STATEMENT OF WORK
NAVY LODGE (BLDG 99) HURRICANE ROOF REPAIRS, NAS CORPUS CHRISTI, TX
1. GENERAL DESCRIPTION: The Contractor shall provide all supervision, transportation, labor, materials, equipment and incidental work necessary to restore and repair the leaking roof. See paragraph 5 for detailed statement work. The contractor shall comply with
UFGS 01 31 23.13 20 Electronic Construction and Facility Support Contract Management
System for the administration of this contract. See Paragraph 16 for specifics.
2. LOCATION: The work is located at the Navy Lodge (Building 99), Corpus Christi, Texas. See Attachment A for project locations.
3. PERIOD OF PERFORMANCE: The period of performance is 90 calendar days. The period of performance is negotiable; hence, if the contractor believes a different/longer period of performance is needed, they should negotiate this with the Contract Specialist prior to award.
4. ATTACHMENTS:
Attachment Title
A Project Location
B Solid Waste Summary Sheet
C Roof Photos
D Attic Photos
E Room Photos
F As-built Drawings
G Spill Response Poster
5. SCOPE OF WORK: The services that the contractor shall provide include furnishing all supervision, transportation, equipment, labor and materials required to restore and repair the leaking roof.
Contractor shall NOT complete any Porte-Cochere Roof Repairs located over the Main
Entrance of the Navy Lodge. The area below the Porte-Cochere and the surrounding structure are currently off limits due to structural instability. The Porte-Cochere roof repairs are NOT covered within this project.
Contractor shall follow all environmental mitigation and protection practices that will take place to contain displaced materials and protect storm drains. Contractor shall ensure that
ANY liquid materials on site are off of the ground, covered and away from storm drains.
Contractor shall cover and protect storm drains if needed and approved in the stormwater pollution prevention protection plan.
Contractor shall ensure that any waste water from sandblasting/power washing must first be filtered to minimize associated paint flakes, rust, and metal particles, and then routed to the sanitary sewer.
Contractor shall provide all safety equipment including fall protection to comply with all
OSHA regulations, company safety program, and commonly accepted safety practices.
Contractor shall provide all hoisting required for loading and unloading materials from the work site.
Contractor shall implement safety measures to protect all residents and guests from objects falling off the roof. Contractor shall post warning signs on all entrances and exits of the building that state “Men Working Above”. Contractor shall place restricted cones and red tape around the working area to make all residents and guests aware of all hazards involved.
Contractor shall ensure Navy Lodge provides a printed letter to all residents and guests upon arrival to make them aware of the work being performed on the building especially for families with kids. The playground will be affected due to the playground’s close proximity to the Navy Lodge roof.
Work tasks shall include the following:
a. Contractor shall replace any loose, missing, deteriorated, discolored or damaged shingles on the entire roof with new composition shingles to match existing color and design. The total area of new composition shingles installed shall not exceed 1,500 square feet.
b. Contractor shall replace all composite shingles and replace underlayment on the two jetty roofs near the front main entrance and the rear entrance of the building. The area of both jetty roof are approximately 350 square feet of the 1,500 square feet total. The total area of underlayment is approximately 350 square feet.
c. Contractor shall replace any loose, missing, deteriorated, discolored or damaged ridge cap shingles with new ridge cap shingles to match existing color and design. The total length of new ridge cap shingles installed shall not exceed 500 linear feet. The 500 linear feet of new ridge cap shingles are additional to the 1,500 square feet of new composite shingles.
d. Contractor shall reseal all roof vent pipes, reseal all flashing around laundry chute vent and replace metal cap with vent and screen on laundry chute vent.
e. Contractor shall replace the corroded vent caps on the roof vent pipes of the first floor
Mechanical Room 515.
f. Contractor shall replace the missing downspout (rectangular 4”x5” prefinished sheet metal with 4” PVC downspout in wall) near the rear of the elevator tower roof. The total length of the downspout is approximately 25 linear feet.
g. Contractor shall fabricate and install new 24-gauge metal edge flashing to replace any damaged metal edge flashing. The total length of the new metal edge flashing installed shall not exceed 60 linear feet.
h. Contractor shall clean gutter system then apply sealant at all gutter joints. The total length of the gutter system to reseal is approximately 970 linear feet.
i. Contractor shall test the entire roofing system for leaks and proper drainage after completing all work. Contractor must consult with the Contracting Officer if any leaks or improper drainage of entire roofing system exists to correct any malfunctions.
