This document is a Task Assignment Notification Form for the Florida Department of Environmental Protection (FDEP) under Contract No. HW555. The contractor is GHD Services, Inc., with Brian Moore serving as the Contractor Representative and Billy Hessman as the DEP Contract Manager. The task assignment pertains to the Sargent's One Hour Cleaners (Formerly) site located at 45 E. Washington St., Orlando, Orange County, Florida, designated as FDEP Site No. ERIC_5061.

Task Assignment DC027J is for the monitoring phase and involves the abandonment of four off-site monitoring wells (MW020 through MW023) prior to property development activities. The task is divided into two subtasks: Subtask 1 covers project management calculated at 12.5 percent of direct labor, and Subtask 2 encompasses the actual well abandonment in accordance with applicable Water Management District guidelines, including permitting, mobilization, grouting, pad removal, site restoration, and off-site disposal of materials. The final deliverable is a Well Abandonment Report with a due date of October 2, 2020, and the overall task completion date is January 15, 2021. The task assignment type is Fixed Price with a total value of $3,598.92, with no retainage. Invoice payment is contingent upon completion of well abandonment activities and FDEP approval of the Well Abandonment Report. The document includes detailed cost estimates, level-of-effort worksheets, and a project schedule spanning from July 20, 2020, through October 2, 2020.

View the file

Other files

File Type Posted
CN-370000-HW555-CO2.pdf PDF
CN-370000-HW555-DC002L.pdf PDF
CN-370000-HW555-DC004G.pdf PDF
CN-370000-HW555-DC010H.pdf PDF
CN-370000-HW555-DC010J.pdf PDF
CN-370000-HW555-DC010M.pdf PDF
CN-370000-HW555-DC013J.pdf PDF
CN-370000-HW555-DC014I.pdf PDF
CN-370000-HW555-DC015B.pdf PDF
CN-370000-HW555-DC019A.pdf PDF
CN-370000-HW555-DC01ACO3.pdf PDF
CN-370000-HW555-DC020M.pdf PDF
CN-370000-HW555-DC027H.pdf PDF
CN-370000-HW555-DC02BCO1.pdf PDF
CN-370000-HW555-DC02BCO2.pdf PDF
CN-370000-HW555-DC02HCO3.pdf PDF
CN-370000-HW555-DC02HCO5.pdf PDF
CN-370000-HW555-DC02ICO2.pdf PDF
CN-370000-HW555-DC02N.pdf PDF
CN-370000-HW555-DC031H.pdf PDF
CN-370000-HW555-DC034E.pdf PDF
CN-370000-HW555-DC034I.pdf PDF
CN-370000-HW555-DC035D.pdf PDF
CN-370000-HW555-DC035K.pdf PDF
CN-370000-HW555-DC039C.pdf PDF
CN-370000-HW555-DC039F.pdf PDF
CN-370000-HW555-DC03E.pdf PDF
CN-370000-HW555-DC03F.pdf PDF
CN-370000-HW555-DC03G.pdf PDF
CN-370000-HW555-DC040H.pdf PDF
CN-370000-HW555-DC041B.pdf PDF
CN-370000-HW555-DC043C.pdf PDF
CN-370000-HW555-DC045G.pdf PDF
CN-370000-HW555-DC049G.pdf PDF
CN-370000-HW555-DC049H.pdf PDF
CN-370000-HW555-DC051A.pdf PDF
CN-370000-HW555-DC052G.pdf PDF
CN-370000-HW555-DC063E.pdf PDF
CN-370000-HW555-DC07D.pdf PDF
CN-370000-HW555-DC09HCO6.pdf PDF
CN-370000-HW555-DC09K.pdf PDF
CN-370000-HW555-DC09M.pdf PDF
CN-370000-HW555-DC10FCO2.pdf PDF
CN-370000-HW555-DC10I.pdf PDF
CN-370000-HW555-DC11DCO1.pdf PDF
CN-370000-HW555-DC11DCO2.pdf PDF
CN-370000-HW555-DC11E.pdf PDF
CN-370000-HW555-DC11F.pdf PDF
CN-370000-HW555-DC12B.pdf PDF
CN-370000-HW555-DC12BCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP CONTRACT NO.

Task Assignment #: Module #: Grant #:

Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #:

DEP Site #:

Site Name:

Address(Street, City, County):

Phase:

Task Description [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverables:

Final Deliverable Due Date:

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

FIXED FEE

RETAINAGE:

TOTAL TASK ASSIGNMENT VALUE: $0.00

DEP Task Manager:

DEP Contract Manager:

Contractual Authority:

Contractor Representative:

CC: Procurement Section (MS 93) Section Representative ________

TASK ASSIGNMENT NOTIFICATION FORM

COST PLUS FIXED FEE

COST REIMBURSEMENT

FIXED PRICE FEE SCHEDULE

Period of Performance:

Execution of Task Assignment through:

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

WCP TAFORM 01_18

HW555

D000 NADC027J

GHD Services, Inc.

