This document is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) for Contract No. HW555 under Task Assignment DC009o. The contract involves GHD Services, Inc., a contractor, with Brian Moore serving as the contractor representative. Kevin Kane is the FDEP Contract Manager, and the task is assigned to the West Side Cleaners site located at 5036 W. Colonial Drive, Orlando, Orange County, Florida (DEP Site #ERIC_5025). The task falls under the monitoring phase of the indefinite delivery contract vehicle.

GHD Services, Inc. will conduct annual groundwater monitoring activities in accordance with the May 2021 scope of work and cost proposal. The work comprises two subtasks: Subtask 1 (Project Management) calculated at 12.5 percent of direct labor, and Subtask 2 (Groundwater Monitoring), which includes standard groundwater sampling at six monitoring wells and passive diffusion bag sampling at seven additional wells. All samples will be analyzed for volatile organic halocarbons by EPA Method 8260. The final deliverable is a Groundwater Monitoring Report due September 9, 2021, with task completion scheduled for December 10, 2021. The task assignment is structured as a Fixed Price contract with a total not-to-exceed amount of $6,140.62, with no retainage. Invoice payment of the full amount is due upon completion of groundwater monitoring activities and FDEP approval of the Groundwater Monitoring Report. No option periods or renewals are specified in the documentation.

View the file

Other files

File Type Posted
CN-370000-HW555-CO2.pdf PDF
CN-370000-HW555-DC002L.pdf PDF
CN-370000-HW555-DC004G.pdf PDF
CN-370000-HW555-DC010H.pdf PDF
CN-370000-HW555-DC010J.pdf PDF
CN-370000-HW555-DC010M.pdf PDF
CN-370000-HW555-DC013J.pdf PDF
CN-370000-HW555-DC014I.pdf PDF
CN-370000-HW555-DC015B.pdf PDF
CN-370000-HW555-DC019A.pdf PDF
CN-370000-HW555-DC01ACO3.pdf PDF
CN-370000-HW555-DC020M.pdf PDF
CN-370000-HW555-DC027H.pdf PDF
CN-370000-HW555-DC02BCO1.pdf PDF
CN-370000-HW555-DC02BCO2.pdf PDF
CN-370000-HW555-DC02HCO3.pdf PDF
CN-370000-HW555-DC02HCO5.pdf PDF
CN-370000-HW555-DC02ICO2.pdf PDF
CN-370000-HW555-DC02N.pdf PDF
CN-370000-HW555-DC031H.pdf PDF
CN-370000-HW555-DC034E.pdf PDF
CN-370000-HW555-DC034I.pdf PDF
CN-370000-HW555-DC035D.pdf PDF
CN-370000-HW555-DC035K.pdf PDF
CN-370000-HW555-DC039C.pdf PDF
CN-370000-HW555-DC039F.pdf PDF
CN-370000-HW555-DC03E.pdf PDF
CN-370000-HW555-DC03F.pdf PDF
CN-370000-HW555-DC03G.pdf PDF
CN-370000-HW555-DC040H.pdf PDF
CN-370000-HW555-DC041B.pdf PDF
CN-370000-HW555-DC043C.pdf PDF
CN-370000-HW555-DC045G.pdf PDF
CN-370000-HW555-DC049G.pdf PDF
CN-370000-HW555-DC049H.pdf PDF
CN-370000-HW555-DC051A.pdf PDF
CN-370000-HW555-DC052G.pdf PDF
CN-370000-HW555-DC063E.pdf PDF
CN-370000-HW555-DC07D.pdf PDF
CN-370000-HW555-DC09HCO6.pdf PDF
CN-370000-HW555-DC09K.pdf PDF
CN-370000-HW555-DC09M.pdf PDF
CN-370000-HW555-DC10FCO2.pdf PDF
CN-370000-HW555-DC10I.pdf PDF
CN-370000-HW555-DC11DCO1.pdf PDF
CN-370000-HW555-DC11DCO2.pdf PDF
CN-370000-HW555-DC11E.pdf PDF
CN-370000-HW555-DC11F.pdf PDF
CN-370000-HW555-DC12B.pdf PDF
CN-370000-HW555-DC12BCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP CONTRACT NO.

Task Assignment #: Module #: Grant #:

Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #:

DEP Site #:

Site Name:

Address(Street, City, County):

Phase:

Task Description [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverables:

Final Deliverable Due Date:

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

FIXED FEE

RETAINAGE:

TOTAL TASK ASSIGNMENT VALUE: $0.00

DEP Task Manager:

DEP Contract Manager:

Contractual Authority:

Contractor Representative:

CC: Procurement Section (MS 93) Section Representative ________

TASK ASSIGNMENT NOTIFICATION FORM

COST PLUS FIXED FEE

COST REIMBURSEMENT

FIXED PRICE FEE SCHEDULE

Period of Performance:

Execution of Task Assignment through:

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

WCP TAFORM 01_18

HW555

D000 N/ADC009o

GHD Services, Inc.

