CM162633 T_Hangar Repairs Bldg 409_Specs 09911.pdf
PDF 57 KB Posted
- Attached to
- T-HANGAR EMERGENCY DOOR FRAME REPAIRS, BLDG 409
- Solicitation number
- Q26003366
- Issued by
- Maui County, Hawaii
About this file
This is a specification document for exterior painting work on Building 409 at Kahului Airport in Hawaii, associated with T-Hangar emergency door frame repairs. The project, identified as State Project No. CM1626-33, requires surface preparation and application of paint systems to structural steel substrates. The work includes all design, shop drawings, materials, labor, construction, placement, and finishing necessary to complete the exterior painting scope. The specification mandates compliance with MPI (Master Painters Institute) standards and the MPI Architectural Painting Specification Manual for all preparation and workmanship. Contractors must submit product data, samples for each paint system and color/gloss combination, and a current MPI Approved Product List with proposed products highlighted. Acceptable manufacturers include Benjamin Moore & Co. and Sherwin-Williams Company or approved equals.
The painting system specified for structural steel substrates follows the MPI EXT 5.1L schedule, consisting of three coats: a zinc-rich inorganic primer, an epoxy high-build intermediate coat, and a two-component polyurethane topcoat with pigmented gloss finish. All materials must comply with VOC limits established by local authorities and match existing colors. Surface preparation requires removal of rust and loose mill scale from steel substrates using methods recommended by the paint manufacturer, with careful attention to cleaning away dirt, oil, grease, and incompatible existing coatings. The contract work is measured and paid on a lump sum basis for item 09911 (Exterior Painting). Contractors must provide five percent extra materials, minimum one gallon of each color applied, packaged and labeled for storage. The owner reserves the right to conduct dry film thickness testing, with contractors responsible for costs if results show non-compliance with manufacturer specifications and required to apply additional coats at their expense.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
T-HANGAR EMERGENCY REPAIRS, BUILDING 409
KAHULUI AIRPORT Exterior Painting
STATE PROJECT NO. CM1626-33 09911-1
DIVISION 9 - FINISHES
SECTION 09911 – EXTERIOR PAINTING
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
The General Provisions, Special Provisions and General Requirements of the Specifications, apply to the work specified in this Section.
1.02 DESCRIPTION OF WORK
A. This section includes, but not limited to, all the design, shop drawings, materials, labor, construction, placement and finishing of all structural steel necessary to complete the project.
B. Related Sections:
1. Section 05120 – STRUCTURAL STEEL
1.03 SUMMARY
A. This Section includes surface preparation and application of paint systems on the following substrates:
1. Structural steel.
1.04 SUBMITTALS
A. Product Data: For each type of product indicated. Include preparation requirements and application instructions.
B. Samples: For each type of paint system and each color and gloss of topcoat.
C. Product List: For each product indicated. Include printout of current “MPI Approved Product List” for each product category specified, with the proposed product highlighted.
STATE PROJECT NO. CM1626-33 09911-2
1.05 QUALITY ASSURANCE
A. MPI Standards:
1. Products: Comply with MPI standards indicated and listed in “MPI Approved Products List.”
2. Preparation and Workmanship: Comply with requirements in "MPI Architectural Painting Specification Manual" for products and paint systems indicated.
1.06 DELIVERY, STORAGE, AND HANDLING
A. Store materials not in use in tightly covered containers in well-ventilated areas with ambient temperatures continuously maintained at not less than 45 deg F (7 deg C).
1. Maintain containers in clean condition, free of foreign materials and residue.
2. Remove rags and waste from storage areas daily.
1.07 EXTRA MATERIALS
A. Furnish extra materials that match products installed and that are packaged with protective covering for storage identified with labels describing contents.
1. Paint: 5 percent, but not less than 1 gallon of each material and color applied.
PART 2 - PRODUCTS
2.01 MANUFACTURERS
A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following or approved equal:
1. Benjamin Moore & Co.
2. Sherwin-Williams Company (The).
STATE PROJECT NO. CM1626-33 09911-3
2.02 PAINT, GENERAL
A. MPI Standards: Provide products that comply with MPI standards indicated and that are listed in its "MPI Approved Products List."
