CDRL - Hydraulic Actuator Test Stand (1).pdf
PDF 575 KB Posted
- Attached to
- Hydraulic Actuator Test Stand Federal contract opportunity
- Solicitation number
- N68520
About this file
This document is a Contract Data Requirements List (CDRL) that specifies data deliverables required for a contract to provide a Hydraulic Actuator Test Stand (HATS). The CDRL lists 13 data items the contractor must provide, including computer software, technical data package, key events schedule, design review information, calibration system description, acceptance test plan, training materials, weight handling procedures, government property inventory, test/inspection reports, maintenance support plan, field service reports, and warranty performance reports. The CDRL provides details on the format, frequency, and distribution of each data item. Related to this CDRL is a federal contract opportunity to procure the HATS, which is a competitive solicitation with a proposal due date of 9 September 2024. The contract is anticipated to be a single award firm-fixed price contract with an initial 12-month period of performance and four option years.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| HATS RFP Amendment 2.pdf | ||
| HATS Price Matrix 22 Aug 2024.xlsx | XLSX spreadsheet | |
| HATS RFP Amendment 1.pdf | ||
| HATS Questions and Answers 22 Aug.xlsx | XLSX spreadsheet | |
| HATS Questions and Answers 9 Aug.xlsx | XLSX spreadsheet | |
| Hydraulic Actuator Test Stand RFP.pdf | ||
| Hydraulic Actuator Test Stand RFP.pdf | ||
| Question Submittal Form.xlsx | XLSX spreadsheet | |
| HATS Price Matrix 7 Aug 2024.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 1 of
CONTRACT DATA REQUIREMENTS LIST (CDRL)
(1 Data Item)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ____ TM _____ OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Hydraulic Actuator Test Stand TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A001 Computer Software Product End Items N/A
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-AVCS-80700A Section 3.2.3, 4.15 FRCSW
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SD D OTIME 5DATC
a. ADDRESSEE
b. COPIES
8. APP CODE
11. AS OF DATE 13. DATE OF SUBSEQUENT SUBM.
Draft
Final A N/A N/A Reg Repro
16. REMARKS FRCSW TPOC 1 0
Block 12: Contractor is required to provide the Government the software end items, including licenses after test completion.
15. TOTAL ▬▬▬▬► 1 0
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
David Colson 3/25/2024 William K. Fields 3/25/2024
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 2 of
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ____ TM _____ OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Hydraulic Actuator Test Stand TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A002 Technical Data Package (TDP) N/A
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-SESS-80776B Section 4.24 FRCSW
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SD D OTIME EOC
a. ADDRESSEE
Final N/A N/A N/A Reg Repro
16. REMARKS FRCSW TPOC 4 0
Block 4: Deliverable shall be in Microsoft Office file format (i.e. 2016 Microsoft Word, Excel, PowerPoint, and Project) and must be completely accessible (including formulas) to the Government.
Forms, letters, and signed documents shall be in fully searchable Portable Document Format (.pdf) file.
Use of other electronic file formats will be rejected. Data deliverables are not proprietary and shall not be marked as proprietary.
The Contractor shall provide three (3) hard copies and one (1) electronic copy to the TPOC.
This deliverable shall include all engineering drawings, operator manuals, diagnostic procedures, preventative maintenance, software manuals.
Block 9: Use Distribution Statement D: Distribution authorized to U.S. Government Agencies and their Contractors administrative or operational use. Other requests shall be referred to Materials Engineering Laboratory, Fleet Readiness Center Southwest (FRCSW), NAS North Island, San Diego, CA.
Block 14: Administrative and Technical Data deliverables shall not be marked proprietary nor be marked with any other non-conforming or unjustified markings. See DFARS 252.227-7013, Right in Technical Data - Noncommercial Items, and DFARS 252.227-7015, Technical Data - Commercial Items.
15. TOTAL ▬▬▬▬► 4 0
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 3 of
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ____ TM _____ OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Hydraulic Actuator & Flow Test Stand TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A003 Key Events Schedule N/A
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-MGMT-81791 Section 4.25 FRCSW
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
DS D OTIME 30DAC
a. ADDRESSEE
Final N/A N/A N/A Reg Repro
16. REMARKS FRCSW TPOC 1 0
Block 4: Deliverable shall be in Microsoft Office file format (i.e. 2016 Microsoft Word, Excel, PowerPoint, and Project) and must be completely accessible (including formulas) to the Government.
Forms, letters, and signed documents shall be in fully searchable Portable Document Format (.pdf) file.
Use of other electronic file formats will be rejected. Data deliverables are not proprietary and shall not be marked as proprietary.
This deliverable shall include a list of all parts that require calibration.