5.1. The Contracting Officer will appoint a Facilities Engineering and Acquisition Point of
Contact (FEAD POC). The contractor shall only take direction from the contracting officer or FEAD POC. The contractor shall contact the FEAD POC to schedule the preconstruction meeting.
5.2. All work shall be performed in compliance with the latest edition of Unified Facilities
Criteria, UFC 1-200-01 DoD Building Code, UFC 3-101-01 Architecture with Change
5, UFC 3-110-03 Roofing with Change 4, UFC 3-301-01 Structural Engineering, UFC
3-600-01 section 34-11 Roof coverings, National Roofing Contractors Association
Roofing Manuals, 2018 International Building Code, 2018 International Plumbing
Code, 2018 International Existing Building Code, National Fire Protection Agency requirements, 2017 National Electric Code, Whole Building Design Guide, and the
Installation Design Guide. All products shall be installed according to manufacturer’s recommendations.
5.3. Licensing Requirements: All work is to be accomplished with a licensed journeyman roofing company that has met all current city & state certifications or license requirements to accomplish the specified work.
5.4. Submittals: Submittals shall be provided and approved prior to delivery to the job site.
a. Composite Shingles.
b. Underlayment.
c. Roof Flashing.
d. Roof Flashing Sealant.
e. Metal Downspout with PVC Drain.
Work Schedule (to include start date and ending date of all major activities).
The approval or acceptance of submittals is not to be construed as a complete check, but rather indicates only that the general method of construction, materials, detailing and other information are satisfactory. Approval or acceptance will not relieve the
Contractor of the responsibility for any error, which may exist, as the Contractor is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work.
6. EXAMINATION OF SITE: Bidders are expected to visit the site, take their own measurements, inspect the work area carefully and satisfy themselves as to the character and amount of work to be done. The contractor shall report any discrepancy between the statement of work and existing conditions prior to bid.
7. WORK RESTRICTIONS: The following work restrictions apply to this project:
7.1. Schedule hours: The work shall be scheduled to cause minimum interference to the normal operations of the tenants. Work shall be accomplished between the hours of
7:30 A.M. and 4:30 P.M., Monday through Friday. If the Contractor desires to work on
Saturday, Sunday, holidays, or outside of the Station’s regular hours, a request may be submitted to the FEAD POC for approval.
7.2. Base Access: Base Access can be obtained through a base pass or participating in the
Defense Biometric Identification System (DBIDS) program. A DBIDS pass is required for all prime contractor personnel.
7.2.1. DBIDS (Defense Biometric Identification System): DBIDS is a program in which
Contractor personnel who enroll and are approved, are subsequently granted access to the installation for a period up to one year, or the length of the contract, whichever is less. The Government performs background screening and credentialing. Throughout the year, the Contractor employee must continue to meet background-screening standards. Under the DBIDS program, no commercial vehicle inspection is required, although vehicles may be subject to random inspection. There is no cost to obtain DBIDS credentials.
7.2.2. Base Passes: Participation in the DBIDS is not mandatory for subcontractor personnel or material delivery drivers. However, personnel who do not participate in the DBIDS program will have to obtain a 30-day pass, may be subject to daily mandatory vehicle inspection, and may have limited access to the installation.
There is a four-day lead-time required to obtain a 30-day pass. Only three 30-day passes may be granted in any 12-month period for any one individual. After the three 30-day passes have expired, the individual will not be granted base access unless they participate in the DBIDS program.
7.3. Material deliveries: Material delivery trucks do not necessarily require DBIDS passes, flight line passes, or ramp passes. However, Government personnel must escort any material delivery driver that does not have a DBIDS or base pass. Three (3) workings days’ notice is require to properly planning for Government escort availability. Any material delivery driver that delivering to the flight line or airfield must provide advance notification.
