This is a DD Form 1423, Contract Data Requirements List (CDRL), dated February 2024, establishing documentation requirements for a federal contract related to the MPDE (Modular Power Distribution Equipment) system.

The CDRL specifies a single data item requirement (A001) titled "Spare Equipment Harvesting – As-Found Condition Report," classified as OTHER MGMT category under Exhibit A for Contract Line Item 0001. This data item is referenced in Performance Work Statement Paragraph 7.8.1 and is required by the Contracting Officer Representative (COR) at MSC PM8. The report must be submitted as required (AS REQ frequency) with one final copy distributed to the COR. No DD 250 receipt and acceptance documentation is required for this data item. The form carries a distribution statement designation of "C" and an APP code of "A." The document was prepared by Damian Finke and approved by Danielle Bisconti. Contract number and contractor information are marked as TBD (to be determined), indicating this is a template or preliminary planning document.

View the file

Other files

File Type Posted
JA-harvesting_Redacted.pdf PDF
WD Aiken South Carolina.txt TXT text file
Solicitation - N3220526Q7188.pdf PDF
PWS 6.25.2026.docx DOCX document
CDRL B001-2.pdf PDF
WD Beaumont Texas.txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PREVIOUS EDITION MAY BE USED.

DD FORM 1423, FEB 2024 Page 1 of 1

(Updated 20260512)UNCLASSIFIED

UNCLASSIFIED

Show Attachment Bar

Show Hide Instructions

CONTRACT DATA REQUIREMENTS LIST

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

A

C. CATEGORY:

TDP TM OTHER MGMT

D. SYSTEM/ITEM

MPDE

E. CONTRACT/PR NO.

TBD

F. CONTRACTOR

TBD

1. DATA ITEM NO.

A001

2. TITLE OF DATA ITEM

(T-EPF CLASS) SPARE EQUIPMENT HARVESTING

3. SUBTITLE

AS-FOUND CONDITION REPORT

4. AUTHORITY (Data Acquisition Document No.)

N/A

5. CONTRACT REFERENCE

PWS PARA 7.8.1

6. REQUIRING OFFICE

MSC PM8

7. DD 250 REQ

NO

8. APP CODE

A

9. DIST STATEMENT

REQUIRED

C

10. FREQUENCY

AS REQ

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

16. REMARKS

Add Continuation of Remarks Remove Current Page Insert Page

COR 0 1 0

15.TOTAL 0 1 0

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

G. PREPARED BY

Damian Finke

H. SIGNATURE I. APPROVED BY

Danielle Bisconti

J. SIGNATURE Add Page to End

PREVIOUS EDITION MAY BE USED.

DD FORM 1423, FEB 2024

Page of (Updated 20260512) Instructions

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoDM 5010.12 for detailed instructions.)

DD FORM 1423, FEB 2024

Page of (Updated 20260512)

CONTRACT DATA REQUIREMENTS LIST

C. CATEGORY:

14. DISTRIBUTION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES Draft Final Reg Repro

16. REMARKS

14. DISTRIBUTION

15.TOTAL

Image of arrow pointing towards totals

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support (e.g., Mission Design Series (MDS) designator).

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Name of preparer of CDRL.

Item H. Date CDRL was prepared and signature of preparer of CDRL.

Item I. Name of CDRL approval authority.

Item J. Date CDRL was approved and signature of CDRL approval authority.

Item 1. See DFARS Subpart 204.71 for proper numbering. To add or delete additional data items, point and click the plus or minus sign to the right of Block J.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Identify only one Data Acquisition Document No. If a single work task generates more than one deliverable data product, prepare a separate data item for each deliverable data product.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work/Performance Work Statement paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data and computer software, specify the contractor's requirement to mark the appropriate distribution statement on the technical data or computer software (ref. DoDI 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.

Identify for which data item additional remarks are provided. When tailoring the Data Acquisition Document invoked in Item 4, identify which portions of that Document are being tailored.

Identify any referenced attachments to the form. Attachments can be added using the button at the bottom of page 1.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government’s rights to use the data shall be governed by the pertinent provisions of the contract.

9.0.0.2.20120627.2.874785 DD Form 1423, "Contract Data Requirements List"

CurrentPage:
PageCount:
Select Classification from drop-down list.: 1
CUI Indicator Information:
Click on this button to attach a file(s).:
show:
hide:
A. CONTRACT LINE ITEM NUMBER: 0001
exhibit: A
C. CATEGORY: Select for "TDP.": 0
C. CATEGORY: Select for "TM.": 0
C. CATEGORY: Select for "OTHER.": 1
C. CATEGORY: Enter specification for "Other.": MGMT
System: MPDE
ContractNum: TBD
Contractor: TBD
1. DATA ITEM NUMBER: A001
titleDataItem: (T-EPF CLASS) SPARE EQUIPMENT HARVESTING
subtitle: AS-FOUND CONDITION REPORT
4. AUTHORITY (Data Acquisition Document Number): N/A
contractRef: PWS PARA 7.8.1
reqOffice: MSC PM8
7. DD 250 REQUIREMENT: NO
8. APPROVAL CODE : A
9. DISTRIBUTION STATEMENT REQUIRED: C
freq: AS REQ
asOfDate:
dateFirstSub:
dateSubseqSub:
16. REMARKS:
Click to add/remove continuation field for Remarks:
Click to delete CURRENT data items for 1 through 18, unless this is the only data item.:
Click to add a page of data items for 1 through 18 immediately following the current page.:
14. DISTRIBUTION - a. ADDRESSEE, new line: COR
15.TOTAL - Total draft copies is automatically calculated.: 0
15.TOTAL - Total draft copies is automatically calculated.: 0
15.TOTAL - Total final regular copies is automatically calculated.: 1
15.TOTAL - Total final regular copies is automatically calculated.: 1
15.TOTAL - Total final reproducible copies is automatically calculated.: 0
15.TOTAL - Total final reproducible copies is automatically calculated.: 0
priceGrp:
estTotalPrice:
remarks_cont:
preparedBy: Damian Finke
H. SIGNATURE: H. SIGNATURE
H. SIGNATURE:
approvedBy: Danielle Bisconti
J. SIGNATURE: J. SIGNATURE
J. SIGNATURE:
Click to add additional data items 1 through 18 to the end of the form.:

File details come from the government source that posted it. Updated .