP COST ESTIMATE - HW559 - Original Contractor: Wood E&IS
Date: 4/21/2020 (rev. 5/12/21)
Task #: HW559 - DC007G SubTask 1
Site: SubTask 2 Activity/Phase: SubTask 3 Well Abandonment Report
Project Manager: Crystal Posey (FDEP) / Ron White (Wood) SubTask 4 6090180019 SubTask 5
Totals 1 2 3 4 5
Project Management
Well Abandonment Activities Well Abandonment Mr. Dryclean
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $32.50 $32.50 $0.00 $0.00 $0.00
Subtotal $4,811.56 $189.62 $3,993.45 $628.49 $0.00 $0.00 Completion Fee $167.37 $18.60 $87.13 $61.64 $0.00 $0.00
Total Estimated Cost $4,978.93 $208.22 $4,080.58 $690.13 $0.00 $0.00
REV: 02/11 Wood Page 2
SITE : Mr. Dryclean SUBTASK 2 Well Abandonment Activities DATE: 4/21/2020 (rev. 5/12/21)
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal Scientist
Staff Scientist N. Stoudt Mobe/Demob for Well Abandonment (1 round trip mobilization) 5 Well Abandonment oversight (14 wells) 10
TOTAL LABOR 15
VEHICLE TYPE RATE UNIT USAGE
Automobile $272.00 week 0 $0.00
$68.00 day 0 $0.00
Equipment Van $420.00 week 0 $0.00
$97.00 day 1 $97.00
Truck $420.00 week 0 $0.00 $97.00 day 0 $0.00
TOTAL VEHICLE $97.00
PER DIEM STAFF RATE UNIT USAGE
Hotel $100.00 day $0.00
Per Diem $36.00 day $0.00
Hotel $100.00 day $0.00 Per Diem $36.00 day $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
RNA Consulting Group Well abandonment $2,705.00
$0.00 $0.00
TOTAL $2,705.00
SUPPLIES ITEM RATE COSTING UNIT UNITS TOTALS
Expendables $32.50 per day 1 $32.50
$0.00 per foot $0.00 $0.00 per foot $0.00
TOTAL SUPPLIES $32.50
HW559 - Original
SITE : Mr. Dryclean SUBTASK 5 Well Abandonment Report DATE: 4/21/2020 (rev. 5/12/21)
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal Sci RW Report review 1 Sr. Sci
Sr. Eng
Eng/Sci AP Prepare Well Abandonment Report 5
Sr. Tech Drafter GB Prepare figures for report 2 Word Proc/Cler
TOTAL LABOR 8
3122 Mahan Dr. Ste 801-313 · Tallahassee, FL 32317 · 850-545-0672 · www.RNAConsultingGroup.com
Date: April 20, 2020 Estimate #20-013
Submitted to Ron White, P.G., Wood PLC
Project: Mr. Dryclean (ERIC_4259)
Address: 700-5 Blanding Boulevard, Orange Park, Florida
Proposal of RNA Consulting Group, LLC, organized and existing under the laws of the State of
Florida, agrees to do perform all the work described in the Contract Documents for the following unit prices:
Task No.
Description Number Units/
Quantity Price Per
Unit Total Price
1 Mobilization 1 Each $500.00 $500.00
Abandon 1-inch Wells w/pad removal
303 Feet $7.00 $2,121.00
Abandon 2-inch wells w/pad removal
12 Feet $7.00 $84.00
Estimate length of project 1 days Total Cost Estimate: $2,705.00
Quote is valid for 120 days from date listed.
