CITB_0011_26 Everett Park .pdf
PDF 677 KB Posted
- Attached to
- CITB-0011-26, Everett Park Parking Lot Improvement and Installation of a Kayak Launch Dock
- Solicitation number
- PE-66869-NONST-2026-000000028
- Issued by
- Dekalb County, Georgia
About this file
This is a Construction Invitation to Bid (CITB) issued by the City of Stonecrest, Georgia, seeking a qualified contractor to complete a fixed, one-time project to provide recreational access to South River at Everett Park located at 5106 Klondike Road, Stonecrest, Georgia 30038. The scope of work includes construction and installation of a floating kayak launch system, asphalt driveway, permeable interlocking concrete pavement system, drainage improvements, site grading, concrete curb and gutter, landscaping, fencing, erosion control measures, tree protection, ADA-compliant ramp, parking lot construction, and signage installation. The contractor must furnish all labor, materials, equipment, personnel, tools, supervision, and incidentals necessary to complete the project. A mandatory pre-bid meeting and site visit is scheduled for Wednesday, July 8, 2026, at 10:30 a.m. at City Hall, 3120 Stonecrest Boulevard, Suite 190, Stonecrest, Georgia 30038, followed by an on-site visit to Everett Park. Electronic bid responses are due by 3:00 p.m. on Tuesday, August 4, 2026, via the Bidnet platform. The deadline for non-administrative questions is Friday, July 17, 2026, at 5:00 p.m. Bid openings will be conducted electronically via Microsoft Teams and in-person at City Hall on the due date. The contractor must substantially complete the work within 60 calendar days and finally complete it within 180 calendar days from the Notice to Proceed. Work hours are 7:00 a.m. to 7:00 p.m., Monday through Friday, with no work on national or City holidays.
Pricing must be submitted on Attachment B (Bid Cost Proposal Form) and is inclusive of all costs and complete compensation. A bid bond equal to five percent of the total bid amount is required and must be submitted by 12:00 p.m. on Thursday, July 30, 2026. A performance and payment bond equal to 100 percent of the contract value is required within ten business days of the Notice of Intent to Award. Liquidated damages of $250 per calendar day will apply for delays beyond the specified completion date. Payment will be made in two installments: upon completion of 50 percent of the project and upon final completion and City acceptance, with five percent retainage withheld until DBRA compliance is verified. The contract is governed by Georgia Department of Transportation specifications, Georgia Department of Natural Resources standards, U.S. Army Corps of Engineers regulations, Clean Water Act Section 404, Americans with Disabilities Act requirements, OSHA standards, and all applicable City ordinances. No extensions will be granted for typical weather conditions, and the contractor is responsible for all maintenance of traffic, erosion control, utility protection, equipment and materials storage, site security, signage, and final restoration and cleanup. The City reserves the right to reject any or all bids and award based on responsiveness, responsibility, and best value to the City.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION TO BID
(CONSTRUCTION)
(CITB)
CITB-00011-26
EVERETT PARK
PARKING LOT IMPROVEMENT AND INSTALLATION
OF A KAYAK LAUNCH DOCK
SOLICITATION ISSUE DATE: Monday, June 22, 2026
BID’S DUE DATE and OPENING DATE:
Tuesday, August 4, 2026, by 3:00 P.M.
BIDNET WILL NOT ACCEPT LATE SUBMITTALS
“Electronic” Submittals Must be uploaded to “Bidnet” https://Bidnetdirect.com/georgia/cityofstonecrest
(Paper, Faxed, E-mail, Mail Submittals Will Not Be Accepted)
ISSUED BY:
City of Stonecrest
Procurement Division 3120 Stonecrest Boulevard
Stonecrest, Ga. 30038 https://bidnetdirect.com/georgia/cityofstonecrest
CITB-0011-26 CITB-1
Everett Park Parking Lot Improvement and Installation of a Kayak Launch Dock
TABLE OF CONTENT
TITLE PAGE NO.
GENERAL INFORMATION 2
PROCUREMENT SCHEDULED AND EVENTS 4
SCOPE OF WORK 5
GENERAL TERMS AND CONDITIONS 13
SPECIAL TERMS AND CONDITIONS 26
ADDITIONAL ATTACHMENTS AND REQUIRED FORMS:
ATTACHMENT “A” – BIDDER’S REQUIRED FORMS:
1. BID CHECKLIST
2. BIDDER’S CERTIFICATION
3. STATEMENT OF QUALIFICATIONS
4. AUTHORIZED SIGNATORIES
5. PURCHASING POLICY ADDENDUM
6. CONFLICT OF INTEREST DISCLOSURE
7. AFFIDAVIT VERIFICATION STATUS FOR CITY
PUBLIC BENEFIT APPLICATION
8. DRUG-FREE WORKPLACE
9. GEORGIA SECURITY AND IMMIGRATION COMPLIANCE
ACT AFFIDAVIT “E-VERIFY”
10. SUBCONTRACTOR AFFIDAVIT UNDER O.C.G.A. § 13-10-91(B)(3)
11. INDEMNIFICATION CLAUSE
12. NON-COLLUSION STATEMENT
13. VENDOR CERTIFICATION REGARDING SCRUTINIZED
COMPANIES LIST
14. TRENCH SAFETY
15. BID BOND
16. PERFORMANCE AND PAYMENT BOND
17. SCHEDULE I AND SCHEDULE II
18. SUBCONTRACTOR LIST
19. REFERENCES
Attachment B – Bid Cost Proposal Form (Bid Sheet) Attachment C – Everett Park Design Drawings Attachment D – Request for Approved Equal To Attachment E – “Sample” Construction Contract – Fixed Project Attachment F – Purchasing Policy
CITB-0011-26 CITB-2
GENERAL INFORMATION
The following information and instructions are given for the purpose of guiding Bidders in properly preparing their bid responses and are standard for Construction Invitations to Bid (CITB) Solicitations as issued by the City of Stonecrest Procurement Division. These directions and instructions have equal force and weight with the scope of services, specifications and strict compliance which is required with all of these provisions. The City may delete, modify supersede any of these standard instructions for a particular contract to Contractor or in the line item. It is the Bidder’s sole responsibility to become familiar with the scope of services and requirements herein prior to submitting a bid.