Brian Moore

850-245-8972Billy Hessman

ERIC_5061

Sargent's One Hour Cleaners (Formerly)

45 E. Washington St., Orlando, Orange

Monitoring

GHD Services, Inc. will abandon four off-site monitoring wells prior to property development activities.

Well Abandonment Report

10/02/2020

01/15/2021

$ 3,598.92 $ 0.00 $ 0.00 $ 0.00

$ 0.00

Billy Hessman Digitally signed by Billy Hessman Date: 2020.07.20 11:29:10 -04'00'

Billy Hessman Digitally signed by Billy Hessman Date: 2020.07.20 11:29:16 -04'00'

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2020.07.20 12:07:06 -04'00'

Brian Moore Digitally signed by Brian Moore Date: 2020.07.20 14:49:03 -04'00'

$ 3,598.92

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01-2018

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Well Abandonment Report 10/02/2020

Upon completion of well abandonment activities and FDEP approval of the Well Abandonment Report $ 3,598.92

$ 3,598.92

HW555

DC027J

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Noah Valenstein Secretary

TO: HW555 Contract File Sargent’s One Hour Cleaners (Formerly)

ERIC_5061

Orlando, Orange County

FROM:

DATE:

SUBJECT:

Billy Hessman, Contract Manager

July 20, 2020

Task Assignment Summary

HW555 DC027J

Monitoring

GHD Services, Inc. will abandon four off-site monitoring wells prior to property development activities. Specific subtasks are detailed below:

Subtask 1: Project Management Project management is calculated at 12.5 percent of the direct labor.

Subtask 2: Well Abandonment Subtask 2 includes costs associated with abandoning four off-site monitoring wells prior to site development activities. All wells will be abandoned by a licensed water well driller in accordance with applicable Water Management District guidelines. Upon completion of abandonment activities, a Well Abandonment Report will be submitted to the Department.

Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and the GHD proposal. The final deliverable due date is October 2, 2020, and the completion date for the task assignment is January 15, 2021.

The final cost total for Task Assignment DC027J is $3,598.92.

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 07/20/20

Task #: DC027J SubTask 1 Project Management SubTask 6

Site: Sargents One Hour Cleaners (for SubTask 2 Well Abandonment SubTask 7

Activity/Phase: Well Abandonment SubTask 3 SubTask 8

Project Manager: Brian Moore, P.E. SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$69.71 Project Manager BM 1.71 1.714 $0.00 President/V.P 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$68.51 Sr. Professional Engineer BM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$49.00 Professional Engineer/Geologist ES 4.50 4.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $46.41 Professional Engineer/Geologist MC 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $45.90 Professional Engineer/Geologist KC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.19 Staff Engineer/Scientist WT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $25.38 Project Manager/Engineer AS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.11 Staff Engineer/Scientist EG 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Senior Computer Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$20.22 Senior Technician BJ 13.00 13.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.34 Senior Technician AP 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $17.51 Junior Technician WO 13.00 13.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.82 Drafting Technician MJ 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Senior Assistant/Accounting 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.18 Staff Assistant ET 2.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Computer Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Hours 39.21 1.714 37.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $1,075.29 $119.48 $955.81 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 113.00% $1,215.08 $135.01 $1,080.07 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 28.00% $301.08 $33.45 $267.63 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 25.50% $274.20 $30.47 $243.73 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $2,865.65 $318.41 $2,547.24 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $53.76 $5.97 $47.79 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel

REV: 02/03 CEF GHD Services Inc. Page 1

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 07/20/20

Task #: DC027J SubTask 1 Project Management SubTask 6

Site: Sargents One Hour Cleaners (for SubTask 2 Well Abandonment SubTask 7

Activity/Phase: Well Abandonment SubTask 3 SubTask 8

Project Manager: Brian Moore, P.E. SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Orange County $200.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $200.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $20.00 $20.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $220.00 $220.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $43.45 $43.45 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $75.95 $75.95 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $3,312.36 $324.38 $2,987.98 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $286.56 $31.84 $254.72 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $3,598.92 $356.22 $3,242.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GHD Services Inc. Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET Sub 2

SITE : Sargents One Hour Cleaners (formerly)

PROJECT NUMBER: 90135

FDEP NO: ERIC_5061

SUBTASK: Well Abandonment

DATE: 7/20/2020

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Professional Geologist ES Field Work Preparation 0.5 Professional Geologist ES Prepare Well Abandonment Summary 4

4.5

Professional Geologist MC Well abandonment permitting 4

Senior Technician BJ Mob/Demob (from Tampa) 4 Senior Technician BJ Well Abandonment (4 wells) 5 Senior Technician BJ Remove pads restore areas 4

Junior Technician WO Mob/Demob (from Tampa) 4 Junior Technician WO Well Abandonment (4 wells) 5 Junior Technician WO Remove pads restore areas 4

Drafting Technician MJ Prepare site plan with wells abandoned 1

Staff Assistants ET Revise tables/upload pictures 1 Staff Assistants ET Document Preparation/Publishing/pdf 1

TOTAL LABOR 37.5

TRAVEL TYPE RATE UNIT USEAGE Miles Free

Truck $97.00 day 1 $97.00

TOTAL VEHICLE $97.00

SUBCONTRACTOR

Equipment Procurement

NAME PURPOSE COST UNIT USEAGE

Services Procurement

NAME PURPOSE COST UNIT USEAGE

Orange County Health Dept Permits $50.00 well 4 $200.00

TOTAL SUBS $0.00

LABORATORY

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

FIELD EXPENSES ITEM RATE UNIT USEAGE TOTALS

Field Equipment

Expendables $32.50 Day 1 $32.50 Sub-Total $32.50

Portland Cement Grout $4.55 bag 4 $18.20 Centrifugal Pump $25.25 Day 1 $25.25

Sub-Total $43.45

TOTAL EQUIPMENT $75.95

TA_027J.xlsx\sub 2 Page 3 7/20/202010:26 AM

COST PROPOSAL FOR TASK DC027J

< Sargents One Hour Cleaners (formerly), ERIC_5061>

Well Abandonment

1. INTRODUCTION:

GHD is currently conducting periodic groundwater monitoring at the former Sargents One Hour Cleaners site located in Orlando, Orange County. During the previous sampling event, monitor wells MW020 through MW023 were not accessible because they were located within a fence-enclosed property to the southeast of the site. After additional discussions with representatives of the property owner, well abandonment was recommended.

Subtask 1: Project Management Task 1 includes all activities associated with project management for the abandonment of monitoring wells MW020 through MW023 and reporting.

Subtask 2: Well Abandonment GHD personnel will obtain well abandonment permits from the local Health Department (if required). The permitting will be conducted by GHDs licensed water well driller.

Following permit receipt, GHD personnel will mobilize to the subject site and abandon four monitor wells (MW020 through MW023) that were installed as part of the Site Assessment activities. The well abandonment will be conducted in accordance with applicable Water Management District guidelines. Wells will be grouted from bottom up using the tremie method. Following well abandonment, the concrete pads and manholes will be removed and the areas will be backfilled with asphalt, concrete, or sand to match the surrounding surface.

All well material and concrete will be disposed off-site.

Following completion of the field activities, a brief well abandonment summary report will be prepared. The summary report will include copies of well permits, a site plan show the location of abandoned wells and detail photo documentation of the well abandonment activities.

Deliverables:

Deliverable Deliverable Due Date

Well Abandonment Report 10/2/20

ID Task Mode

Task Name Duration Start Finish

1 LOE Submittal/Approva 2 wks Mon 7/20/20Fri 7/31/20

2 Subtask 1: Project Management

45 days Mon 8/3/20 Fri 10/2/20

3 Subtask 2: Well Abandonment

45 days Mon 8/3/20 Fri 10/2/20

4 Permitting 3 wks Mon 8/3/20 Fri 8/21/20

5 Field Work Preparatio1 wk Mon 8/24/20Fri 8/28/20

6 Well Abandonment 1 day Tue 9/1/20 Tue 9/1/20

7 Well Abandonment Report

4 wks Mon 9/7/20 Fri 10/2/20

S M T W T F S S M T W Jul 19, '20 Jul 26, '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC027J at the Sargents One Hour Cleaners (formerly) located in Orlando, Orange County

Project: TA_027J Date: Mon 7/20/20

Task Name Duration Start Finish

1 LOE Submittal/Approva 2 wks Mon 7/20/20Fri 7/31/20

2 Subtask 1: Project Management

45 days Mon 8/3/20 Fri 10/2/20

3 Subtask 2: Well Abandonment

45 days Mon 8/3/20 Fri 10/2/20

4 Permitting 3 wks Mon 8/3/20 Fri 8/21/20

5 Field Work Preparatio1 wk Mon 8/24/20Fri 8/28/20

6 Well Abandonment 1 day Tue 9/1/20 Tue 9/1/20

7 Well Abandonment Report

4 wks Mon 9/7/20 Fri 10/2/20

T F S S M T W T F S S Aug 2, '20 Aug 9, '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC027J at the Sargents One Hour Cleaners (formerly) located in Orlando, Orange County

