About this file
This document is a Bid Form for the Town of Monument's 2024 CDBG 3rd Street ADA Accessibility Project (Project #24-05-02), located in Colorado. The project involves infrastructure improvements including 222 square yards of concrete sidewalk, 100 linear feet of concrete curb & gutter (type 1), 160 square yards of ADA concrete curb ramps, 27 tons of asphalt patching, 183 square yards of concrete sidewalk/driveway/crossspan, 50 cubic yards of aggregate base course, 20 cubic yards of embankment, and demolition and disposal of existing asphalt pavement and curb and gutter. The bid form includes provisions for erosion control, construction traffic control, and utility pull box cover reset, with all concrete specified as 4,500 psi at 28 days.
The bid form is part of a Community Development Block Grant (CDBG) project funded by HUD, with specific requirements for labor reporting and contractor compliance. All unit costs are installed, and pricing for demolished materials includes haul-off and proper disposal. Contractors are required to remove all demolished materials from the site prior to each pay application. The project appears to be focused on improving ADA accessibility along 3rd Street in Monument, with specific technical specifications for materials and installation methods. The bid documents indicate that all concrete will use a City Mix and that unit costs include installation of materials.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project # 24-05-02
Item Unit Quantity Unit Cost** Total Notes
Concrete Sidewalk (4") yd² 222
Concrete Curb & Gutter (type 1) ft (lineal) 100 ** 8" Curb Head
Concrete Curb & Gutter (type 5) 0 0
ADA Concrete Curb Ramps yd² 160
Asphalt Patching ton 27
Concrete Sidewalk/Driveway/Crosspan (8") installed yd² 183
Aggregate Base Course (6") installed yd³ 50
Embankment yd³ 20
Erosion Control BMP's lump sum 1
Demo & Dispose Asphalt Pavement yd² 150
Demo & Dispose Curb and Gutter (type 1) ft (lineal) 100
Demo & Dispose Curb and Gutter (type 5) ft (lineal) 0
Demo & Dispose Sidewalk (4") yd² 0
Construction Traffic Control lump sum 1
6" Curb Head ft (lineal) 0
Reset Existing Utility Pull Box Cover lump sum 1
Mobilization lump sum 1
Notes:* all concrete to be 4,500 psi at 28 days (City Mix)
Pricing for demo'd material to include haul-off and proper disposal
All demo'd material to be removed from site prior to each pay application
** - Unit Costs are installed
Total Dollars Bid
Total Dollars (printed)
I acknowledge and have incorporated Addendums (initial)
Company Name:
Name and Title of Officer Authorized to Bind Bid:
Signature Date:
Town of Monument CDBG 3rd Street ADA Accessibility Project Bid Form
Addendum 1 (05/10/2024) 1
Addendum 1
DATE REC'D TIME REC'D
PROJECT: TOWN OF MONUMENT 2024 CDBG ADA 3rd Street Post Office Project
PROJECT NUMBER: 24-05-02
OFFICE USE ONLY
CONTRACTOR NAME: ________________________________________________
CONTRACTOR ADDRESS:______________________________________________
CONTACT NAME AND PHONE:_________________________________________
DELIVER TO GREGG HEINZEL
x
MONUMENT TOWN HALL (645 BEACON LITE RD)
Deliver envelope here
SEALED BID - DO NOT OPEN
This location for early drop-off
If attending the bid opening-bring bid to 259 Beacon Lite Road No Later than 10:00am Mountain Time.
Addendum 1 (05/10/2024) 1