This is a Task Assignment Notification Form for DEP Contract No. HW555, issued by the Florida Department of Environmental Protection (FDEP) to GHD Services, Inc. for groundwater monitoring services at the Boston Man Cleaners site located at 6081 West Sunrise Boulevard, Sunrise, Broward County, Florida. The contract is managed by Kevin Kane (FDEP Contract Manager) and Brian Moore (Contractor Representative), with the site designated as ERIC_4086. The task assignment was executed on May 18-19, 2021, and is part of the state's indefinite delivery vehicle for environmental remediation services.

Task Assignment DC006L requires GHD Services, Inc. to conduct annual groundwater sampling and analysis at five monitoring wells (MW001, MW010, MW015, MW016, and MW018), with water level measurements taken from all 18 site monitor wells. Samples will be analyzed for volatile organic hydrocarbons using EPA Methods 8021/8260. The deliverable is a Groundwater Monitoring Report due August 20, 2021, with task completion by November 19, 2021. The task is structured as a fixed-price assignment with a total not-to-exceed amount of $5,744.26, broken down as $5,744.26 in fixed price with no cost reimbursement, fee schedule, or retainage. Costs include direct labor ($1,491.95), overhead (113% at $1,685.90), general and administrative charges (28% at $417.75), fringe benefits (25.50% at $380.45), travel ($366.00), laboratory analytical services ($431.00), subcontractor services including IDW disposal ($104.50), field equipment and expendables ($394.50), and a completion fee ($397.61). Invoice is due upon completion of groundwater sampling activities and FDEP approval of the Groundwater Monitoring Report.

View the file

Other files

File Type Posted
CN-370000-HW552-SS11SCO1.pdf PDF
CN-370000-HW555-A2.pdf PDF
CN-370000-HW555-A6.pdf PDF
CN-370000-HW555-A8.pdf PDF
CN-370000-HW555-A9.pdf PDF
CN-370000-HW555-CO3.pdf PDF
CN-370000-HW555-DC001I.pdf.crdownload CRDOWNLOAD file
CN-370000-HW555-DC004J.pdf PDF
CN-370000-HW555-DC007J.pdf PDF
CN-370000-HW555-DC009o.pdf PDF
CN-370000-HW555-DC011G.pdf PDF
CN-370000-HW555-DC012J.pdf PDF
CN-370000-HW555-DC013F.pdf PDF
CN-370000-HW555-DC015H.pdf PDF
CN-370000-HW555-DC019F.pdf PDF
CN-370000-HW555-DC019H.pdf PDF
CN-370000-HW555-DC019J.pdf PDF
CN-370000-HW555-DC01ACO4.pdf PDF
CN-370000-HW555-DC01ACO5.pdf PDF
CN-370000-HW555-DC01ACO7.pdf PDF
CN-370000-HW555-DC01D.pdf PDF
CN-370000-HW555-DC01F.pdf PDF
CN-370000-HW555-DC01G.pdf PDF
CN-370000-HW555-DC020D.pdf PDF
CN-370000-HW555-DC023L.pdf PDF
CN-370000-HW555-DC027F.pdf PDF
CN-370000-HW555-DC027J.pdf PDF
CN-370000-HW555-DC02B.pdf PDF
CN-370000-HW555-DC02G.pdf PDF
CN-370000-HW555-DC02H.pdf PDF
CN-370000-HW555-DC02HCO1.pdf PDF
CN-370000-HW555-DC02HCO2.pdf PDF
CN-370000-HW555-DC02ICO1.pdf PDF
CN-370000-HW555-DC02ICO3.pdf PDF
CN-370000-HW555-DC02ICO4.pdf PDF
CN-370000-HW555-DC02J.pdf PDF
CN-370000-HW555-DC02O.pdf PDF
CN-370000-HW555-DC030G.pdf PDF
CN-370000-HW555-DC032E.pdf PDF
CN-370000-HW555-DC034P.pdf PDF
CN-370000-HW555-DC035Q.pdf PDF
CN-370000-HW555-DC03C.pdf PDF
CN-370000-HW555-DC03H.pdf PDF
CN-370000-HW555-DC03K.pdf PDF
CN-370000-HW555-DC03i.pdf PDF
CN-370000-HW555-DC041C.pdf PDF
CN-370000-HW555-DC045H.pdf PDF
CN-370000-HW555-DC046A.pdf PDF
CN-370000-HW555-DC049A.pdf PDF
CN-370000-HW555-DC049I.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP CONTRACT NO.

Task Assignment #: Module #: Grant #:

Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #:

DEP Site #:

Site Name:

Address(Street, City, County):

Phase:

Task Description [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverables:

Final Deliverable Due Date:

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

FIXED FEE

RETAINAGE:

TOTAL TASK ASSIGNMENT VALUE: $0.00

DEP Task Manager:

DEP Contract Manager:

Contractual Authority:

Contractor Representative:

CC: Procurement Section (MS 93) Section Representative ________

TASK ASSIGNMENT NOTIFICATION FORM

COST PLUS FIXED FEE

COST REIMBURSEMENT

FIXED PRICE FEE SCHEDULE

Period of Performance:

Execution of Task Assignment through:

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

WCP TAFORM 01_18

HW555

D000 N/ADC006L

GHD Services, Inc.

Brian Moore

(850) 245-8971Kevin Kane

ERIC_4086

Boston Man Cleaners

6081 West Sunrise Boulevard, Sunrise, Broward County

Monitoring

GHD Services, Inc. will conduct groundwater sampling in accordance with the May 2021 scope of work and cost proposal. Groundwater Monitoring Report will be generated.

Groundwater Monitoring Report

08/20/2021

11/19/2021

$ 5,744.26 $ 0.00 $ 0.00 $ 0.00

$ 0.00

Kevin Kane Digitally signed by Kevin Kane Date: 2021.05.18 14:27:50 -04'00'

Kevin Kane Digitally signed by Kevin Kane Date: 2021.05.18 14:28:13 -04'00'

William Burns Digitally signed by William Burns Date: 2021.05.18 15:36:15 -04'00'

Brian Moore Digitally signed by Brian Moore Date: 2021.05.19 10:02:39 -04'00'

$ 5,744.26

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01-2018

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Groundwater Monitoring Report 08/20/2021

Upon completion of groundwater sampling activities and FDEP approval of Groundwater Monitoring Report $ 5,744.26

$ 5,744.26

HW555

DC006L

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Noah Valenstein Secretary

TO: HW555 Contract File Boston Man Cleaners

ERIC_4086

Sunrise, Broward County

FROM: Kevin Kane, Contract Manager

DATE: May 18, 2021

SUBJECT: Task Assignment Summary

HW555 DC006L

Monitoring

GHD Services, Inc. will conduct groundwater sampling. Specific subtasks are detailed below:

Subtask 1: Project Management Project management is calculated at 12.5 percent of the direct labor.

Subtask 2: Groundwater Monitoring Groundwater sampling will be conducted at 5 monitoring wells. Additionally, water level measurements will be taken from all monitor wells present on site (18 total). All samples will be analyzed for the presence of VOHs by EPA Method 8021/8260. IDW disposal is expected for this site and has been accounted for under this subtask. Following receipt of analytical results, a Groundwater Monitoring Report will be generated and submitted to the Department.

This work will be conducted in accordance with the scope of work included in the GHD proposal, received May 17, 2021.

Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and the GHD proposal. The final deliverable due date is August 20, 2021, and the completion date for the Task Assignment is November 19, 2021.

The final cost total for Task Assignment DC006K is $5,744.26.

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 05/18/21

Task #: DC006L SubTask 1 Project Management SubTask 6

Site: Boston Man Cleaners SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$69.71 Project Manager BM 2.38 2.378 $0.00 President/V.P 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$69.71 Sr. Professional Engineer BM 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$40.00 Professional Engineer/Geologist ES 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $42.64 Professional Engineer/Geologist GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $49.00 Professional Engineer/Geologist KC 12.50 12.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.72 Staff Engineer/Scientist BG 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.91 Project Manager/Engineer SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $28.29 Staff Engineer/Scientist AW 14.50 14.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Senior Computer Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Field Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$28.85 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.18 Junior Technician SA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $17.51 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.82 Drafting Technician PM 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Senior Assistant/Accounting 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.14 Staff Assistant SS 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Computer Specialist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Hours 42.38 2.378 40.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $1,491.95 $165.77 $1,326.18 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 113.00% $1,685.90 $187.32 $1,498.58 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 28.00% $417.75 $46.42 $371.33 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 25.50% $380.45 $42.27 $338.18 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $3,976.05 $441.78 $3,534.27 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $74.60 $8.29 $66.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Travel

REV: 02/03 CEF GHD Services Inc. Page 1

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 05/18/21

Task #: DC006L SubTask 1 Project Management SubTask 6

Site: Boston Man Cleaners SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Vehicle Rental $194.00 $194.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $172.00 $172.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $366.00 $366.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $95.00 $95.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $95.00 $95.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $9.50 $9.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $104.50 $104.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $396.00 $396.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $35.00 $35.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $431.00 $431.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $65.00 $65.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $329.50 $329.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $394.50 $394.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $5,346.65 $450.07 $4,896.58 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $397.61 $44.18 $353.43 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $5,744.26 $494.25 $5,250.01 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF GHD Services Inc. Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET Sub 2

SITE : Boston Man Cleaners

PROJECT NUMBER: 11158286

FDEP NO: 069500621 ERIC_4086

SUBTASK: Groundwater Monitoring

DATE: 5/18/2021

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr Professional Engineer BM Conclusions/Recommendations 1

Professional Geologist KC Sample kit coordination/contact property owner 1 Professional Geologist KC Verify COC/field sampling parameters/field notes 0.5 Professional Geologist KC Arrange for IDW disposal 1 Professional Geologist KC Historical assessment and remedial summary 1 Professional Geologist KC Field sampling scope of work and methodology 1 Professional Geologist KC Field parameter evaluation/discussion 1 Professional Geologist KC groundwater flow evaluation (shallow, intermediate, deep) 2.5 Professional Geologist KC groundwater analytical evaluation (shallow, intermediate, deep) 2.5 Professional Geologist KC QA/QC data verification 1 Professional Geologist KC Conclusions/Recommendations 1

12.5

Staff Engineer/Scientist AW Mob/demob from Ft Myers 4 Staff Engineer/Scientist AW Water Levels all wells (18 total) 3 Staff Engineer/Scientist AW Groundwater Sampling (5 wells) 7.5

14.5

Drafting Technician PM Groundwater flow maps (shallow, intermediate, deep) 3 Drafting Technician PM Groundwater analytical maps (shallow, intermediate, deep) 3

Staff Assistant SS Data Entry (7 wells and 18 water levels) 1 Staff Assistant SS Generate summary tables 1 Staff Assistant SS Document Preparation/Publishing (generate pdf) 2 Staff Assistant SS ADAPT/GIS Update 2

TOTAL LABOR 40

TRAVEL TYPE RATE UNIT USEAGE Miles Free

Truck $97.00 day 2 $194.00

TOTAL VEHICLE $194.00

PER DIEM TYPE RATE UNIT USEAGE Miles Free

Hotel $100.00 day 1 $100.00 Per Diem $36.00 day 2 $72.00

TOTAL VEHICLE $172.00

SUBCONTRACTOR

Equipment Procurement

NAME PURPOSE COST UNIT USEAGE

Services Procurement

NAME PURPOSE COST UNIT USEAGE

Gulf Coast IDW drum disposal $95 drum 1 $95.00

TOTAL SUBS $95.00

LABORATORY

PARAMETER RATE # SAMPLES #QAQC

VOHS EPA 8260 $66.00 5 1 $396.00

Sample Shipping small cooler (2 day) $35.00 1 $35.00

TOTAL LAB $431.00

FIELD EXPENSES ITEM RATE UNIT USEAGE TOTALS

Field Equipment

Expendables $32.50 Day 2 $65.00 Sub-Total $65.00

Groundwater Sampling Kit $208.55 Day 1 $208.55 Poly Tubing $0.25 ft 211 $52.75 55-gallon drum $58.20 drum 1 $58.20 silicon Tubing $2.00 ft 5 $10.00

Sub-Total $329.50

TOTAL EQUIPMENT $394.50

TA_006L\sub 2 Page 1 5/18/202111:47 AM

COST PROPOSAL FOR TASK DC006K

Boston Man Cleaners, 069500621

Groundwater Monitoring (Annual)

1. INTRODUCTION: <DISCUSS SCOPE OF WORK, DATES >

GHD completed active remediation at the Boston Man Cleaners site in 2008. Active remediation included the operation of a Soil Vapor Extraction (SVE) system. Groundwater monitoring has been conducted following active remediation. The first year of groundwater monitoring was completed in April 2009. Task DC006L includes annual groundwater monitoring in accordance with GHD recommendations and FDEP correspondence dated August 28, 2020.

Subtask 1: Project Management Subtask 1 includes all activities associated with completion of groundwater sampling and reporting for the Boston Man Cleaners site.

Subtask 2: Groundwater Monitoring

Task DC006L includes annual groundwater monitoring in accordance with GHD recommendations and Department approval. Annual groundwater monitoring will be conducte at monitoring wells MW001, MW010, MW015, MW016, and MW018. Prior to sampling, depth to water measurements will be gathered from all available site monitor wells (18 total). Groundwater sampling will be conducted in general accordance with FDEP Standard Operating Procedures. Groundwater samples will be analyzed for the presence of volatile organic hydrocarbons by EPA Method 8021/8260.

The results of the sampling will be summarized in a groundwater monitoring report that will be submitted to the Department for approval. The groundwater monitoring report will include a summary of field and laboratory data. The report will also include recommendations for additional sampling.

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

Groundwater Monitoring Report 8/20/21

Gulf Coast Vacuum Truck Services 1744 Williams Ditch Rd

Cantonment, FL 32533 US

+1 8504500058 accounting@gcvts.net

Estimate

ADDRESS

GHD

ESTIMATE 1040

DATE 04/15/2021

DATE SERVICE DESCRIPTION QTY RATE AMOUNT

Drum Disposal Disposal of of 1 drum of contaminated water.

1 95.00 95.00

Island Cleaners - Sanibel TOTAL $95.00

Accepted By

Accepted Date

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Brian Moore

GHD

5904 Hampton Oaks Parkway – Suite F

Tampa, FL 33610

April 15, 2021

Re: Non-Hazardous Drum Disposal Quote – South and Central Florida

Mr. Moore:

The price for disposal of drums of non-hazardous soil or groundwater located in south and central

Florida will be $100.00 per drum, total, for both transportation and disposal.

Pricing for the Florida Keys will be quoted separately on a case-by-case basis.

This quote is valid for 180 days.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

ID Task Mode

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 5/17/21Fri 5/28/21

2 Subtask 1: Project Management

60 days Mon 5/31/21

Fri 8/20/21

3 Subtask 2: Groundwater Monitoring

50 days Mon 6/14/21

Fri 8/20/21

4 Field Work Preparation 2 wks Mon 6/14/21Fri 6/25/21

5 Groundwater Sampling 2 days Thu 7/1/21 Fri 7/2/21

6 Groundwater Monitoring Report

6 wks Mon 7/12/21

Fri 8/20/21

5/9 5/16 5/23 5/30 June

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC006L at the Boston Man Cleaners site located in Sunrise, Broward County

Project: TA_006L Date: Mon 5/17/21

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 5/17/21Fri 5/28/21

2 Subtask 1: Project Management

60 days Mon 5/31/21

Fri 8/20/21

3 Subtask 2: Groundwater Monitoring

50 days Mon 6/14/21

Fri 8/20/21

4 Field Work Preparation 2 wks Mon 6/14/21Fri 6/25/21

5 Groundwater Sampling 2 days Thu 7/1/21 Fri 7/2/21

6 Groundwater Monitoring Report

6 wks Mon 7/12/21

Fri 8/20/21

Ken Caldwell

A

6/6 6/13 6/20 6/27 July

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC006L at the Boston Man Cleaners site located in Sunrise, Broward County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 5/17/21Fri 5/28/21

2 Subtask 1: Project Management

60 days Mon 5/31/21

Fri 8/20/21

3 Subtask 2: Groundwater Monitoring

50 days Mon 6/14/21

Fri 8/20/21

4 Field Work Preparation 2 wks Mon 6/14/21Fri 6/25/21

5 Groundwater Sampling 2 days Thu 7/1/21 Fri 7/2/21

6 Groundwater Monitoring Report

6 wks Mon 7/12/21

Fri 8/20/21

Andrew Wyatt

7/4 7/11 7/18 7/25

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC006L at the Boston Man Cleaners site located in Sunrise, Broward County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 5/17/21Fri 5/28/21

2 Subtask 1: Project Management

60 days Mon 5/31/21

Fri 8/20/21

3 Subtask 2: Groundwater Monitoring

50 days Mon 6/14/21

Fri 8/20/21

4 Field Work Preparation 2 wks Mon 6/14/21Fri 6/25/21

5 Groundwater Sampling 2 days Thu 7/1/21 Fri 7/2/21

6 Groundwater Monitoring Report

6 wks Mon 7/12/21

Fri 8/20/21 Ken Caldwell,Brian

8/1 8/8 8/15 8/22 August

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC006L at the Boston Man Cleaners site located in Sunrise, Broward County

Task Assignment Notification
BWC Task Assignment Form (Rev 02_17).pdf
Task Assignment Notification
BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf
Deliverable & Invoice Schedule

File details come from the government source that posted it. Updated .