CN-370000-HW555-DC030K.pdf

PDF 895 KB Posted

Attached to
Master Agreement FL|HW555|3626b1bfe23ad9cb6d0c11811d472cb2
Contract number
HW555
Issued by
Florida

About this file

This document is a Task Assignment Notification Form for contract HW555 between the Florida Department of Environmental Protection (FDEP) and GHD Services, Inc. The task assignment (DC030K) is for groundwater monitoring services at the Town & Country Cleaners site located at 8490 West Hillsborough Avenue in Tampa, Hillsborough County, Florida. The site is designated as ERIC_4730. Kevin Kane serves as the FDEP Contract Manager, with Brian Moore representing GHD Services, Inc. as the contractor representative.

The task involves annual groundwater monitoring conducted in accordance with GHD's April 2021 scope of work and cost proposal. The work comprises two subtasks: Project Management (calculated at 12.5% of direct labor) and Groundwater Sampling, which includes redevelopment of four monitoring wells (MW003, MW006, MW009, and MW014) and sampling of ten monitoring wells for volatile organic halocarbons using EPA Method 8260. The final deliverable is a Groundwater Monitoring Report due September 3, 2021, with task completion scheduled for December 3, 2021. The total task assignment value is $6,205.22 on a fixed price basis with no retainage. Invoice submission is triggered upon completion of groundwater monitoring activities and FDEP approval of the Groundwater Monitoring Report. The cost estimate includes labor ($4,190.27), travel ($97.00), subcontractor services ($104.50), laboratory analysis ($720.00), field expenses ($595.80), and a completion fee ($419.03).

View the file

Other files

File Type Posted
CN-370000-HW552-SS11SCO1.pdf PDF
CN-370000-HW555-A2.pdf PDF
CN-370000-HW555-A6.pdf PDF
CN-370000-HW555-A8.pdf PDF
CN-370000-HW555-A9.pdf PDF
CN-370000-HW555-CO3.pdf PDF
CN-370000-HW555-DC001I.pdf.crdownload CRDOWNLOAD file
CN-370000-HW555-DC004J.pdf PDF
CN-370000-HW555-DC007J.pdf PDF
CN-370000-HW555-DC009o.pdf PDF
CN-370000-HW555-DC011G.pdf PDF
CN-370000-HW555-DC012J.pdf PDF
CN-370000-HW555-DC013F.pdf PDF
CN-370000-HW555-DC015H.pdf PDF
CN-370000-HW555-DC019F.pdf PDF
CN-370000-HW555-DC019H.pdf PDF
CN-370000-HW555-DC019J.pdf PDF
CN-370000-HW555-DC01ACO4.pdf PDF
CN-370000-HW555-DC01ACO5.pdf PDF
CN-370000-HW555-DC01ACO7.pdf PDF
CN-370000-HW555-DC01D.pdf PDF
CN-370000-HW555-DC01F.pdf PDF
CN-370000-HW555-DC01G.pdf PDF
CN-370000-HW555-DC020D.pdf PDF
CN-370000-HW555-DC023L.pdf PDF
CN-370000-HW555-DC027F.pdf PDF
CN-370000-HW555-DC027J.pdf PDF
CN-370000-HW555-DC02B.pdf PDF
CN-370000-HW555-DC02G.pdf PDF
CN-370000-HW555-DC02H.pdf PDF
CN-370000-HW555-DC02HCO1.pdf PDF
CN-370000-HW555-DC02HCO2.pdf PDF
CN-370000-HW555-DC02ICO1.pdf PDF
CN-370000-HW555-DC02ICO3.pdf PDF
CN-370000-HW555-DC02ICO4.pdf PDF
CN-370000-HW555-DC02J.pdf PDF
CN-370000-HW555-DC02O.pdf PDF
CN-370000-HW555-DC030G.pdf PDF
CN-370000-HW555-DC032E.pdf PDF
CN-370000-HW555-DC034P.pdf PDF
CN-370000-HW555-DC035Q.pdf PDF
CN-370000-HW555-DC03C.pdf PDF
CN-370000-HW555-DC03H.pdf PDF
CN-370000-HW555-DC03K.pdf PDF
CN-370000-HW555-DC03i.pdf PDF
CN-370000-HW555-DC041C.pdf PDF
CN-370000-HW555-DC045H.pdf PDF
CN-370000-HW555-DC046A.pdf PDF
CN-370000-HW555-DC049A.pdf PDF
CN-370000-HW555-DC049I.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP CONTRACT NO.

