CDBG Bid Form and Envelope Template_add 1.pdf

PDF 120 KB Posted

Attached to
Town of Monument 3rd Street ADA Improvements
Solicitation number
24-05-02
Issued by
El Paso County, Colorado

About this file

This document is a Bid Form for the Town of Monument's 2024 CDBG 3rd Street ADA Accessibility Project (Project #24-05-02), located in Colorado. The project involves infrastructure improvements including 222 square yards of concrete sidewalk, 100 linear feet of concrete curb & gutter (type 1), 160 square yards of ADA concrete curb ramps, 27 tons of asphalt patching, 183 square yards of concrete sidewalk/driveway/crossspan, 50 cubic yards of aggregate base course, 20 cubic yards of embankment, and demolition and disposal of existing asphalt pavement and curb and gutter. The bid form includes provisions for erosion control, construction traffic control, and utility pull box cover reset, with all concrete specified as 4,500 psi at 28 days.

The bid form is part of a Community Development Block Grant (CDBG) project funded by HUD, with specific requirements for labor reporting and contractor compliance. All unit costs are installed, and pricing for demolished materials includes haul-off and proper disposal. Contractors are required to remove all demolished materials from the site prior to each pay application. The project appears to be focused on improving ADA accessibility along 3rd Street in Monument, with specific technical specifications for materials and installation methods. The bid documents indicate that all concrete will use a City Mix and that unit costs include installation of materials.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project # 24-05-02

Item Unit Quantity Unit Cost** Total Notes

Concrete Sidewalk (4") yd² 222

Concrete Curb & Gutter (type 1) ft (lineal) 100 ** 8" Curb Head

Concrete Curb & Gutter (type 5) 0 0

ADA Concrete Curb Ramps yd² 160

Asphalt Patching ton 27

Concrete Sidewalk/Driveway/Crosspan (8") installed yd² 183

Aggregate Base Course (6") installed yd³ 50

Embankment yd³ 20

Erosion Control BMP's lump sum 1

Demo & Dispose Asphalt Pavement yd² 150

Demo & Dispose Curb and Gutter (type 1) ft (lineal) 100

Demo & Dispose Curb and Gutter (type 5) ft (lineal) 0

Demo & Dispose Sidewalk (4") yd² 0

Construction Traffic Control lump sum 1

6" Curb Head ft (lineal) 0

Reset Existing Utility Pull Box Cover lump sum 1

Mobilization lump sum 1

Notes:* all concrete to be 4,500 psi at 28 days (City Mix)

Pricing for demo'd material to include haul-off and proper disposal

All demo'd material to be removed from site prior to each pay application

** - Unit Costs are installed

Total Dollars Bid

Total Dollars (printed)

I acknowledge and have incorporated Addendums (initial)

Company Name:

Name and Title of Officer Authorized to Bind Bid:

Signature Date:

Town of Monument CDBG 3rd Street ADA Accessibility Project Bid Form

Addendum 1 (05/10/2024) 1

Addendum 1

DATE REC'D TIME REC'D

PROJECT: TOWN OF MONUMENT 2024 CDBG ADA 3rd Street Post Office Project

PROJECT NUMBER: 24-05-02

OFFICE USE ONLY

CONTRACTOR NAME: ________________________________________________

CONTRACTOR ADDRESS:______________________________________________

CONTACT NAME AND PHONE:_________________________________________

DELIVER TO GREGG HEINZEL

x

MONUMENT TOWN HALL (645 BEACON LITE RD)

Deliver envelope here

SEALED BID - DO NOT OPEN

This location for early drop-off

If attending the bid opening-bring bid to 259 Beacon Lite Road No Later than 10:00am Mountain Time.

Addendum 1 (05/10/2024) 1