8. PROTECTION OF EXISTING WORK: Existing work to remain shall be protected from damage. Work damaged by the Contractor shall be repaired to original condition at no additional cost to the Government.
9. CONTRACTOR QUALITY (QC) CONTROL: Provide a QC Manager at the work site to implement and manage the QC program. The QC Manager must have a minimum of 2 years combined experience in the following positions: Project Superintendent, QC
Manager, Project Manager, Project Engineer or Construction Manager on similar or larger size and type of construction contracts. The QC Manager must have completed the course entitled "Construction Quality Management (CQM) for Contractors." If the QC Manager does not have a current certification, they must obtain the CQM for Contractors course certification within 90 days of award. The Naval Facilities Engineering Command and the
Army Corps of Engineers periodically offer this course. Contact the Contracting Officer for information on the next scheduled class.
10. SAFETY REQUIREMENTS: The Contractor shall comply with the safety rules and regulations to ensure compliance with applicable OSHA Regulations and U.S. Army
Corps of Engineers Safety and Health Manual EM 385-1-1. Per the EM 385-1-1, the following submittals will be required before construction begins:
a. EMR/DART rates for subcontractors
b. Accident Prevention Plan
c. Activity Hazard Analysis
d. Qualifications of Site Safety Health Officer
e. Monthly man-hour report
The site safety health officer must have completed the 30 hours OSHA Safety Industry
Course. The quality control manager and site safety health officer may be the same person as long as he/she meets the qualifications for the other position.
The contractor shall report total man hours worked upon completion of the project, or at the end of each calendar quarter, whichever comes first.
10.1. Lock out/ Tag Out Policy:
a. Combination locks shall not be used for lockout;
b. No two (2) lockout devices (locks) shall be keyed alike;
c. No more than two (2) keys shall exist for any lock. The worker shall maintain one key, and the supervisor shall maintain the other in a location readily accessible in the event of an emergency;
d. Both lockout and tag-out devices shall indicate the identity of the employee applying the device(s). Tag-out devices shall include the cognizant shop, the telephone number where the employee can be reached during working hours, name of his/her supervisor, date the device was applied, and the machine, equipment, or system component that is de-energized.
11. ASBESTOS AND LEAD: There is no known asbestos containing material (ACM) and/or lead based paint on this project. If additional materials are encountered, which may contain ACM and/or lead, DO NOT TOUCH THE MATERIAL. IMMEDIATELY
NOTIFY THE CONTRACTING OFFICER IN WRITING. If it is determined that ACM and/lead are present and must be disturbed, the Contracting Officer may direct a change accordingly.
12. WEIGHT HANDLING EQUIPMENT (WHE): Also called Load Handling Equipment
(LHE) in the EM385-1-1. The provision of NAVFAC Publication P-307 and EM 385-1-1 apply to all civilian, military, and contractor personnel who operate weight handling equipment and use crane related rigging gear on board Naval Air Station Corpus Christi.
Any equipment carrying a suspended load from a cable is considered weight-handling equipment. Public Works Department Corpus Christi prior to use on the project must inspect all weight handling equipment. A ten (10) day advance notice is required to schedule the inspection. Upon arrival, the contractor shall present the following documentation:
a. NAVFAC Certificate of Compliance Form P-1 (NAVFAC P-307)
b. Crane certification (per ASME B30.5)
c. Operator’s qualification information (per ASME B.30.5 and EM385-1-1)
d. Operator’s medical card (per ASME B30. 5)
e. Rigging gear certification (per ASME B30.9 and ASME B30.26)
f. Lift Plan Form P-2 (NAVFAC P-307)
g. Operator’s daily check list (per crane manufacturer or NAVFAC P-307)
h. Critical Lift Plan form 16-3 (EM385-1-1) where lift exceeds 75% of rated capacity, any blind lift, any lift with more than one crane, or any lift hoisting personnel.