‘Wood’ is a trading name for John Wood Group PLC and its subsidiaries
April 20, 2020 (Revised 5/12/21)
Mr. David Meyers Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blair Stone Road Tallahassee, FL 32399-2400
RE: Cost Estimate to Conduct Well Abandonment
Activities Mr. Dryclean 700-5 Blanding Boulevard Orange Park, Clay County, Florida FDEP FAC ID No: 10/9500198 ERIC No.: ERIC_4259 Task Assignment No: HW559-DC007H Wood Project No: 6090180019
Dear Dave, Per the request of FDEP, Wood Environment & Infrastructure Solutions, Inc. (Wood) is pleased to provide this cost proposal for the Mr. Dryclean site in Orange Park, Florida. The site is in the process of receiving a Site Rehabilitation Completion Order based on the site assessment conducted at this facility. The cost estimate with summary spreadsheets for conducting well abandonment activities at the site and preparing the Well Abandonment Report detailing the level of effort (LOE) necessary to conduct the described events are included as Attachment A. This work will be conducted under Contract Number HW559. The events in this proposal are separated into the following subtasks in the attached cost estimate spreadsheets.
All field work activities will be conducted in accordance with FDEP’s standard operating procedures (SOPs; DEP-SOP-001/01), FDEP’s Considerations for Assessment of Drycleaning Solvent Contaminated Sites (FDEP 2002) and Wood’s site-specific Health & Safety Plan.
Subtask 1 – Project Management This subtask includes all tasks associated with Project Management for this task assignment at the Mr. Dryclean site including the LOE for managing and providing technical oversight for the duration of the project, scheduling with subcontractors, communication with the property owner, all communications with FDEP including meetings, and invoicing.
Subtask 2 – Well Abandonment Activities This subtask includes the LOE necessary for Wood personnel to oversee the abandonment of 11 micro-wells and three MAGS wells that were installed as part of the site assessment. This will include properly abandoning 11, 1-inch diameter, micro-wells varying in depth from 7.5 feet below lands surface (bls) to 64 feet bls and three, 2-inch diameter, 4-foot deep MAGS wells. Each well will be abandoned in place by filling with Portland-type cement from the bottom of the well until completely filled with grout. This will include removing (12) 2’x2’ concrete pads and associated steel vaults and replacing with either new concrete or soil and sod (depending on location). The wells vaults for micro-well MW-1 and MAGS well MAGS-1 (located inside building under carpet) will be left in place so as not to potentially damage the floor and carpet inside the building.
These two wells will be grouted to the top of their vault and the man-hole cover will be replaced and the carpet will be glued back down in place. Well abandonment activities will be completed by RNA Consulting of Tallahassee, Florida, a licensed well driller. Well abandonment permits will be obtained and provided by RNA Consulting.
Subtask 3 – Well Abandonment Report This subtask includes the LOE for preparing a Well Abandonment Report detailing the activities of the well abandonment including a table with well details and updated figures.
Sampling & Deliverable Schedule
Subtask Scheduled Activities Deliverables Deliverable Due Date
Invoice Amount
2 May 2020* Field notes, Photographs June 15, 2021* $4,080.58
3 After receipt of Lab data Well Abandonment Report June 30, 2021 $690.13 + PM $208.22
*Assuming FDEP Tasks by 5/30/21 to be able to schedule in May
Wood is prepared to schedule the initial field work activities within 30 days of receipt of a signed task assignment based upon subcontractor availability.
Please let me know if there are any questions concerning this package. Wood appreciates the opportunity to assist the Waste Site Cleanup Section with this project.
Sincerely, Wood Environment & Infrastructure Solutions, Inc.
Ron White, P.G.
Principal Geologist
Well Abandonment Details
Well ID Diameter (inches) Total Well Depth (feet) Screen Interval (feet)
MW-1 1 7.5 2.5 – 7.5
MW-2 & MW-3 1 15 5 – 15
MW-4R & MW-6 1 14 2 – 12
MW-5 1 12 2 – 12
DW-1 1 64 14 – 24
DW-2 1 24 14 – 24
DW-3 1 50 45 – 50
MAGS-1 2 4 1 – 4
MAGS-2 2 4 1 – 4
MAGS-3 2 4 1 – 4
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| Task Assignment Notification |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |