The document is a Bid Form for the Town of Monument's 2024 CDBG 3rd Street ADA Accessibility Project (Project #24-05-02), located in Colorado. The project involves various infrastructure improvements including 222 square yards of 4-inch concrete sidewalk, 100 linear feet of concrete curb & gutter (type 1), 160 square yards of ADA concrete curb ramps, 27 tons of asphalt patching, 183 square yards of 8-inch concrete sidewalk/driveway/crossspan, 50 cubic yards of aggregate base course, and related demolition and disposal activities. The bid form requires unit pricing for each component, with all concrete specified as 4,500 psi at 28 days and using a City Mix.
The project is funded through the El Paso County Community Development Block Grant (CDBG) Program, with funding sourced from the U.S. Department of Housing and Urban Development (HUD). The bid form indicates that unit costs are installed, and all demolished material must be hauled off and properly disposed of prior to each pay application. Contractors are required to acknowledge and incorporate any addendums, and the bid form includes spaces for company details, authorized officer information, and signature. The project appears to focus on improving accessibility and infrastructure on 3rd Street, with specific attention to ADA compliance and streetscape improvements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project # 24-05-02
Item Unit Quantity Unit Cost** Total Notes
Concrete Sidewalk (4") yd² 222
Concrete Curb & Gutter (type 1) ft (lineal) 100 ** 8" Curb Head
Concrete Curb & Gutter (type 5) 0 0
ADA Concrete Curb Ramps yd² 160
Asphalt Patching ton 27
Concrete Sidewalk/Driveway/Crosspan (8") installed yd² 183
Aggregate Base Course (6") installed yd³ 50
Embankment yd³ 20
Erosion Control BMP's lump sum 1
Demo & Dispose Asphalt Pavement yd² 150
Demo & Dispose Curb and Gutter (type 1) ft (lineal) 100
Demo & Dispose Curb and Gutter (type 5) ft (lineal) 0
Demo & Dispose Sidewalk (4") yd² 0
Construction Traffic Control lump sum 1
6" Curb Head ft (lineal) 0
Reset Existing Utility Pull Box Cover lump sum 1
Mobilization lump sum 1
Notes:* all concrete to be 4,500 psi at 28 days (City Mix)
Pricing for demo'd material to include haul-off and proper disposal
All demo'd material to be removed from site prior to each pay application
** - Unit Costs are installed
Total Dollars Bid
Total Dollars (printed)
I acknowledge and have incorporated Addendums (initial)
Company Name:
Name and Title of Officer Authorized to Bind Bid:
Signature Date:
Town of Monument CDBG 3rd Street ADA Accessibility Project Bid Form gheinzel Rectangle gheinzel Rectangle gheinzel Typewritten Text
DATE REC'D TIME REC'D
gheinzel Typewritten Text gheinzel Typewritten Text PROJECT: TOWN OF MONUMENT 2024 CDBG ADA 3rd Street Post Office Project
PROJECT NUMBER: 24-05-02
gheinzel Typewritten Text
OFFICE USE ONLY
gheinzel Typewritten Text
CONTRACTOR NAME: ________________________________________________
CONTRACTOR ADDRESS:______________________________________________
CONTACT NAME AND PHONE:_________________________________________
gheinzel Typewritten Text
DELIVER TO GREGG HEINZEL
gheinzel Rectangle gheinzel Line gheinzel Line gheinzel Rectangle gheinzel Line gheinzel Line gheinzel Line gheinzel Typewritten Text x gheinzel Typewritten Text
MONUMENT TOWN HALL (645 BEACON LITE RD)
gheinzel Typewritten Text Deliver envelope here gheinzel Arrow gheinzel Line gheinzel Rectangle gheinzel Typewritten Text
SEALED BID - DO NOT OPEN
File details come from the government source that posted it. Updated .