Task Assignment #: Module #: Grant #:

Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #:

DEP Site #:

Site Name:

Address(Street, City, County):

Phase:

Task Description [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverables:

Final Deliverable Due Date:

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

FIXED FEE

RETAINAGE:

TOTAL TASK ASSIGNMENT VALUE: $0.00

DEP Task Manager:

DEP Contract Manager:

Contractual Authority:

Contractor Representative:

CC: Procurement Section (MS 93) Section Representative ________

TASK ASSIGNMENT NOTIFICATION FORM

COST PLUS FIXED FEE

COST REIMBURSEMENT

FIXED PRICE FEE SCHEDULE

Period of Performance:

Execution of Task Assignment through:

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

WCP TAFORM 01_18

HW555

D000 N/ADC030K

GHD Services, Inc.

Brian Moore

(850) 245-8971Kevin Kane

ERIC_4730

Town & Country Cleaners

8490 West Hillsborough Ave., Tampa, Hillsborough County

Monitoring

GHD Services, Inc. will conduct groundwater monitoring in accordance with the April 2021 scope of work and cost proposal. Groundwater Monitoring Report will be generated.

Groundwater Monitoring Report

09/03/2021

12/03/2021

$ 6,205.22 $ 0.00 $ 0.00 $ 0.00

$ 0.00

Kevin Kane Digitally signed by Kevin Kane Date: 2021.04.20 11:04:41 -04'00'

Kevin Kane Digitally signed by Kevin Kane Date: 2021.04.20 11:05:02 -04'00'

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2021.04.20 12:16:12 -04'00'

Brian Moore Digitally signed by Brian Moore Date: 2021.04.20 13:51:51 -04'00'

$ 6,205.22

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01-2018

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Groundwater Monitoring Report 09/03/2021

Upon completion of groundwater monitoring activities and FDEP approval of Groundwater Monitoring Report $ 6,205.22

$ 6,205.22

HW555

DC030K

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Noah Valenstein Secretary

TO: HW555 Contract File Town & Country Cleaners

ERIC_4730

Tampa, Hillsborough County

FROM: Kevin Kane, Contract Manager

DATE: April 20, 2021

SUBJECT: Task Assignment Summary

HW555 DC030K

Monitoring

GHD will conduct annual groundwater monitoring. Specific subtasks are detailed below:

Subtask 1: Project Management Project management is calculated at 12.5 percent of the direct labor.

Subtask 2: Groundwater Sampling Groundwater sampling for VOHs by EPA Method 8260 will be conducted at 10 monitoring wells, 4 of which (MW003, MW006, MW009, and MW014) will be redeveloped by GHD prior to sampling. Upon completion of groundwater sampling a Groundwater Monitoring Report will be prepared and submitted to FDEP. Report will include field notes, analytical results, and recommendations.

This work will be conducted in line with the scope of work included in the GHD proposal, received April 19, 2021.

Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and the GHD proposal. The final deliverable due date is September 3, 2021, and the completion date for the task assignment is December 3, 2021.

The final cost total for Task Assignment DC030K is $6,205.22.

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 04/20/21

Task #: DC030K SubTask 1 Project Management SubTask 6

Site: Town & Counrty Claners SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, P.E. SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$69.71 Project Manager BM 2.51 2.506 $0.00 President/V.P 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$69.71 Sr. Professional Engineer BM 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$40.00 Professional Engineer/Geologist ES 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $42.64 Professional Engineer/Geologist GE 12.50 12.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $49.00 Professional Engineer/Geologist KC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.72 Staff Engineer/Scientist BG 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.91 Project Manager/Engineer SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $24.73 Staff Engineer/Scientist VH 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Senior Computer Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$28.85 Senior Technician WM 14.50 14.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $17.16 Junior Technician WJ 10.75 10.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $17.51 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.82 Drafting Technician PM 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Senior Assistant/Accounting 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.14 Staff Assistant SS 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Computer Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Hours 51.26 2.506 48.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $1,572.33 $174.70 $1,397.63 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 113.00% $1,776.73 $197.41 $1,579.32 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 28.00% $440.26 $48.92 $391.34 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 25.50% $400.95 $44.55 $356.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $4,190.27 $465.58 $3,724.69 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $78.62 $8.74 $69.88 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel

REV: 02/03 CEF GHD Services Inc. Page 1

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 04/20/21

Task #: DC030K SubTask 1 Project Management SubTask 6

Site: Town & Counrty Claners SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, P.E. SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $95.00 $95.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $95.00 $95.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $9.50 $9.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $104.50 $104.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $660.00 $660.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $60.00 $60.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $720.00 $720.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $563.30 $563.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $595.80 $595.80 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $5,786.19 $474.32 $5,311.87 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $419.03 $46.56 $372.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $6,205.22 $520.88 $5,684.34 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GHD Services Inc. Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET Sub 2

SITE : Town N' Country Cleaners

PROJECT NUMBER: 090160 (600-1989)