Task Name Duration Start Finish

1 LOE Submittal/Approva 2 wks Mon 7/20/20Fri 7/31/20

2 Subtask 1: Project Management

45 days Mon 8/3/20 Fri 10/2/20

3 Subtask 2: Well Abandonment

45 days Mon 8/3/20 Fri 10/2/20

4 Permitting 3 wks Mon 8/3/20 Fri 8/21/20

5 Field Work Preparatio1 wk Mon 8/24/20Fri 8/28/20

6 Well Abandonment 1 day Tue 9/1/20 Tue 9/1/20

7 Well Abandonment Report

4 wks Mon 9/7/20 Fri 10/2/20

M T W T F S S M T W T 20 Aug 16, '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC027J at the Sargents One Hour Cleaners (formerly) located in Orlando, Orange County

Task Name Duration Start Finish

1 LOE Submittal/Approva 2 wks Mon 7/20/20Fri 7/31/20

2 Subtask 1: Project Management

45 days Mon 8/3/20 Fri 10/2/20

3 Subtask 2: Well Abandonment

45 days Mon 8/3/20 Fri 10/2/20

4 Permitting 3 wks Mon 8/3/20 Fri 8/21/20

5 Field Work Preparatio1 wk Mon 8/24/20Fri 8/28/20

6 Well Abandonment 1 day Tue 9/1/20 Tue 9/1/20

7 Well Abandonment Report

4 wks Mon 9/7/20 Fri 10/2/20

Meeghan Casey

Ed Siersema

F S S M T W T F S S M Aug 23, '20 Aug 30, '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC027J at the Sargents One Hour Cleaners (formerly) located in Orlando, Orange County

Task Name Duration Start Finish

1 LOE Submittal/Approva 2 wks Mon 7/20/20Fri 7/31/20

2 Subtask 1: Project Management

45 days Mon 8/3/20 Fri 10/2/20

3 Subtask 2: Well Abandonment

45 days Mon 8/3/20 Fri 10/2/20

4 Permitting 3 wks Mon 8/3/20 Fri 8/21/20

5 Field Work Preparatio1 wk Mon 8/24/20Fri 8/28/20

6 Well Abandonment 1 day Tue 9/1/20 Tue 9/1/20

7 Well Abandonment Report

4 wks Mon 9/7/20 Fri 10/2/20

Brent Jones,William Ouchie

T W T F S S M T W T F Sep 6, '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC027J at the Sargents One Hour Cleaners (formerly) located in Orlando, Orange County

Task Name Duration Start Finish

1 LOE Submittal/Approva 2 wks Mon 7/20/20Fri 7/31/20

2 Subtask 1: Project Management

45 days Mon 8/3/20 Fri 10/2/20

3 Subtask 2: Well Abandonment

45 days Mon 8/3/20 Fri 10/2/20

4 Permitting 3 wks Mon 8/3/20 Fri 8/21/20

5 Field Work Preparatio1 wk Mon 8/24/20Fri 8/28/20

6 Well Abandonment 1 day Tue 9/1/20 Tue 9/1/20

7 Well Abandonment Report

4 wks Mon 9/7/20 Fri 10/2/20

S S M T W T F S S M T W Sep 13, '20 Sep 20, '20

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC027J at the Sargents One Hour Cleaners (formerly) located in Orlando, Orange County

Task Name Duration Start Finish

1 LOE Submittal/Approva 2 wks Mon 7/20/20Fri 7/31/20

2 Subtask 1: Project Management

45 days Mon 8/3/20 Fri 10/2/20

3 Subtask 2: Well Abandonment

45 days Mon 8/3/20 Fri 10/2/20

4 Permitting 3 wks Mon 8/3/20 Fri 8/21/20

5 Field Work Preparatio1 wk Mon 8/24/20Fri 8/28/20

6 Well Abandonment 1 day Tue 9/1/20 Tue 9/1/20

7 Well Abandonment Report

4 wks Mon 9/7/20 Fri 10/2/20 Ed Sier

W T F S S M T W T F S Sep 27, '20 Oc

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC027J at the Sargents One Hour Cleaners (formerly) located in Orlando, Orange County

Task Assignment Notification
BWC Task Assignment Form (Rev 02_17).pdf
Task Assignment Notification
BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf
Deliverable & Invoice Schedule
TA_027JCEF.pdf
Cost Estimate
sub 2

File details come from the government source that posted it. Updated .