Brian Moore

(850) 245-8971Kevin Kane

ERIC_5025

West Side Cleaners

5036 W. Colonial Drive, Orlando, Orange

Monitoring

GHD Services, Inc. will conduct groundwater monitoring in accordance with the May 2021 scope of work and cost proposal. Groundwater Monitoring Report will be generated.

Groundwater Monitoring Report

09/09/2021

12/10/2021

$ 6,140.62 $ 0.00 $ 0.00 $ 0.00

$ 0.00

Kevin Kane Digitally signed by Kevin Kane Date: 2021.05.27 09:24:54 -04'00'

Kevin Kane Digitally signed by Kevin Kane Date: 2021.05.27 09:25:21 -04'00'

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2021.06.01 12:47:59 -04'00'

Brian Moore Digitally signed by Brian Moore Date: 2021.06.01 14:56:53 -04'00'

$ 6,140.62

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01-2018

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Groundwater Monitoring Report 09/09/2021

Upon completion of groundwater monitoring activities and FDEP approval of Groundwater Monitoring Report $ 6,140.62

$ 6,140.62

HW555

DC009o

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Noah Valenstein Secretary

TO: HW555 Contract File West Side Cleaners

ERIC_5025

Orlando, Orange County

FROM: Kevin Kane, Contract Manager

DATE: May 27, 2021

SUBJECT: Task Assignment Summary

HW555 DC009o Monitoring

GHD Services, Inc. will conduct groundwater monitoring. Specific subtasks are detailed below:

Subtask 1: Project Management Project management is calculated at 12.5 percent of the direct labor.

Subtask 2: Groundwater Monitoring Standard groundwater sampling will be conducted at 6 monitoring wells. Additional sampling will be conducted at 7 monitor wells via passive diffusion bags. All samples will be submitted to a certified lab for testing and analyzed for VOHs by EPA Method 8260.

IDW disposal is anticipated for this sampling event and has been accounted for under this subtask. All available site wells (31 total) will also be sampled for water level measurements. Upon completion of groundwater sampling, a Groundwater Monitoring Report will be prepared and submitted to FDEP. Report will include field notes, analytical results, and recommendations.

This work will be conducted in line with the scope of work included in the GHD proposal, received May 21, 2021.

Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and the GHD proposal. The final deliverable due date is September 9, 2021, and the completion date for the Task Assignment is December 10, 2021.

The final cost total for Task Assignment DC009o is $6,140.62.

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 05/26/21

Task #: DC009o SubTask 1 Project Management SubTask 6

Site: West Side Cleaners SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$69.71 Project Manager BM 2.40 2.397 $0.00 President/V.P 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$69.71 Sr. Professional Engineer BM 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$44.21 Professional Engineer/Geologist JH 14.00 14.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $42.64 Professional Engineer/Geologist GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $49.00 Professional Engineer/Geologist KC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.72 Staff Engineer/Scientist BG 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.91 Project Manager/Engineer SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $24.73 Staff Engineer/Scientist VH 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Senior Computer Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$21.14 Junior Technician BJ 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.18 Junior Technician SA 11.00 11.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $17.51 Junior Technician WO 14.00 14.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.82 Drafting Technician PM 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Senior Assistant/Accounting 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.14 Staff Assistant SS 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Computer Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Hours 52.40 2.397 50.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $1,504.00 $167.11 $1,336.89 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 113.00% $1,699.52 $188.83 $1,510.69 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 28.00% $421.12 $46.79 $374.33 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 25.50% $383.52 $42.61 $340.91 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $4,008.16 $445.34 $3,562.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $75.20 $8.36 $66.84 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel

REV: 02/03 CEF GHD Services Inc. Page 1

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 05/26/21

Task #: DC009o SubTask 1 Project Management SubTask 6

Site: West Side Cleaners SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $97.00 $97.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $95.00 $95.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $95.00 $95.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $9.50 $9.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $104.50 $104.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $858.00 $858.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $60.00 $60.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $918.00 $918.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $32.50 $32.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $504.45 $504.45 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $536.95 $536.95 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $5,739.81 $453.70 $5,286.11 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $400.81 $44.53 $356.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $6,140.62 $498.23 $5,642.39 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GHD Services Inc. Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET Sub 2

SITE : West Side Cleaners

PROJECT NUMBER: 090132

FDEP NO: 489502256 ERIC_5025

SUBTASK: Groundwater Monitoring

DATE: 5/26/2021

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr Professional Engineer BM Conclusions and Recommendations 1

Professional Engineer JH Order sample kit/develop field scope of work/contact property owner 1.5 Professional Engineer JH Verify COC after sampling/review results when received 1 Professional Engineer JH Coordinate IDW Disposal 1 Professional Engineer JH Site Assessment/Remediation Background 1 Professional Engineer JH Groundwater Sampling Scope of Work 1.5 Professional Engineer JH Groundwater Field Parameter Summary 1 Professional Engineer JH Water Level evaluation (shallow / deep) 2 Professional Engineer JH Groundwater analytical results evaluation (shallow / deep) 3 Professional Engineer JH QA/QC 1 Professional Engineer JH Conclusion and Recommendations 1

Junior Technician SA Mob/Demob (from Orlando) 1 Junior Technician SA Water Levels (all wells - 31 total) 2.5 Junior Technician SA Sample 3 wells 4.5 Junior Technician SA Sample diffusion bags (7 wells) 3

Junior Technician WO Mob/Demob (from Tampa) 4 Junior Technician WO Water Levels (all wells - 31 total) 2.5 Junior Technician WO Sample 3 wells 4.5 Junior Technician WO Sample diffusion bags (7 wells) 3

CADD Design PM Groundwater elevation and flow (shallow/deep) 2 CADD Design PM Groundwater Analytical Maps (shallow/deep) 2

Staff Assistants SS Data Entry (31 water levels/13 well samples) 2 Staff Assistants SS Summary tables (elevation, analytical) 1.5 Staff Assistants SS Publish Report/generate pdf 1 Staff Assistants SS GIS/Adapt update 1.5

TOTAL LABOR 50.0

TRAVEL TYPE RATE UNIT USEAGE Miles Free

Truck $97.00 day 1 $97.00

TOTAL VEHICLE $97.00

SUBCONTRACTOR

Equipment Procurement

NAME PURPOSE COST UNIT USEAGE

Services Procurement

NAME PURPOSE COST UNIT USEAGE

Gulf Coast IDW disposal $95.00 drum 1 $95.00

TOTAL SUBS $95.00

LABORATORY

PARAMETER RATE # SAMPLES #QAQC

EPA method 8260 VOHs $66.00 13 $858.00 mple shipping (Two Day - large cooler) $60.00 1 $60.00

TOTAL LAB $918.00

FIELD EXPENSES ITEM RATE UNIT USEAGE TOTALS

Field Equipment

Expendables $32.50 Day 1 $32.50 Sub-Total $32.50

Diffusion sampler each (small well) $22.35 each 7 $156.45 Groundwater Sampling Kit $208.55 day 1 $208.55 Poly Tubing $0.25 ft 277 $69.25 Silicon Tubing $2.00 ft 6 $12.00 Drum $58.20 drum 1 $58.20

Sub-Total $504.45

TOTAL EQUIPMENT $536.95

TA_009o.xlsx\sub 2 Page 3 5/26/20214:51 PM

COST PROPOSAL FOR TASK DC009o < West Side Cleaners, 489502256 ERIC_5025>

Groundwater Monitoring

1. INTRODUCTION:

A Soil Vapor Extraction (SVE) system was operated at the West Side Cleaners site until late 2015. At that time, the system was shutdown and soil confirmation sampling was conducted.

Since the drycleaner was still active and utilized PCE in its operation, continued system shutdown was recommended along with periodic groundwater monitoring. Task DC009o includes annual groundwater monitoring in accordance with GHD recommendations and Department approval dated September 22, 2020.

Subtask 1: Project Management Includes all tasks associated with project management for completion of groundwater sampling and reporting.

Subtask 2: Groundwater Monitoring Subtask 2 includes annual groundwater sampling in July 2021. Prior to groundwater sampling, depth to water measurements will be gathered from all available site monitor wells (31 total). During the previous sampling in July 2019, GHD personnel installed passive diffusion bags (PDB) at select site monitor wells. As such, PDB sampling is proposed at seven

(7) site monitor wells including MW014, MW018, MW021, MW023, MW024, MW026, and MW027. In addition to the use of existing PDBs, GHD will also sample monitoring wells MW003, MW005, MW007, MW009, MW015, and MW028 using conventional methods per FDEP recommendations. These wells do not contain diffusion bags. All samples will be submitted to a Florida-certified laboratory and analyzed for the presence of volatile organic halocarbons by EPA Method 8260.

Upon receipt of analytical data, a summary report will be prepared. The summary report will include a detail of field sampling methodology, a summary of groundwater elevation data and flow interpretations, as well as a summary of groundwater analytical results. The report will also include conclusions and recommendations for additional monitoring and/or remedial activities.

Deliverables:

Deliverable Deliverable Due Date

Groundwater Monitoring Report 9/9/21

Gulf Coast Vacuum Truck Services 1744 Williams Ditch Rd

Cantonment, FL 32533 US

+1 8504500058 accounting@gcvts.net

Estimate

ADDRESS

GHD

ESTIMATE 1040

DATE 04/15/2021

DATE SERVICE DESCRIPTION QTY RATE AMOUNT

Drum Disposal Disposal of of 1 drum of contaminated water.

1 95.00 95.00

Island Cleaners - Sanibel TOTAL $95.00

Accepted By

Accepted Date

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Brian Moore

GHD

5904 Hampton Oaks Parkway – Suite F

Tampa, FL 33610

April 15, 2021

Re: Non-Hazardous Drum Disposal Quote – South and Central Florida

Mr. Moore:

The price for disposal of drums of non-hazardous soil or groundwater located in south and central

Florida will be $100.00 per drum, total, for both transportation and disposal.

Pricing for the Florida Keys will be quoted separately on a case-by-case basis.

This quote is valid for 180 days.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

ID Task Mode

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Fri 5/21/21 Thu 6/3/21

2 Subtask 1: Project Management

71 days Thu 6/3/21 Thu 9/9/21

3 Subtask 2:

Groundwater Monitoring

51 days Thu 7/1/21 Thu 9/9/21

4 Field Work Preparation2 wks Thu 7/1/21 Wed 7/14/21

5 Groundwater Sampling1 day Thu 7/22/21 Thu 7/22/21

6 Groundwater Monitoring Report

6 wks Fri 7/30/21 Thu 9/9/21

5/9 5/16 5/23 5/30

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC009o at the Westside Cleaners facility located in Orlando, Orange County

Project: TA_009o Date: Fri 5/21/21

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Fri 5/21/21 Thu 6/3/21

2 Subtask 1: Project Management

71 days Thu 6/3/21 Thu 9/9/21

3 Subtask 2:

Groundwater Monitoring

51 days Thu 7/1/21 Thu 9/9/21

4 Field Work Preparation2 wks Thu 7/1/21 Wed 7/14/21

5 Groundwater Sampling1 day Thu 7/22/21 Thu 7/22/21

6 Groundwater Monitoring Report

6 wks Fri 7/30/21 Thu 9/9/21

6/6 6/13 6/20 6/27 3rd Quart

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC009o at the Westside Cleaners facility located in Orlando, Orange County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Fri 5/21/21 Thu 6/3/21

2 Subtask 1: Project Management

71 days Thu 6/3/21 Thu 9/9/21

3 Subtask 2:

Groundwater Monitoring

51 days Thu 7/1/21 Thu 9/9/21

4 Field Work Preparation2 wks Thu 7/1/21 Wed 7/14/21

5 Groundwater Sampling1 day Thu 7/22/21 Thu 7/22/21

6 Groundwater Monitoring Report

6 wks Fri 7/30/21 Thu 9/9/21

Jeremy Hess

Skylar Albritton,Will

7/4 7/11 7/18 7/25 ter

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC009o at the Westside Cleaners facility located in Orlando, Orange County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Fri 5/21/21 Thu 6/3/21

2 Subtask 1: Project Management

71 days Thu 6/3/21 Thu 9/9/21

3 Subtask 2:

Groundwater Monitoring

51 days Thu 7/1/21 Thu 9/9/21

4 Field Work Preparation2 wks Thu 7/1/21 Wed 7/14/21

5 Groundwater Sampling1 day Thu 7/22/21 Thu 7/22/21

6 Groundwater Monitoring Report

6 wks Fri 7/30/21 Thu 9/9/21 iam Ouchie

8/1 8/8 8/15 8/22

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC009o at the Westside Cleaners facility located in Orlando, Orange County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Fri 5/21/21 Thu 6/3/21

2 Subtask 1: Project Management

71 days Thu 6/3/21 Thu 9/9/21

3 Subtask 2:

Groundwater Monitoring

51 days Thu 7/1/21 Thu 9/9/21

4 Field Work Preparation2 wks Thu 7/1/21 Wed 7/14/21

5 Groundwater Sampling1 day Thu 7/22/21 Thu 7/22/21

6 Groundwater Monitoring Report

6 wks Fri 7/30/21 Thu 9/9/21 Brian Moore,Jeremy Hess,Peter McLea

8/29 9/5 9/12 9/19

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC009o at the Westside Cleaners facility located in Orlando, Orange County

Task Assignment Notification
BWC Task Assignment Form (Rev 02_17).pdf
Task Assignment Notification
BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf
Deliverable & Invoice Schedule

File details come from the government source that posted it. Updated .