For information concerning procedures, clarification, and technical assistance pertaining to this solicitation, contact the Procurement Specialist / Buyer identified in the solicitation.
City of Stonecrest Procurement Division
ATTN: Tanisha Boynton, Procurement Official 3120 Stonecrest Blvd., Suite 190
Stonecrest, Ga. 30038 Phone: (772)-224-0194
Email: Tboynton@stonecresga.gov
All questions and requests for clarification concerning this solicitation and procurement process MUST be submitted in writing via Bidnet under “Message – Opportunity Q&A” at: (https://Bidnetdirect.com/georgia/cityofstonecrest). Please follow the instructions provided on Bidnet. The deadline to submit non-administrative questions is Friday, July 17, 2026 by 5:00 P.M. Answers to questions received will be responded to via an Addendum posted on Bidnet. Questions received after the date referenced above will not be accepted.
• No bid response will be accepted from, nor will any contract be awarded to, any person who is in arrears to the City, upon any debt or contract, or who has defaulted, as surety or otherwise, upon any obligation to the City such as delinquent in payment of property or other taxes with Stonecrest, delinquent in payment of a loan(s) with the City, has had property acquired through foreclosure or a judgment within the past ten (10) years, has outstanding judgements or debts owed to the City, has been convicted of a felony that affects property or neighborhood or neighborhood stability, health, safety or welfare or who is deemed irresponsible or unreliable by the City Council.
• No variation in price or conditions shall be permitted based upon a claim of ignorance. Submission of a bid response will be considered evidence that the Bidder has familiarized themselves with the nature and extent of the work, equipment, materials, and labor required.
• ADDITIONAL TERMS AND CONDITIONS: No additional terms and conditions included by the Bidder with the Bid response shall be evaluated or considered. Any and all such additional terms and conditions shall have no force and effect and are inapplicable to this Bid if submitted either purposely through intent or design, or inadvertently appearing separately in transmittal letters, specifications, literature, price lists or warranties. It is understood and agreed that the general conditions in this Invitation to Bid are the only conditions applicable to this Bid and the Bidder’s authorized signature on Attachment “B” - Bid Cost Proposal Form – Bid Sheet attests to this.
• AUTHORIZED SIGNATORIES: All associated forms must be signed by one duly authorized to do so. The individual submitting shall be authorized to sign (electronically accept) this solicitation response on the behalf of the Contractor as indicated in the Certificate as to Corporate Principal, designation letter by Director/Corporate Officer, or other business authorization to bind on the behalf of the Contractor. No bid response will be accepted, for any reason whatsoever, which is not submitted to the City as stated above, within the specified time.
• BID ACCEPTANCE: Bidder warrants, by virtue of bidding, that their bid and the prices quoted will be firm for acceptance by the City for a period of One Hundred and Twenty (120) days from the date of bid opening unless otherwise stated in the solicitation. The City shall award contract within this time period or shall request to the recommended awarded Contractor an extension to hold pricing, until products/services have been awarded.
CITB-0011-26 CITB-3
• MATERIAL MODIFICATIONS / ALTERATIONS: Material modification and/or alterations to the verbiage or documents herein made by the Bidder is expressly prohibited and is not enforceable. Modifications and/or alterations may render the Bidder’s submission void and bar the Contractor from consideration in connection with this solicitation.
• REQUEST FOR APPROVED EQUALS OR EQUIVALENT: The products specified herein does not necessarily constitute the exhaustive list of products required to complete this project. Therefore, the Contractor is responsible for providing any other parts and materials needed to deliver a complete and fully operational system. All items, functioning capabilities and requirements listed within the scope of work are the MINIMUM REQUIREMENT acceptable to the City.
The Contractor may use Approved Equal or Equivalent equipment and parts as applicable to stay in compliance with current industry standards. The Contractor shall provide the City technical specification, data sheets for any equipment, parts, and accessories that meets or exceeds the minimum requirement listed in herein. Bidders shall complete Attachment “E” - Request for Approved Equal Form and submit request to Tboynton@stonecrestga.gov on or before 5:00PM, Friday, July 10, 2026. Requests received after the date and time specified will not be reviewed or accepted. Approval of such request is at the control and approval of the City.
Remainder of Page Intentionally Left Blank mailto:Tboynton@stonecrestga.gov
CITB-0011-26 CITB-4
PROCUREMENT SCHEDLE AND EVENTS
1. PRE-BID MEETING & SITE VISIT:
There will be a Pre-Bid Meeting on Wednesday, July 8, 2026, at 10:30 am, local time, at City of Stonecrest Annex Conference Room, located at City Hall, 3120 Stonecrest Blvd., Suite 190, Stonecrest, Ga. 30038. The purpose of this pre-bid conference is to explain the method of selection, to provide an overview of the service requirements and view the area in which services will be performed.
Upon completion of the Pre-Bid meeting, staff and vendors will drive to the site. Site Visit Location: Everett Park located at 5106 Klondike Road, Stonecrest, Georgia 30038.
It will be the sole responsibility of the Bidder to become familiar with the scope of work and City requirements prior to submitting a bid. No variation in price or conditions shall be permitted based upon a claim of ignorance. Submission of a bid will be considered evidence that the bidder has familiarized himself with the nature and extent of the work, equipment, materials, and labor required.
2. TRANSACTION FEES:
The City of Stonecrest uses Bidnet (https://Bidnetdirect.com/georgia/cityofstonecrest) to distribute solicitations. There is no charge to Contractors to register and participate in the solicitation process, nor will any fees be charged to the awarded Contractor.