13. PRODUCTS: Products shall be new, manufacturer's standard products, and commonly available from manufacturer's stock.
14. ORAL MODIFICATIONS: No oral statement of any person other than the Contracting
Officer or his/her representative, as provided in the contract clause entitled “Changes” shall in any manner or degree modify or otherwise affect the terms of this contract.
15. CLEANUP: The premises shall be kept free at all times from the accumulation of waste material and/or rubbish resulting from the work. Combustibles shall be removed daily, and upon completion of the work, all debris, tools, and other surplus materials shall be removed and the premises left in approved condition.
16. COMPLIANCE WITH ENVIRONMENTAL LAWS AND REGULATIONS:
Contractor shall comply with all applicable federal, state, and local environmental laws, statutes, regulations, executive orders, permits, and installation regulations and policies.
Contractor shall immediately report any conflicts between applicable federal, state, local environmental laws, statutes, executive orders, and any specifications within this contract to the Government Representative and/or the Installation Environmental Program Director
(IEPD). In the event a regulatory agency assesses either a monetary or non-monetary fine or penalty for Contractor’s noncompliance, the Contractor shall reimburse the government for all associated cost. Ensure all hazardous material and waste is managed and disposed of upon completion of the contract. Under NO, circumstances are hazardous materials and waste to be abandoned or left unattended. The contractor shall bear the cost of any analytical, disposal other costs incurred to manage abandoned or “unknown” waste.
16.1. Environmental Protection Plan (EPP): When required by the Installation Environmental
Program Director, the contractor shall prepare and submit an Environmental Protection
Plan (EPP) to contracting officer for review and approval prior to beginning work under this contract. The EPP must state contractor will comply with all applicable Federal, state and local environmental regulations. Additionally, the EPP must address each of the numbered requirements listed below. Any requirements not applicable to contract must be so indicated as “Not applicable”. A copy of those document(s) and form(s) specifically cited in below requirements must be included as appendices to the EPP.
Submit the Environmental Protection Plan in the following format and include the elements specified below.
Description of the Environmental Protection Plan
(1) General overview and purpose
(a) A brief description of each specific plan required by environmental permit or elsewhere in this contract.
(b) The duties and level of authority assigned to the person(s) on the job site that oversee environmental compliance.
(c) A copy of any standard or project specific operating procedures that will be used to effectively manage and protect the environment on the project site. Communication and training procedures that will be used to convey environmental management requirements to contractor employees and subcontractors. Contractors involved with hazardous waste management must successfully complete hazardous waste training. Contractor shall provide NAS Corpus Christi Environmental
Hazardous Waste Program Manager with the following documents: (1)
The job title for each position related to hazardous waste management, and the name of the employee filling each job; (2) A written job description for each position listed in (1). This description must include the requisite skill, education, or other qualifications, and duties of employees assigned to each position; (3) A written description of the type and amount of both introductory and continuing training that will be given to each person filling a position listed in (1); (4) Records that document the training or job experience required has been given to, and completed by, personnel. These records will be retained in the
Environmental Department for three years from the date the employee last worked at NASCC.
(d) Emergency contact information contact information (office phone number, cell phone number, and e-mail address).
(2) General site information
16.2. Solid Waste Disposal: All waste must be tracked by NASCC whether directly disposed in a landfill or recycled. Contractor shall recycle waste to the greatest extent feasible.
The solid waste tracking form is included as Attachment B, “SOLID WASTE
SUMMARY SHEET.” The contractor shall turn in this report at the conclusion of the project. Interim reports are required on 30 SEP if the project continues into the next fiscal year.
16.3. Prevention of Spills: Contractor shall ensure that ANY liquid materials on site are off of the ground, covered and away from storm drains. Contractor shall cover and protect storm drains if needed and approved in the stormwater protection plan.
The Contractor shall ensure secondary containment is in place any time liquid materials are stored on-site in containers of 55 gallons or more, and shall provide his or her own spill response supplies and have them readily available at each work site. See
Attachment I for Spill Response Poster.
WHAT TO DO IN CASE OF A SPILL:
STEP 1 - If Material spilled presents a potential for harm to human life, evacuate the area immediately and skip steps 2 & 3.