B. Material Compatibility:
1. Provide materials for use within each paint system that are compatible with one another and substrates indicated, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience.
2. For each coat in a paint system, provide products recommended in writing by manufacturers of topcoat for use in paint system and on substrate indicated.
C. VOC Content: Provide materials that comply with VOC limits of authorities having jurisdiction.
D. Colors: Match existing.
2.03 PRIMERS/SEALANTS
A. Primer, Zinc-Rich, Inorganic: MP #19.
2.04 TOPCOATS
A. Epoxy, High Build, Low Gloss, MPI #108.
B. Polyurethane, Two-Component, Pigmented, Gloss, MPI #72.
PART 3 - EXECUTION
3.01 EXAMINATION
A. Examine substrates and conditions, with Applicator present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work.
B. Verify suitability of substrates, including surface conditions and compatibility with existing finishes and primers.
C. Proceed with coating application only after unsatisfactory conditions have been corrected.
1. Application of coating indicates acceptance of surfaces and conditions.
STATE PROJECT NO. CM1626-33 09911-4
3.02 PREPARATION
A. Comply with manufacturer's written instructions and recommendations in "MPI Manual" applicable to substrates and paint systems indicated.
B. Remove plates, machined surfaces, and similar items already in place that are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection before surface preparation and painting.
1. After completing painting operations, use workers skilled in the trades involved to reinstall items that were removed. Remove surface-applied protection if any.
2. Do not paint over labels of independent testing agencies or equipment name, identification, performance rating, or nomenclature plates.
C. Clean substrates of substances that could impair bond of paints, including dirt, oil, grease, and incompatible paints and encapsulants.
1. Remove incompatible primers and reprime substrate with compatible primers as required to produce paint systems indicated.
D. Steel Substrates: Remove rust and loose mill scale. Clean using methods recommended in writing by paint manufacturer.
3.03 APPLICATION
A. Apply paints according to manufacturer's written instruction and recommendations in "MPI Manual."
B. Apply paints to produce surface films without cloudiness, spotting, holidays, laps, brush marks, roller tracking, runs, sags, ropiness, or other surface imperfections.
Cut in sharp lines and color breaks.
3.04 FIELD QUALITY CONTROL
A. Dry Film Thickness Testing: Owner may engage the services of a qualified testing and inspecting agency to inspect and test paint for dry film thickness.
B. Contractor shall touch up and restore painted surfaces damaged by testing. If test results show that dry film thickness of applied paint does not comply with paint manufacturer's written recommendations, Contractor shall pay for testing and apply additional coats as needed to provide dry film thickness that complies with paint manufacturer's written recommendations.
STATE PROJECT NO. CM1626-33 09911-5
3.05 CLEANING AND PROTECTION
A. Protect work of other trades against damage from paint application. Correct damage to work of other trades by cleaning, repairing, replacing, and refinishing, as approved by the State, and leave in an undamaged condition.
B. At completion of construction activities of other trades, touch up and restore damaged or defaced painted surfaces.
3.06 EXTERIOR PAINTING SCHEDULE
A. Structural Steel Substrate, Polyurethane, Pigmented System (MPI EXT 5.1L)
1. Application; Typical for exterior ferrous metals.
2. Prime Coat: Primer, Zinc-Rich, Inorganic.
3. Intermediate Coat: Epoxy, High Build, Gloss.
4. Topcoat: Polyurethane, Two-Component, Pigmented, Gloss.
PART 4 - MEASUREMENT AND PAYMENT
4.01 BASIS OF MEASUREMENT AND PAYMENT
Work under this Section will not be measured for payment but will be paid for at the Contract Lump Sum Price.
Item No. Item Unit
09911 Exterior Painting Lump Sum
END OF SECTION