3. ELECTRONIC BID SUBMISSION DEADLINE:
Electronic Bid Responses shall be submitted via Bidnet (https://Bidnetdirect.com/georgia/cityofstonecrest) in response to this solicitation, prior to the designated bids due date and time indicated in the solicitation, Tuesday, August 4, 2026, by 3:00PM. PAPER BID SUBMITTALS WILL NOT BE ACCEPTED.
BID BOND: REQUIRED FOR THIS SOLICITATION
FAILURE TO SUBMIT A BID BOND WILL RESULT IN A NON-RESPONSIVE AND NON-RESPONSIBLE
DETERMINATION. BIDDER’S MUST SUBMIT A COPY OF THE BID BOND WITH BID SUBMITTAL.
BID BOND MUST BE MAILED OR HAND DELIVERED TO: FAILURE TO SUBMIT A BID BOND WILL
PRIOR TO 12:00 PM, THURSDAY, July 30, 2026, WILL RESULT IN A NON-RESPONSIVE AND NON-
RESPONSIBLE DETERMINATION.
City of Stonecrest Procurement Division ATTN: Tanisha Boynton, Procurement Official 3120 Stonecrest Blvd., Suite 190 Stonecrest, Ga. 30038
PERFORMANCE AND PAYMENT BOND: IS REQUIRED FOR THIS SOLICITATION. FAILURE TO
SUBMIT PROOF OF BONDABILITY WILL RESULT IN A NON-RESPONSIBE AND NON-RESPONSIBLE
DETERMINATION.
4. ELECTRONIC BID OPENING:
All Invitations to Bid solicited by the City of Stonecrest will be opened electronically via Bidnet (https://Bidnetdirect.com/georgia/cityofstonecrest) at the date and time indicated in the solicitation. This meeting will be conducted virtually via “Microsoft Teams Meeting” Platform and in-person at City Hall, 3120 Stonecrest Blvd., Suite 190, Stonecrest, Ga. 30038, Lithonia Conference Room. Bidders may attend this meeting in real time on a computer, laptop, cell phone or any other device with Wi-Fi access.
Get the app now and be ready when your first meeting starts https://www.microsoft.com/en-us/microsoft-teams/downloadapp. Information on bid results and solicitations currently out to bid can be obtained on the City website:
https://www.stonecrestga.gov/199/Procurement
Microsoft Teams meeting Join on your computer, mobile app or room device
Meeting ID: 236 995 515 693 028 Passcode: y8Je2MT7 https://bidnetdirect.com/georgia/cityofstonecrest https://bidnetdirect.com/georgia/cityofstonecrest https://bidnetdirect.com/georgia/cityofstonecrest https://www.microsoft.com/en-us/microsoft-teams/downloadapp https://www.microsoft.com/en-us/microsoft-teams/downloadapp https://www.stonecrestga.gov/199/Procurement
CITB-0011-26 CITB-5
SCOPE OF WORK
1. PURPOSE:
The City of Stonecrest (“City”) is seeking qualified and experienced Bidder, herein after referred to as (“Contractor”) to respond to a fixed (one-time) project to provide recreational access to South River located at Everett Park. Work shall be performed in accordance with the terms, conditions, and specifications contained in this Construction Invitation to Bid
(“CITB”).
The Contractor shall furnish all labor, materials, equipment, personnel, tools, supervision, transportation, machinery and other incidentals necessary to perform the work requested herein and typical of these types of projects.
Prices offered on the Attachment “B” - Bid Cost Proposal Form (Bid Sheet) are all inclusive and shall constitute complete compensation. Note: Bid Line Items may not be fully disbursed. Please incorporate the cost within the provided bid line items in Attachment “B”.
2. BACKGROUND:
Stonecrest is a community of approximately 60,000 people that was incorporated in 2017. The City is located along Interstate 20 roughly three miles east of I-285 (“The Perimeter”) and 20 miles east of Downtown Atlanta. Stonecrest is in the southeastern portion of Dekalb County and is bordered by Rockdale County to the east, Henry County to the south, and the City of Lithonia and unincorporated Dekalb County to the north and west. I-20 separates the City into a northern area which includes residential neighborhoods, commercial development along Covington Highway, industrial parks that date to the 1960s and active quarries that predate incorporation by 130 years. South of I-20 features regional retail and lodging, suburban neighborhoods, and substantial outdoor recreation areas.
3. CONTRACT ADMINISTRATOR/DESIGNEE/PROJECT MANAGER:
The designated Contract Administrator for this project is Hari Karikaran, P.E., City Engineer, he can be reached at hkarikaran@stonecrestga.gov or (770) 224-0200. The Contractor will work with the Contract Administrator / Designee to complete this project.
4. GOVERNING REGULATIONS:
The Contractor shall perform services requested herein in accordance with all State, Federal, Local, and City rules, regulations, policies, procedures and requirements herein but not limited to:
1. Georgia Department of Transportation (GDOT) Section 150 - Traffic Control, as amended;
2. Georgia Department of Transportation (GDOT) Section 400 – Hot Mix Asphaltic Concrete Construction, as amended;
3. Georgia Department of Transportation (GDOT) Section 828 – Hot Mix Asphaltic Concrete Mixtures, as amended;
4. Georgia Department of Natural Resources standards, as amended;
5. Provisions of O.C.G.A. § 12-7-6(b)(15), as amended;
6. Pursuant to Ga. Comp. R. and Regs. 391-3-7-.05(2)(a), as amended;
7. US Army Corps of Engineers (Corps) PRDs, Section 10, Rivers and Harbors Act (Navigation) regulations, as amended;
8. Clean Water Act, Section 404, as amended;
9. The Americans with Disabilities Act (ADA), as amended;
10. City of Stonecrest ordinances and regulations;
11. OSHA standards and guidelines; and
12. All other applicable State, Federal, and Local laws, codes, and regulations applicable to perform the work requested herein.