STEP 2 - Shut off source of spill, if possible (if it can be done safely).
STEP 3 - Contain spill with proper absorbents in assigned spill kits.
STEP 4 - Report other than minor housekeeping spills to 911. Identify your location as NAS Corpus Christi, with specific building number and street address.
STEP 5 – Supervisor initiates spill report, NASCC spill emergency incident response form and gives report to Public Works Environmental Division (Fax:
361-961-3798) and the Government Representative. The form can be accessed at the following website:
http://cnic.navy.mil/regions/cnrse/installations/nas_corpus_christi/om/envi ronmental_support/spcc.html)
Contractor shall reimburse the government for any expenses incurred because of government assistance for cleanup of the spill/release event. At a minimum, train oil-handling personnel in the operation and maintenance of equipment to prevent discharges; discharge procedure protocols; applicable control laws, rules, and regulations; general facility operations.
16.4. Use of Temporary Fuel Tanks: For temporary oil or fuel tank greater than 55 gallons, the contractor shall submit a Spill Prevention Control and Countermeasures (SPCC) plan. The contractor must notify Public Works Environmental Division 48 hours prior to bringing tank on site. Use of tanks must comply with 40 CFR 112, NFPA 30 and 29
CFR 1910.106. Tanks must have all equipment required by regulation properly installed and functional while in use. Tanks must have secondary containment and adequate vehicle protection (i.e. jersey barriers). Identify fuel/oil storage areas on site plans. 40 CFR 112.8 (c) (6) requires periodic Monthly and Annual AST visual inspections to be performed and documented for all in-service stationary above ground tanks on the facility and portable container with 55 gallon capacity or greater. Submit monthly tank and/or container inspections and secondary container drainage log to the
Public Works Environmental Division SPCC Coordinator via the Contracting Officer http://cnic.navy.mil/regions/cnrse/installations/nas_corpus_christi/om/environmental_support/spcc.html http://cnic.navy.mil/regions/cnrse/installations/nas_corpus_christi/om/environmental_support/spcc.html and maintain compliance 40 CFR 112 training requirements. The Contractor shall ensure all containers are kept closed, except when adding or removing fuel/oil, that containers remain in good condition and are properly labeled, and the fill ports are locked when not in use. Spill kits must be on-hand and easily accessible for immediate spill response. During fueling operations, storm drains within 25 feet of fuel tank must be covered with drain blocker to prevent fuel from entering storm drain in the event of a spill. All tanks must be grounded. This includes integral generator base tanks, but does not include oil-filled operational equipment.
16.5. Wastewater Compliance/Sewage Releases and Spills: All discharges to the installation wastewater collection system require prior written authorization to ensure that they do not violate NAS Corpus Christi's TPDES discharge permit. All sanitary sewer overflow events must be reported to the Government Representative immediately upon discovery.
Any waste water from sandblasting/power washing must first be filtered to minimize associated paint flakes, rust, and metal particles, and then routed to the sanitary sewer.
16.6. Environmental Compliance Assessment Tracking and Training System: The
Contractor's on-site project superintendent shall complete ECATTS training prior to starting work. If personnel changes occur, ECATTS training must be completed within
14 days of assignment to the project.
ECATTS is available 24/7 on the Internet. Contractors who perform work on more than one contract for the same installation or within the same state will not have to take the training each time they start a new project. Contractors will carry forward all applicable credits received for taking ECATTS to future contracts. ECATTS is available for use by all contractor and subcontractor personnel associated with this project
ECATTS is available at:https://environmentaltraining.ecatts.com
Registration Password = navfac (case sensitive)
Sample registration instructions that can be provided to users are available from
ECATTS Customer Support.