Block 9: Use Distribution Statement D: Distribution authorized to U.S. Government Agencies and their Contractors administrative or operational use. Other requests shall be referred to Materials Engineering Laboratory, Fleet Readiness Center Southwest (FRCSW), NAS North Island, San Diego, CA.
Blocks 10 and 12: Contractor is required to provide the Government the Key Events Schedule or the Plan of Action Milestones (POA&M) one time, thirty (30) days after contract award.
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 4 of
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ____ TM _____ OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Hydraulic Actuator Test Stand TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A004 Design Review Information Package N/A
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-SESS-81757A Sections 3.1.2, 4.26, 4.27 FRCSW
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
DS D OTIME/R 60DAC
a. ADDRESSEE
Final A N/A See Block 16 Reg Repro
16. REMARKS FRCSW TPOC 1 1 0
Block 4: Deliverable shall be in Microsoft Office file format (i.e. 2016 Microsoft Word, Excel, PowerPoint, and Project) and must be completely accessible (including formulas) to the Government.
Forms, letters, and signed documents shall be in fully searchable Portable Document Format (.pdf) file.
Use of other electronic file formats will be rejected. Data deliverables are not proprietary and shall not be marked as proprietary.
Block 9: Use Distribution Statement D: Distribution authorized to U.S. Government Agencies and their Contractors administrative or operational use. Other requests shall be referred to Materials Engineering Laboratory, Fleet Readiness Center Southwest (FRCSW), NAS North Island, San Diego, CA.
Block 12: Contractor is required to provide the Government the Preliminary Design Review sixty (60) days after contract award. An electronic copy shall also be provided in DWG or DXF format and download to SolidWorks (2019) and AutoCAD 2010 version or older. The Government shall notify the Contractor in writing within ten (10) working days of receipt of drawing if they comply with this preliminary design. If revisions are required, the Contractor has ten (10) working days to make revisions and resubmit for a new review. Rejection of drawings does not relieve the Contractor from final delivery date of contract performance period.
Block 13: Contractor has sixty (60) days to provide the final design to the Government. The Government will notify the Contractor in writing within ten (10) working days of receipt of drawing if they comply with the final design. If revisions are required, the Contractor has ten
(10) working days to make revisions and resubmit for a new review. Rejection of drawings does not relive the Contractor from final delivery date of contract performance period.
Block 14: Administrative and Technical Data deliverables shall not be marked proprietary nor be marked with any other non-conforming or unjustified markings. See DFARS 252.227-7013,
15. TOTAL ▬▬▬▬► 1 1 0
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 5 of
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ____ TM _____ OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Hydraulic Actuator Test Stand TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A005 Calibration System Description N/A
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-QCIC-80906 Section 4.28 FRCSW
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SD A OTIME EOC
a. ADDRESSEE
Final N/A N/A N/A Reg Repro
16. REMARKS FRCSW TPOC 1 0
Block 4: Deliverable shall be in Microsoft Office file format (i.e. 2016 Microsoft Word, Excel, PowerPoint, and Project) and must be completely accessible (including formulas) to the Government.
Forms, letters, and signed documents shall be in fully searchable Portable Document Format (.pdf) file.
Use of other electronic file formats will be rejected. Data deliverables are not proprietary and shall not be marked as proprietary.
Block 14: Administrative and Technical Data deliverables shall not be marked proprietary nor be marked with any other non-conforming or unjustified markings. See DFARS 252.227-7013, DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 6 of
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ____ TM _____ OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Hydraulic Actuator Test Stand TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A006 Acceptance Test Plan N/A
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-QCIC-80553A Section 4.29 FRCSW
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SD D OTIME 30DAC
a. ADDRESSEE
Final A N/A N/A Reg Repro
16. REMARKS FRCSW TPOC 1 0
Block 4: Deliverable shall be in Microsoft Office file format (i.e. 2016 Microsoft Word, Excel, PowerPoint, and Project) and must be completely accessible (including formulas) to the Government.
Forms, letters, and signed documents shall be in fully searchable Portable Document Format (.pdf) file.
Use of other electronic file formats will be rejected. Data deliverables are not proprietary and shall not be marked as proprietary.
Block 9: Use Distribution Statement D: Distribution authorized to U.S. Government Agencies and their Contractors administrative or operational use. Other requests shall be referred to Materials Engineering Laboratory, Fleet Readiness Center Southwest (FRCSW), NAS North Island, San Diego, CA.
Block 12: The Contractor shall submit the initial ATP thirty (30) calendar days after contract award for Government review and approval.