Note: Failure to follow governing regulations may lead to project delays and stoppage of work as deemed necessary by the Contract Administrator / Designee.
mailto:hkarikaran@stonecrestga.gov
CITB-0011-26 CITB-6
5. PROJECT LOCATION AND CONDITION: (See Figure 1):
Everett Park is located along South River at 5106 Klondike Road, Stonecrest, Georgia 30038. Park will be closed during construction.
Link to Google Streetview map of Everett Park: https://maps.app.goo.gl/dvEyq3RbWSMRSC3r6
FIGURE 1 – Parking Lot Entrance
6. WORK TO BE PERFORMED: (See Attachment “C” – Everett Park Design Drawings) The Contractor shall furnish all materials, equipment, tools, and the performance of all necessary labor necessary to complete the scope of work requested herein. Work shall include but is not limited to; construction and installation of a floating kayak launch system, asphalt driveway and permeable interlocking concrete pavement system. Additional scope of work and related requirements can be found in Attachment “C” – Everett Park Design Drawings. This is a turnkey project.
6.1 Measurements:
Prior to ordering materials or commencement of any work, the Contractor shall verify all dimensions and quantities for each location in which work is to be performed. The Contractor shall notify the City of any discrepancies in the measurements provided herein. The Contractor shall provide the adjusted measurements to the Contract Administrator / Designee for review and approval prior to ordering materials and commencement of any work.
6.2 Drainage Improvements:
The Contractor shall perform drainage improvements along Klondike Road, provide necessary landscaping to stabilize the disturbed area(s) and ensure restoration of the natural environment. Work shall be performed in accordance with Attachment “C” – Everett Park Design Drawings.
https://maps.app.goo.gl/dvEyq3RbWSMRSC3r6
CITB-0011-26 CITB-7
6.3 Additional Site Improvements:
The Contractor shall perform additional site improvements consisting of demolition, grading, concrete curb and gutter, landscaping, fencing and erosion control measures. Work shall be performed in accordance with Attachment “C” – Everett Park Design Drawings.
6.4 Erosion Control:
The Contractor shall address erosion control in accordance with Attachment “C” – Everett Park Design Drawings.
6.5 Product Specifications:
The Contactor shall use and provide products in accordance with Attachment “C” – Everett Park Design Drawings or an Approved Equal To where permissible.
6.6 Silt Fence:
The Contractor shall provide silt fencing in accordance with Attachment “C” – Everett Park Design Drawings.
6.7 Tree Protection:
The location in which the work is to be performed is in a heavily wooded area. The Contractor shall take care and necessary precautions by providing protection to surrounding trees in accordance with Attachment “C” – Everett Park Design Drawings.
6.8 Disturbed Area Stabilization:
The location in which the work is to be performed is in a highly vegetive area. The Contractor shall take care and necessary steps to ensure area is stabilized at the completion of this project in accordance with Attachment “C” – Everett Park Design Drawings.
6.9 Outlet Protection:
The Contractor shall preform outlet protection work in accordance with Attachment “C” – Everett Park Design Drawings.
6.10 Concrete and Pavement:
The Contractor shall perform all concrete and pavement work in accordance with Attachment “C” – Everett Park Design Drawings.
6.11 Asphalt Drive:
The Contractor shall construct and install an asphalt drive in accordance with Attachment “C” – Everett Park Design Drawings.
6.12 ADA Ramp and Kayak Launch Dock:
The Contractor shall construct and install a ADA compliant ramp and new kayak launch dock in accordance with Attachment “C” – Everett Park Design Drawings.
6.13 Parking Lot:
The Contractor shall construct a parking lot in accordance with Attachment “C” – Everett Park Design Drawings.
6.13 Signage:
The Contractor shall supply and install signage in accordance with Attachment “C” – Everett Park Design Drawings.
CITB-0011-26 CITB-8
6.14 Trees and Shrubs:
The Contractor shall supply and install trees and shrubs in accordance with Attachment “C” – Everett Park Design Drawings and in accordance with American Nursery standards.
7. MATERIALS AND METHODS:
Materials and methods to complete this project shall be in accordance with GDOT requirements and regulations.
7.1 Materials:
Materials must be certified, were required and come from GDOT approved sources and product list, were required. The Contractor will be required to submit in writing a list of proposed sources of materials. Upon request, the Contractor shall provide certificates from manufacturers for products and materials used to complete this project.
7.2 Testing:
When required, representative samples will be taken for examination and testing prior to approval. The materials used in the work shall meet all quality requirements of the contract. Materials will not be considered as finally accepted until all tests, including any to be taken from the finished work which has been completed and evaluated. All materials will be tested according to the GDOT Sampling, Testing, and Inspection Manual by an approved consultant/lab hired by the City.
8. MAINTENANCE OF TRAFFIC (MOT):
The Contractor shall closely follow the directions provided throughout this document and shall be in conformance with the applicable sections of the GDOT Section 104.05, 107.09 and 150. Temporary speed limit reductions in Work zones must comply with Georgia Law (Code Section 40-6-188).
8.1 The Contractor shall provide a comprehensive MOT Plan to the Contract Administrator / Designee for review and approval.
8.2 The Contractor shall conduct operations that shall not close any thoroughfare, nor interfere in any way with any traffic on roadways without the written consent of the proper authorities within the City.
8.3 The Contractor shall confine operations of all equipment, workers and storage of materials and equipment to areas permitted by law, ordinances, permits or the requirements of the contract and shall not unreasonably encumber the premises with material or equipment.
8.4 NO WORK shall be performed as denoted under herein, without the appropriate and approved maintenance of traffic signs, barricades, flashers and ALL other applicable Maintenance of Traffic (MOT) items being in place per the approved written MOT plan(s).