16.7. Regulated Waste Management: All hazardous wastes generated, as defined in 40 CFR
261, on Naval facilities, whether generated by contractor or federal personnel, remain under the responsibility of NASCC and must comply with the Environmental
Protection Agency, State of Texas, and Navy regulations. NASCC is a large quantity generator of hazardous waste. Regulated waste is defined as (1) hazardous waste as defined in EPA Regulations 40 CFR Part 261, (2) Universal Waste as defined in EPA
Regulations 40 CFR 273, and (3) Class 1 Industrial Waste as defined in Texas
Commission on Environmental Quality (TCEQ) Regulations/30 Texas Administrative
Code Part 335, and asbestos containing material. Contractor shall assign all waste management responsibilities to a designated Environmental representative. Prior to generating regulated waste, the contractor shall be assigned an area for waste management activity, i.e. Satellite Accumulation Area or a <90-day Hazardous Waste
Accumulation Area. The contractor shall be subject to inspection of assigned area.
Where liquid regulated waste is to be stored, the Contractor shall provide appropriate secondary containment and ensure containers are properly bonded and grounded when required. Contractor shall be responsible for maintaining an appropriate spill response kit at all times. All spills are reportable and shall be coordinated with the COR and the
Installation Environmental Program Director.
The contractor is required to use NAVFAC Environmental Services for regulated waste disposal while performing work at NASCC. Environmental Services provides on-site hazardous and industrial waste pickup, identification, storage and disposal service on a cost reimbursable basis. Disposal costs for regulated waste are as follows:
Bulk Container (> 55 gallons) = $1.33/lb.
Non-Bulk Container (<= 55 gallons) = $2.33/lb.
A minimum of 14 calendar days’ lead-time is required for bulk container delivery.
16.8. Stormwater Pollution Prevention: Discharge to the storm water system of hazardous substances or not anything other than storm water or de-chlorinated potable water will
NOT be permitted under any circumstances. Store hazardous materials in a centralized location indoors, undercover, or in lockers that prevent contact with storm water.
Locate storage areas away from drains. Collect and properly dispose non-hazardous construction wastes, trash, and debris throughout the site at least once a day and before storm events.
Disposal of concrete washout to the soil or storm water system is prohibited. Wash out concrete chutes, hoppers, and other containers off Government property or collect concrete washout liquids and solids in pre-fabricated or field erected washout facilities.
Washout facilities must be sited and constructed to resist damage and prevent spills and leaks. Excess concrete shall not be dumped on site.
Contain slurry and sediment from concrete saw cutting or boring operations to the immediate work area. Shovel or vacuum these materials and remove from the site. If residue remains after drying, sweep the area and remove residue to avoid contact with storm water or entering a storm drain.
Prior to soil disturbance and during construction, implement and maintain all erosion and sediment control measures (best management practices) required to retain sediment on-site and to prevent violations of state water quality standards. Best management practices may include temporary seeding, construction of sediment basins, diversion channels, berms, inlet protection, and use of silt fences, and synthetic or straw bales to retard and divert runoff to protected drainage courses. All practices must be in accordance with the guidelines and specifications in the TX DOT Storm Water
Management Guidelines for Construction Activities latest version. If site-specific conditions require additional measures during any phase of construction to prevent erosion or control sediment, implement additional best management practices as necessary.
All areas disturbed by demolition or construction activity shall be graded and stabilized prior to the completion of work. Disturbed areas shall be seeded and mulched or sodded. Reinforcement matting will be used where storm water runoff may cause erosion of stabilized areas. Irrigation shall be provided until a viable root system is established. Dead sod shall be replaced at no cost to the government.
Locate stockpiles of construction materials a minimum of 50 feet from inlets, drainage ditches, or water bodies if feasible. Protect stockpiles with a perimeter sediment barrier to prevent off-site migration of materials. Keep stockpiles organized and surrounding areas clean.
If site-specific conditions require additional measures during any phase of construction to prevent erosion or control sediment, implement additional best management practices as necessary. Submit all BMPs to PWE for review and approval PRIOR to commencement of construction activities.
17. ACCEPTANCE: The work shall be accepted because of a final inspection conducted by a representative of FEAD POC.
18. WARRANTY: All workmanship and materials and/or equipment shall be warranted for a period of not less than one year under normal wear and tear or the normal standard warranty should it extend beyond one year.
** END OF SPECIFICATIONS ***