Block 14: Administrative and Technical Data deliverables shall not be marked proprietary nor be marked with any other non-conforming or unjustified markings. See DFARS 252.227-7013, DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 7 of
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ____ TM _____ OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Hydraulic Actuator Test Stand TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A007 Training Materials N/A
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-ILSS-80872 Section 4.31 FRCSW
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SD A OTIME ASREQ
a. ADDRESSEE
Final N/A N/A N/A Reg Repro
16. REMARKS FRCSW TPOC 1 0
Block 4: Deliverable shall be in Microsoft Office file format (i.e. 2016 Microsoft Word, Excel, PowerPoint, and Project) and must be completely accessible (including formulas) to the Government.
Forms, letters, and signed documents shall be in fully searchable Portable Document Format (.pdf) file.
Use of other electronic file formats will be rejected. Data deliverables are not proprietary and shall not be marked as proprietary.
Block 14: Distribution shall be via Email. Email notification shall be delivered to the FRCSW. See Contract Clause 5252.247-9505, Technical Data and Information for Distribution Addresses.
Administrative and Technical Data deliverables shall not be marked proprietary nor be marked with any other non-conforming or unjustified markings. See DFARS 252.227-7013, Right in Technical Data - Noncommercial Items, and DFARS 252.227-7015, Technical Data -
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 8 of
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ____ TM _____ OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Hydraulic Actuator & Flow Test Stand TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A008 Weight Handling Procedures N/A
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
OT-24-20069 Section 4.32 FRCSW
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SD A OTIME 5DATC
a. ADDRESSEE
Final N/A N/A N/A Reg Repro
16. REMARKS FRCSW TPOC 1 0
Block 4: Deliverable shall be in Microsoft Office file format (i.e. 2016 Microsoft Word, Excel, PowerPoint, and Project) and must be completely accessible (including formulas) to the Government.
Forms, letters, and signed documents shall be in fully searchable Portable Document Format (.pdf) file.
Use of other electronic file formats will be rejected. Data deliverables are not proprietary and shall not be marked as proprietary.
Block 14: Distribution shall be via Email. Email notification shall be delivered to the FRCSW. See Contract Clause 5252.247-9505, Technical Data and Information for Distribution Addresses.
Requirements:
1. Reference Documents. The applicable issue of the documents cited herein, including their approval dates and dates of any applicable amendments, notices, and revisions, shall be as specified in the contract.
2. Format. Use format as defined below. If the element does not apply to the platform or project, annotate as Not Applicable for that paragraph.
3. Content. The Weight Handling Procedures shall include the following:
3.1. The contract number.
3.2. Date.
3.3. The specific type, class, etc. of weight handling equipment to be used for the delivery and installation of the HATS.
3.4. A Lift Plan and Certification that is in compliance with NAVFAC P-307 (June 2016) with applicable sections 11, 14, and Appendix P.
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 9 of
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ____ TM _____ OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Hydraulic Actuator & Flow Test Stand TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE
A009 Government Property (GP) Inventory Report N/A
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE DI-MGMT-80441D Section 5.5 FRCSW
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SD A OTIME 5DATC
a. ADDRESSEE
Final N/A N/A N/A Reg Repro
16. REMARKS FRCSW TPOC 1 0
Block 4: Deliverable shall be in Microsoft Office file format (i.e. 2016 Microsoft Word, Excel, PowerPoint, and Project) and must be completely accessible (including formulas) to the Government. Forms, letters, and signed documents shall be in fully searchable Portable Document Format (.pdf) file. Use of other electronic file formats will be rejected. Data deliverables are not proprietary and shall not be marked as proprietary.
Block 14: Distribution shall be via Email. Email notification shall be delivered to the FRCSW. See Contract Clause 5252.247-9505, Technical Data and Information for Distribution Addresses.
Requirements:
1. Reference Documents. The applicable issue of the documents cited herein, including their approval dates and dates of any applicable amendments, notices, and revisions, shall be as specified in the contract.
2. Format. Use format as defined below. If the element does not apply to the platform or project, annotate as Not Applicable for that paragraph.
3. Content. The Weight Handling Procedures shall include the following:
3.1. The contract number.
3.2. Date.
3.3. The specific type, class, etc. of weight handling equipment to be used for the delivery and installation of the HATS.
3.4. A Lift Plan and Certification that is in compliance with NAVFAC P-307 (June 2016) with applicable sections 11, 14, and Appendix P.
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 10 of
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ____ TM _____ OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Hydraulic Actuator & Flow Test Stand TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A010 Test/Inspection Report N/A
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-NDTI-80809 Section 5.7.1 FRCSW
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SD A OTIME 5DATC
a. ADDRESSEE
Final N/A N/A N/A Reg Repro
16. REMARKS FRCSW TPOC 1 0
Block 4: Deliverable shall be in Microsoft Office file format (i.e. 2016 Microsoft Word, Excel, PowerPoint, and Project) and must be completely accessible (including formulas) to the Government.