8.5 In addition to the Maintenance of Traffic (MOT), driveways and entrances must be kept open, with a minimum disturbance to the adjacent property owner(s). However, by agreement with each owner the Contractor may obtain permission to close such accesses for a short period of time. Any such agreement must be obtained in writing from the applicable property owner(s).
8.6 The flow of traffic will be maintained at all times during construction by permitting at least one lane of traffic to move through the construction site. All flagmen, warning signs, barricades and lights necessary to control the traffic and protect the public shall be furnished by the Contractor. All traffic control devices will be in accordance with the GDOT "Manual on Uniform Traffic Control Devices for Streets and Highways 2009 Edition.
8.7 Traffic, whose origin and destination are within the limits of the project shall be provided ingress and egress at all times unless otherwise specified by the City. The ingress and egress include entrances and exits via driveways at various properties, and access to the intersecting roads and streets. The Contractor shall maintain sufficient personnel and equipment (including flaggers and traffic control signage) on the project
CITB-0011-26 CITB-9
sites at all times, particularly during inclement weather, to ensure that the ingress and egress are safely provided when and where needed.
8.8 Two-way traffic shall be maintained at all times, unless otherwise specified or approved by the City. In the event of an emergency, the Contractor shall provide access to emergency vehicles and/or emergency personnel through or around the construction area. Any pavement damaged by such an occurrence will be repaired by the Contractor at no additional cost to the City.
8.9 The Contractor shall furnish, install and maintain all necessary and required barricades, signs and other traffic control devices in accordance with the MUTCD and GDOT specifications, and take all necessary precautions for the protection of the workers and safety of the public.
8.10 All existing signs, markers and other traffic control devices removed or damaged during construction operations will be reinstalled or replaced at the contractor’s expense, except as otherwise called for in the plans. At no time will Contractor remove regulatory signing which may cause a hazard to the public.
8.11 The Contractor shall contact MARTA at least three weeks prior to commencement of any work to coordinate construction and rest of the signs.
8.12 Public Notification: The Contractor shall be responsible for installing signs at the entrance of the location one week prior to commencement of work requiring lane closure. Payment for this will be included in the item for Traffic Control. The contractor shall be responsible for all applicable construction signage per MUTCD guidelines. Payment for this will be included in the item for Traffic Control.
9. WORK SCHEDULE:
Regular work Hours: 7:00 am to 7:00 pm, Monday through Friday. The City will consider extended workdays, workweeks and hours upon written request by the Contractor on a case-by-case basis. No work will be allowed on national holidays and City Holidays (i.e. Memorial Day, July 4th, Labor Day, etc.). Lane closures, if required, are limited to the hours of 9:00 AM to 4:00PM.
10. PROJECT MEETINGS & PROJECT PROGRESS MEETINGS:
After the contract is awarded and prior to commencement of any work, a pre-construction conference will be held between the Contractor, City representative, Utility Providers and others affected by this work. The time and place of the meeting will be arranged by the City Contract Administrator/Project Manager. The project schedule and dates for completion will be established during this meeting.
10.1 At the pre-construction conference, the Contractor shall identify his designated project manager, foreman, site supervisor and any additional personnel representing the Contractor and their respective roles and responsibilities for the work. The designated project manager shall represent the Contractor, and communications given to the project manager shall be as binding as if given to the Contractor. Important communications shall be confirmed in writing. Other communications shall be similarly confirmed in written requests in each case.
10.2 At the pre-construction conference, the Contractor shall furnish in writing to the City’s Contract Administrator the names of person(s) or entities (including those who are to furnish materials or equipment fabricated to a special design) proposed for each principal portion of the work.
10.3 The City will promptly reply to the Contractor in writing stating whether or not, after due investigation, has reasonable objection to any such proposed person or entity.
10.4 The Contractor shall not contract with a proposed person or entity to whom the City has made reasonable and timely objection. The Contractor shall not be required to contract with anyone to whom the Contractor has made reasonable objection.
CITB-0011-26 CITB-10
10.5 The Contractor shall hold bi-weekly progress meetings at the site, including City and subcontractor representatives. The Contractor shall record meeting minutes and distribute them to attendees prior to the next progress meeting.
11. CONTRACTOR RESPONSIBILITIES:
Unless otherwise specified, Contractor will be responsible for the provision and performance of all equipment, materials, work, etc. offered in their response.
11.1 Person of Contact (POC):
The Contractor shall provide contact information for Primary and Secondary staff within the company who will be responsible for providing a response to City request for support work during the term of this agreement. Contact information shall include: Name of Contact(s), E-mail address. Website Information, Phone Number, and Fax Number.
11.2 The Contractor shall conform to all applicable OSHA, NEPA, Americans with Disabilities Act (ADA), State and Federal safety requirements, rules, regulations, policies, and procedures to perform the work requested herein.
11.3 The Contractor shall maintain all certifications, licenses, bonds, and certificate of insurance for the duration of this project until receipt of final acceptance.
11.4 The Contractor shall supervise and oversee all work performed under this contract.
11.5 The Contractor shall provide and maintain a Punch list throughout the entire project.
11.6 The Contractor shall be responsible for initiating, maintaining, and supervising all safety precautions and provide reasonable protection to prevent damage to properties surrounding the work site, injury or loss to employees, materials, and equipment in connection with the performance of the work herein.
11.7 The Contractor shall be responsible for protecting all existing utilities, irrigation, drainage structures, pipes and signs within the limits of this project site shall remain in place and be in working condition during and after the completion of this project.
11.8 The Contractor shall assess the conditions at this site, notify the designated Contract Administrator / Designee in writing of any discrepancies, conflicts, or omissions promptly upon discovery, and make necessary recommendations to resolve identified issues.
11.9 The Contractor shall be responsible for the appearance of all working personnel assigned to the projects (clean and appropriately always dressed), and their compliance with City Policies and Rules prohibiting smoking and consumption of alcohol and illegal drugs while on City projects.