FDEP NO: 299501408 ERIC_4730

SUBTASK: Groundwater Monitoring

DATE: 4/20/2021

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr. Professional Engineer BM Conclusions/Recommendations 1

Professional Geologist GE Coordinate site access to the interior 0.5 Professional Geologist GE Field work scope and QA/QC field data package 1 Professional Geologist GE Coordinate IDW Disposal 1 Professional Geologist GE Groundwater sampling methdology 1 Professional Geologist GE Groundwater Elevation evaluation (shallow/intermediate) 3 Professional Geologist GE Groundwater analytical evaluation (shallow/intermediate) 4 Professional Geologist GE QA/QC (Laboratory) 1 Professional Geologist GE Conclusions and Recommendations 1

12.5

Senior Technician WM Mob/Demob (2 days) 2 Senior Technician WM Redevelop MW003, 6, 9, and 14 (1 hour each) 4 Senior Technician WM Equipment Calibration/COC forms 1 Senior Technician WM Groundwater Sampling (5 wells) 7.5

14.5

Junior Technician WJ Mob/Demob 1 Junior Technician WJ Water Levels (all wells - 14 total) 2.25 Junior Technician WJ Groundwater Sampling (5 wells) 7.5

10.75

Drafting Technician PM Prepare Groundwater Contour Figures (shallow/intermediate) 2 Drafting Technician PM Prepare Groundwater Analytical Figures (shallow/intermediate) 2

Staff Assistants SS Data Entry (10 wells + water levels) 1.5 Staff Assistants SS Update summary tables 1 Staff Assistants SS Document Preparation/Publishing/PDF 2 Staff Assistants SS GIS/Adapt update 1.5

TOTAL LABOR 48.75

TRAVEL TYPE RATE UNIT USEAGE Miles Free

Truck $97.00 day 1 $97.00

TOTAL VEHICLE $97.00

SUBCONTRACTOR

Equipment Procurement

NAME PURPOSE COST UNIT USEAGE

Services Procurement

NAME PURPOSE COST UNIT USEAGE

Gulf Coast IDW Drum Disposal $95 drum 1 $95.00

TOTAL SUBS $95.00

LABORATORY

PARAMETER RATE # SAMPLES #QAQC

EPA Method 8260 VOHs $66.00 10 $660.00 sample shipping (two day - large cooler) $60.00 1 $60.00

TOTAL LAB $720.00

FIELD EXPENSES ITEM RATE UNIT USEAGE TOTALS

Field Equipment

Expendables $32.50 Day 1 $32.50 Sub-Total $32.50 one per technician Groundwater Sampling Kit $208.55 Day 2 $417.10 Poly Tubing (HDPE) $0.25 Ft 272 $68.00 Silicon Tubing $2.00 Ft 10 $20.00 55-gallon drum $58.20 drum 1 $58.20

Sub-Total $563.30

TOTAL EQUIPMENT $595.80

TA_030K\sub 2 Page 3 4/20/202110:49 AM

COST PROPOSAL FOR TASK DC030J

<Town & Country Cleaners/FDEP #29-9501408>

<Groundwater Monitoring >

1. INTRODUCTION: <DISCUSS SCOPE OF WORK, DATES >

GHD submitted a Supplemental Site Assessment Report (SSAR) in February 2020 for the Town & Country Cleaners site located in Tampa, Hillsborough County. The results of the groundwater sampling conducted identified Vinyl Chloride as the primary contaminant of concern at the site. The SSAR was approved along with the assessment for the site and periodic groundwater sampling was recommended. Task assignment DC030K includes annual groundwater sampling at selected site monitoring wells in accordance with recommendations from GHD’s monitoring report dated October 29, 2020, and Department comments also dated October 29, 2020.

Subtask 1: Project Management Subtask 1 includes all activities associated with completion of groundwater sampling and preparation of a Groundwater Monitoring Report.

Subtask 2: Groundwater Sampling Groundwater sampling is recommended in order to evaluate concentration trends over time.

As recommended, GHD personnel will redevelop monitor wells MW003, MW006, MW009, and MW014 prior to the next sampling event. Annual groundwater sampling will be conducted at site monitoring wells MW001, MW003, MW004, MW005, MW006, MW007, MW009, MW011, MW012, and MW013. The sampling will include gathering water levels from all existing wells and conducting groundwater sampling in accordance with FDEP SOPs.

All groundwater samples will be analyzed for the presence of volatile organic halocarbons by EPA Method 8260.

Following receipt of groundwater analytical results, a summary report will be prepared. The summary report will include a description of field sampling methodology and analytical results. Groundwater elevation and analytical figures will also be prepared. The report will also include recommendations regarding the next step toward site rehabilitation.