Forms, letters, and signed documents shall be in fully searchable Portable Document Format (.pdf) file.
Use of other electronic file formats will be rejected. Data deliverables are not proprietary and shall not be marked as proprietary.
Block 14: Distribution shall be via Email. Email notification shall be delivered to the FRCSW. See Contract Clause 5252.247-9505, Technical Data and Information for Distribution Addresses.
Administrative and Technical Data deliverables shall not be marked proprietary nor be marked with any other non-conforming or unjustified markings. See DFARS 252.227-7013, Right in
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 11 of
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ____ TM _____ OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Hydraulic Actuator & Flow Test Stand TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A011 Maintenance Support Plan N/A
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-ILSS-81225 Section 7.1 FRCSW
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SD A OTIME See Block 16
a. ADDRESSEE
Final N/A N/A N/A Reg Repro
16. REMARKS FRCSW TPOC 2 0
Block 4: Deliverable shall be in Microsoft Office file format (i.e. 2016 Microsoft Word, Excel, PowerPoint, and Project) and must be completely accessible (including formulas) to the Government.
Forms, letters, and signed documents shall be in fully searchable Portable Document Format (.pdf) file.
Use of other electronic file formats will be rejected. Data deliverables are not proprietary and shall not be marked as proprietary.
Contractor shall submit one (1) hard copy and one (1) electronic copy of the Maintenance Support Plan.
Block 12: Contractor shall submit the Maintenance Support Plan after final acceptance of the
HATS.
Block 14: Distribution shall be via Email. Email notification shall be delivered to the FRCSW. See Contract Clause 5252.247-9505, Technical Data and Information for Distribution Addresses.
Administrative and Technical Data deliverables shall not be marked proprietary nor be marked with any other non-conforming or unjustified markings. See DFARS 252.227-7013, Right in
15. TOTAL ▬▬▬▬► 2 0
David Colson 3/25/2024 William K. Fields 3/25/2024
CONTRACT DATA REQUIREMENTS LIST (CDRL)
(1 Data Item)
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 12 of
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ____ TM _____ OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Hydraulic Actuator & Flow Test Stand TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A012 Field Service Report N/A
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-MGMT-81238 Section 7.2 FRCSW
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SD A OTIME See Block 16
a. ADDRESSEE
Final N/A N/A N/A Reg Repro
16. REMARKS FRCSW TPOC 1 0
Block 4: Deliverable shall be in Microsoft Office file format (i.e. 2016 Microsoft Word, Excel, PowerPoint, and Project) and must be completely accessible (including formulas) to the Government.
Forms, letters, and signed documents shall be in fully searchable Portable Document Format (.pdf) file.
Use of other electronic file formats will be rejected. Data deliverables are not proprietary and shall not be marked as proprietary.
Contractor shall submit one (1) hard copy and one (1) electronic copy of the Warranty.
Block 12: Contractor shall submit the Warranty after final acceptance of the HATS.
Block 14: Distribution shall be via Email. Email notification shall be delivered to the FRCSW. See Contract Clause 5252.247-9505, Technical Data and Information for Distribution Addresses.
Administrative and Technical Data deliverables shall not be marked proprietary nor be marked with any other non-conforming or unjustified markings. See DFARS 252.227-7013, Right in
David Colson 3/25/2024 William K. Fields 3/25/2024
CONTRACT DATA REQUIREMENTS LIST (CDRL)
(1 Data Item)
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 13 of
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP ____ TM _____ OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
Hydraulic Actuator & Flow Test Stand TBD TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A013 Warranty Performance Report N/A
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
DI-SESS-81639B Section 8.0 FRCSW
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION
SD A OTIME See Block 16
a. ADDRESSEE
Final N/A N/A N/A Reg Repro
16. REMARKS FRCSW TPOC 2 0
Block 4: Deliverable shall be in Microsoft Office file format (i.e. 2016 Microsoft Word, Excel, PowerPoint, and Project) and must be completely accessible (including formulas) to the Government.
Forms, letters, and signed documents shall be in fully searchable Portable Document Format (.pdf) file.
Use of other electronic file formats will be rejected. Data deliverables are not proprietary and shall not be marked as proprietary.
Contractor shall submit one (1) hard copy and one (1) electronic copy of the Warranty.
Block 12: Contractor shall submit the Warranty after final acceptance of the HATS.
Block 14: Distribution shall be via Email. Email notification shall be delivered to the FRCSW. See Contract Clause 5252.247-9505, Technical Data and Information for Distribution Addresses.
Administrative and Technical Data deliverables shall not be marked proprietary nor be marked with any other non-conforming or unjustified markings. See DFARS 252.227-7013, Right in
15. TOTAL ▬▬▬▬► 2 0
File details come from the government source that posted it. Updated .