11.10 The Contractor shall enforce strict disciple and good order amongst its employees and other persons carrying out work under this contract.
11.11 The Contractor shall be responsible to the City of acts and omissions of its employees, subcontractors, and other agents performing portions of the work for or on the behalf of the Contractor or any of its subcontractors.
11.12 The Contractor shall have an English-speaking supervisor/representative on the work site at all times, who shall be thoroughly knowledgeable of all plans, specifications, and other contract documents and has the authority to act on the contractor's behalf.
11.13 The Contractor shall be solely responsible for the safety of its employees and subcontractors hired to perform the work requested herein.
CITB-0011-26 CITB-11
11.14 The Contractor shall ensure all employees and subcontractors assigned to perform work under this contract are properly licensed, trained and certified.
11.15 The Contractor shall restore all trees, shrubbery, and sodding if all areas disturbed while performing the work herein (as applicable).
11.16 Reporting Dangerous Conditions / Situations:
The Contractor shall notify the Contract Administrator / Designee of any and all encounters with unsafe and dangerous conditions and/or unusual situations occurring at work sites while working on this project.
12. ISSUANCE OF NOTICE TO PROCEED AND PURCHASE ORDER (PO):
The Contractor shall not commence any work until receipt of a Notice to Proceed (NTP) from the Contract Administrator / Designee and receipt of a Purchase Order (PO). Upon receipt of the NTP and PO, the Contractor shall commence work upon the direction of the Contract Administrator / Designee.
13. PROJECT DURATION:
The Contractor shall complete all services no less than One Hundred and Eighty (180) days from receipt of Purchase Order and Notice to Proceed (NTP).
Time is of the essence for the Contractor’s performance of the work. The Contractor is expected to complete this project as expeditiously as possible. The work to be performed under this contract shall commence upon issuance of a Purchase Order (PO) and in conjunction with a Notice to Proceed (NTP). Contract Time extensions will not be allowed for holidays or vacations. At a minimum, the selected Contractor must adhere to the following schedule as set by the City:
13.1 The Contractor recognizes that TIME IS OF THE ESSENCE. The Work shall commence within 10 calendar days of the date of the Notice to Proceed.
13.2 Preliminary Project Schedule:
Within Ten 10 days after notice of award and as a condition precedent to executing the Contract, prior to commencement of any work, the Contractor shall submit their preliminary project schedule to the City for review and approval. The schedule shall be written in sufficient detail to show the chronical relationship of all major aspects of the project (in the form of tabulation, chart/graphic), procurement of materials, scheduling of equipment, construction, phases of each work site, estimated start and completion dates of the various project activities.
13.3 The Work shall be Substantially Completed within 60 calendar days, after the date when the Contract Time commences to run as provided in the Notice to Proceed.
13.4 The Work shall be finally completed on the Final Completion Date and ready for final payment in accordance with this Agreement within 180 calendar days, after the date when the Contract Time commences to run as provided in the Notice to Proceed.
14. LIQUIDATED DAMAGES:
Upon failure of the Contractor to complete the Work within the time specified for completion, the Contractor shall pay to the City the sum of Two Hundred and Fifty Dollars ($250.00) for each and every calendar day that the completion of the Work is delayed beyond the time specified in this Agreement for completion, as fixed and agreed liquidated damages and not as a penalty, so long as the delay is caused by the Contractor.
15. WEATHER:
The Time of Completion for this project has been calculated assuming that the weather conditions will be average to moderate. If in the opinion of the City’s Contract Administrator / Designee / Project Manager that the weather escalates to a point where the work delays on the project more than the Contractor could have reasonably anticipated or controlled, the Contract Administrator / Designee will make arrangements for extending the time of completion for each individual work order package, once the request has been made for such extensions by the Contractor.
CITB-0011-26 CITB-12
15.1 If adverse weather conditions are the basis of a Claim(s) for additional time, such Claim(s) shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the project scheduled activities.
15.2 The Contractor will be required to promptly notify the City’s Contract Administrator / Designee / Project
Manager in writing of any such delays to the work, explaining its efforts to mitigate the effects of such delays. Any such notification received by the Contract Administrator / Designee / Project Manager, more than five business days after the delay has occurred will not be considered. No extension of time shall be granted for delay(s) resulting from typical weather conditions prevailing in the applicable area(s) as defined by the average of the last ten (10) years of weather data recorded with the City and the applicable jurisdiction(s).
16. DELIVERY, STORAGE, AND HANDLING:
The Contractor shall coordinate delivery and arrange storage of materials (if needed). Storage space may be limited.
Components sensitive to damage in a harsh environment shall be stored off-site and delivered as needed. The Contractor shall provide all necessary protective covering needed to prevent damage to surround work areas. The Contractor shall be responsible for on-site security of tools, equipment and materials. The Contractor shall be responsible for securing all equipment and materials stored during this agreement period.
17. RESPONSE TIME:
The Contractor shall respond to request for services within twenty-four (24) hours of notification by the City.
18. RESTORATION OF PROPERTY:
Property - whether public or private - if damaged during construction or removed for the convenience of the work; ALL such property shall be repaired and/or replaced by the Contractor at his/her own expense in a manner acceptable to the City’s Contract Administrator, prior to final acceptance of the work. Restoration of certain items (such as benches, sod, etc.) shall be performed promptly for reasons of public safety, health, and welfare.
19. DISPOSAL OF EXCESS MATERIAL:
All excavated and excess material(s) which is not required for the work shall be promptly removed from site and safely disposed of by the Contractor; such removal and disposal of the applicable material(s) shall be the sole responsibility of the Contractor and conducted at his/her expense. Disposal of all materials shall be carried out in accordance with State, Local, Federal rules and regulations. No stockpiling of removed materials shall be allowed on site.
20. CONTRACTOR AND SUBCONTRACTOR UNIFORM/BADGING:
The Contractor employees assigned to this contract must wear a professional uniform with the company name permanently affixed to the uniform. Uniforms shall comply with all safety provisions from the Georgia Department of transportation, OSHA, and the City.