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

Groundwater Monitoring Report 9/3/21

Gulf Coast Vacuum Truck Services 1744 Williams Ditch Rd

Cantonment, FL 32533 US

+1 8504500058 accounting@gcvts.net

Estimate

ADDRESS

GHD

ESTIMATE 1040

DATE 04/15/2021

DATE SERVICE DESCRIPTION QTY RATE AMOUNT

Drum Disposal Disposal of of 1 drum of contaminated water.

1 95.00 95.00

Island Cleaners - Sanibel TOTAL $95.00

Accepted By

Accepted Date

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Brian Moore

GHD

5904 Hampton Oaks Parkway – Suite F

Tampa, FL 33610

April 15, 2021

Re: Non-Hazardous Drum Disposal Quote – South and Central Florida

Mr. Moore:

The price for disposal of drums of non-hazardous soil or groundwater located in south and central

Florida will be $100.00 per drum, total, for both transportation and disposal.

Pricing for the Florida Keys will be quoted separately on a case-by-case basis.

This quote is valid for 180 days.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

ID Task Mode

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 4/19/21Fri 4/30/21

2 Subtask 1: Project Management

90 days Mon 5/3/21 Fri 9/3/21

3 Subtask 2: Groundwater Monitoring

48 days Wed 6/30/21

Fri 9/3/21

4 Field Work Preparation 2 wks Wed 6/30/21Tue 7/13/21

5 Groundwater Sampling 1 day Wed 7/14/21Wed 7/14/21

6 Groundwater Monitoring Report

6 wks Mon 7/26/21

Fri 9/3/21

4/11 4/18 4/25 5/2 5/9 May

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC030K at the Town & Country Cleaners facility located in Tampa, Hillsborough County

Project: TA_030K Date: Mon 4/19/21

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 4/19/21Fri 4/30/21

2 Subtask 1: Project Management

90 days Mon 5/3/21 Fri 9/3/21

3 Subtask 2: Groundwater Monitoring

48 days Wed 6/30/21

Fri 9/3/21

4 Field Work Preparation 2 wks Wed 6/30/21Tue 7/13/21

5 Groundwater Sampling 1 day Wed 7/14/21Wed 7/14/21

6 Groundwater Monitoring Report

6 wks Mon 7/26/21

Fri 9/3/21

5/16 5/23 5/30 6/6 6/13 June

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC030K at the Town & Country Cleaners facility located in Tampa, Hillsborough County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 4/19/21Fri 4/30/21

2 Subtask 1: Project Management

90 days Mon 5/3/21 Fri 9/3/21

3 Subtask 2: Groundwater Monitoring

48 days Wed 6/30/21

Fri 9/3/21

4 Field Work Preparation 2 wks Wed 6/30/21Tue 7/13/21

5 Groundwater Sampling 1 day Wed 7/14/21Wed 7/14/21

6 Groundwater Monitoring Report

6 wks Mon 7/26/21

Fri 9/3/21

Gabrielle Enos

William McKinney

6/20 6/27 7/4 7/11 7/18 July

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC030K at the Town & Country Cleaners facility located in Tampa, Hillsborough County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 4/19/21Fri 4/30/21

2 Subtask 1: Project Management

90 days Mon 5/3/21 Fri 9/3/21

3 Subtask 2: Groundwater Monitoring

48 days Wed 6/30/21

Fri 9/3/21

4 Field Work Preparation 2 wks Wed 6/30/21Tue 7/13/21

5 Groundwater Sampling 1 day Wed 7/14/21Wed 7/14/21

6 Groundwater Monitoring Report

6 wks Mon 7/26/21

Fri 9/3/21 y,William Jahns

7/25 8/1 8/8 8/15 8/22 August

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC030K at the Town & Country Cleaners facility located in Tampa, Hillsborough County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 4/19/21Fri 4/30/21

2 Subtask 1: Project Management

90 days Mon 5/3/21 Fri 9/3/21

3 Subtask 2: Groundwater Monitoring

48 days Wed 6/30/21

Fri 9/3/21

4 Field Work Preparation 2 wks Wed 6/30/21Tue 7/13/21

5 Groundwater Sampling 1 day Wed 7/14/21Wed 7/14/21

6 Groundwater Monitoring Report

6 wks Mon 7/26/21

Fri 9/3/21 Brian Moore,Gabrielle Enos,Peter McLean,Sheila Stoke

8/29 9/5 9/12 9/19 9/26 September Octo

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC030K at the Town & Country Cleaners facility located in Tampa, Hillsborough County

Task Assignment Notification
BWC Task Assignment Form (Rev 02_17).pdf
Task Assignment Notification
BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf
Deliverable & Invoice Schedule

File details come from the government source that posted it. Updated .