21. CONTRACTOR AND SUBCONTRACTOR VEHICLES:
The Contractor’s company vehicles shall be distinctly labeled with the company name; and shall only be parked in designated spaces provided by the City.
22. DAMAGE REIMBURSEMENT:
The Contractor shall be solely responsible for, and shall reimburse the City, any and all costs and/or expense of any kind or nature relating to the correction of any damage to any City property resulting from the installation, maintenance, replacement of mounted equipment and infrastructure.
23. WARRANTY:
The Contractor shall furnish all pertinent warranty information including manufacturers’ warranties, effective dates, as they become available, for all new equipment. All materials, components and labor work performed shall be fully warranted and guaranteed for a minimum of One (1) year from date of completion of services and acceptance by the City and City Engineer. Repair or replacement defects occurring in labor or product(s) within the warranty period shall be performed and provided at no additional cost to the City.
CITB-0011-26 CITB-13
24. CLEAN UP:
All usable materials and debris shall be removed from the premises at the end of each workday and disposed of in an appropriate manner. Upon final completion, the Contractor shall thoroughly clean up all areas where work has been involved as mutually agreed with the associated location Contract Administrator / Designee.
25. WORK ACCEPTANCE:
25.1 Services performed under this agreement will be inspected by an authorized representative of the
Engineering Department. This inspection shall be performed to determine acceptance of work, appropriate invoicing and warranty conditions.
25.2 The City shall provide written notice of acceptance or rejection within five (5) business days of completion of final inspection.
26. FINAL INSPECTION AND WORK ACCEPTANCE:
The Contractor shall perform a joint inspection with the City’s authorized representative for each project upon the completion of all work. The Contractor shall notify the City when the work is complete and ready for the City’s final inspection. After final inspection, the City’s authorized representative for the project will accept the work if the Contractor has satisfactorily:
26.1 Corrected all deficiencies observed during the final inspection and no new deficiencies have been observed;
26.2 Submitted all other required contract deliverables; and
26.3 The Contractor shall correct work rejected by the City or work failing to conform to the requirements of the contract documents, whether or not fabricated, installed or completed. This shall occur within at least five (5) business days of notice to the Contractor, unless otherwise agreed upon with City staff. The Contractor bears the costs of correcting such rejected work, including additional testing, inspections required and compensation for City services and expenses made necessary thereby.
26.4 The Contractor shall provide the following upon completion of the project;
27. REPORTING REQUIREMENTS:
The Contractor shall submit a two (2) week projected schedule each Friday by 3:00pm.
28. INVOICING AND PAYMENT:
The Contractor shall submit a detailed “itemized” invoice list of equipment, labor, parts, and appurtenances used under this agreement. All one-time and reoccurring charges shall be identified on the invoice. Installation services fees shall be submitted and paid as a one-time charge to the City.
Invoices shall be submitted as follows:
1. Initial: Upon Completion of 50% of the project.
2. Final: Upon Completion and City’s Acceptance of Work.
Note: Payment Retainage is applicable to this agreement at a rate of 5% and will be withheld until it has been determined that the Contractor has complied with DBRA requirements.
Remainder of Page Intentionally Left Blank
CITB-0011-26 CITB-14
GENERAL TERMS AND CONDITIONS
The following instructions are given for the purpose of guiding Bidder’s in properly preparing their bids responses. These directions have equal force and weight with the specifications and strict compliance is required with all of these provisions.
1. ADDENDUMS AND INTERPRETATIONS: No interpretation of the meaning of the plans, specifications, scope of work or other contract documents will be made orally to any Bidder. Prospective Bidders must request such interpretation in writing as instructed in the bid package. To be considered, such request must be received by the Questions and Answers deadline as indicated on Page CITB-2 of this solicitation package and on Bidnet (https://Bidnetdirect.com/georgia/cityofstonecrest). Questions received after this time will not be answered.
• Material changes, if any, to the scope of services or bidding procedures will only be transmitted by written addendum on Bidnet (https://Bidnetdirect.com/georgia/cityofstonecrest).
• Failure of any Bidder to receive any such addenda or interpretation shall not relieve any Bidder from any obligation under his bid as submitted. All addenda so issued shall become a part of the contract document.
• Bidder shall verify in Bidnet (https://Bidnetdirect.com/georgia/cityofstonecrest) that their bid response includes “all” addenda(s) before submitting a bid. Receipt of all addenda shall be acknowledged by the Bidder(s) on the Statement of Qualification Certification Form “Addendum Acknowledgement Section” and submitted with bid response.
2. ASSIGNMENT, SUBCONTRACT: Contractor shall not transfer, convey, pledge, subcontract or assign the performance required by this solicitation without the prior written consent of the Procurement Official. Any award issued pursuant to this solicitation and the monies which may become due hereunder are not assignable, transferable, or otherwise disposable except with the prior written consent of the Procurement Official.
3. AWARD: This Bid shall be awarded to the Bidder providing the lowest responsive and responsible bid and meets and/or exceeds the pre-qualification requirements. Award may be in whole, or by line Item, or by group, whichever is determined to be in the best interest of City. Award will be made to the responsive and responsible Bidder, quoting the lowest price, for that product/service that will best serve the needs of the City.
The City also reserves the right to accept or reject any or all bids, part of bids, to waive minor irregularities or variations to specifications contained in bids, minor irregularities in the bidding process, to negotiate terms with the successful Bidder and the right to disregard all non-conforming, non-responsive, unbalanced or conditional Bids. The City also reserves the right to award the contract on a split order basis; lump sum basis; individual item basis; or such combination as shall best serve the interest of the City. Awarded Bidder and all subcontractors/suppliers shall register as a Contractor with the City prior to notice to proceed and maintain active status in the City’s Vendor Registration System.
4. BID BOND: REQUIRED FOR THIS SOLICITATION.
A COPY OF THE BID BOND MUST BE UPLOADED IN BIDNET. FAILURE TO SUBMIT A BID BOND WILL
RESULT IN A NON-RESPONSIVE DETERMINATION.
Each submittal shall be accompanied by a bid guaranty in an amount equal to five (5)% percent of the total bid amount, payable to The City of Stonecrest. A certified check, cashier's check or bank officer's check, for the sum set forth in the advertisement, made payable to the City, or bid bond in such amount, shall accompany each bid response as evidence of the good faith and responsibility of the Bidder. The check or bond shall be retained by the City as liquidated damages should the Bidder refuse to or fail to enter into a contract for the execution of the work embraced in this bid, in the event the bid submittal of the Bidder is accepted. Retention of such amount shall not be construed as a penalty or forfeiture. The above bond or check shall be a guarantee that the Bidder will, if necessary, promptly execute a satisfactory contract and furnish good and sufficient bonds. As soon as a satisfactory contract has been executed and the bonds furnished and accepted, the check or bond accompanying the bid of the successful Bidder will be returned to him. The certified or other checks or bid bonds of the unsuccessful Bidders will be returned to them upon the acceptance of the bid of the successful Bidder. If the successful Bidder shall not enter into, execute, and deliver such a contract and furnish the required bonds within ten (10) days after receiving notice to do so, the certified or other check or bid bond shall immediately become the property of the City as liquidated damages. Retention of such amount shall not be construed as a penalty or forfeiture.
https://bidnetdirect.com/georgia/cityofstonecrest
CITB-0011-26 CITB-15
5. BIDDER’S COSTS: The City shall not be liable for any costs incurred by Bidder’s in responding to this ITB. All expenses involved with the preparation and submission of bid, or any work performed in connection therewith, shall be the sole responsibility (and shall be at the sole cost and expense) of the Bidder, and shall not be reimbursed by the City.
6. BIDDER PERFORMANCE REVIEWS AND RATINGS: The City Contract Administrator may develop a Bidder’s performance evaluation report. This report should be used to periodically review and rate the Bidder’s performance under the contract with performance rating as follows:
• Excellent - Far exceeds requirements.
• Good - Exceeds requirements
• Fair - Just meets requirements.
• Poor - Does not meet all requirements and Proposer is subject to penalty provisions under the contract.
• Non-Compliance - Continued poor performance after notice or a performance level that does not meet a significant portion of the requirements.
This rating makes the Bidder subject to the default or cancellation for cause provisions of the contract. The report shall also list all discrepancies found during the review period. The Bidder shall be provided with a copy of the report and may respond in writing if he takes exception to the report or wishes to comment on the report. Bidders’ performance reviews and subsequent reports will be used in determining the suitability of contract extension.
7. CODE REQUIREMENTS: The Contractor and his or her subcontractors on this project must be familiar with all applicable Federal, State, City, and Local Laws, Regulations or Codes and be governed accordingly as they will apply to this project and the actions or operations of those engaged in the work or concerning materials used. The contractor shall ask for and receive any required inspections.
8. CONDITIONS AND PACKAGING: Unless otherwise stated in the solicitation, or specifically ordered from an accepted price list, deliveries must consist only of new and unused goods and shall be the model of the current standards production available at the time of the solicitation response. The goods must be suitably packaged for shipment by a common carrier.
Each container or multiple units or items otherwise packaged shall bear a label, imprint, stencil or other legible markings stating name of manufacturer or supplier, purchase order number and any other markings required by specifications, or other acceptable means of identifying Contractor and purchase order number.
9. CONE OF SILENCE: In accordance with the State of Georgia Purchasing Act, the City prohibits any communication, except written correspondence, regarding a particular request for proposal, request for qualification, bid, or any other competitive solicitation between any person’s representative seeking award from such competitive solicitation; and any City Council person or legislative staff, or any City employee authorized to act on behalf of the City Council to award a contract under this Bid.
The Cone of Silence shall be in effect as of the date the solicitation has been released and advertised, bids or other response to this competitive solicitation and shall remain in effect and subject to the terms of this section for any person or person’s representative.
The provisions of this division shall not apply to oral communications at any public proceeding, including pre-bid conference, oral presentations before selection committees, and contract negotiations during any public meetings, presentations made to the City Council and protest hearings. Further, the Cone of Silence shall not apply to contract negotiations between any employee and the intended awardees, any dispute resolution process following the filing of a protest between the person filing the protest and any employee, or any written correspondence at any time with any employee, City Council, or selection committee member, unless specifically prohibited by the applicable competitive solicitation process.
The cone of silence shall terminate at the time the City Council, awards or approves a contract, rejects all bids or responses or otherwise take action which ends the solicitation process.
Any Contract entered into in violation of the cone of silence provisions in this section shall render the transaction voidable.
CITB-0011-26 CITB-16
10. CONFLICT OF INTEREST: All Bidders MUST disclose with their Bid the name of any officer, director, agent, or any relative of an officer, director or agent who is also an employee of the City. Further, all Bidders must disclose the name of any employee who owns, directly or indirectly, an interest of five percent (5%) or more in the Bidders firm or any of its subsidiaries.
11. CONFIDENTIAL, PROPRIETARY OR TRADE SECRET: "If a supplier considers any portion of the documents, data, or records submitted in response to this solicitation to be exempt from disclosure under Georgia law, the supplier must clearly redact in a separate redacted copy each such submission or portions of the submission considered to be excluded from disclosure and specify the statutory exemption justifying such exclusion, i.e., code section Official Code of Georgia Annotated (OCGA) § 50-18-72(20)(A) 'Records that reveal ...'
"Wholesale designation of a response or substantial parts of a response as 'confidential' will not be accepted by the City. If only portions of a page are subject to some disclosure, the supplier should not redact the entire page.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .