This is an insurance requirements exhibit for Seminole County Board of County Commissioners' Pump Station Renewal & Replacement D25 - Phase I project (CC-6690-25) in Florida. The project involves comprehensive improvements to three lift stations (Wembly Park, Heathrow Woods #2, and Carrington Park) and demolition of the Lake Sylvan Oaks lift station with gravity sewer installation. A State of Florida certified General Contractor, Underground Utility, and Electrical contractor is sought with demonstrated experience in pump station/lift station renewal, replacement, or rehabilitation. The project timeline extends 160 days to Substantial Completion and an additional 20 days to Final Completion, totaling 180 days from Notice to Proceed. A mandatory pre-proposal meeting is scheduled for September 3, 2025, at Sawyer Lake Park, with the bid response deadline set for September 24, 2025, at 2:00 pm. Technical drawings and specifications will be provided to prospective bidders upon RSVP submission via OpenGov. The Engineer's estimated project cost is $3,262,335.00.

Bidders must maintain comprehensive insurance coverage with minimum limits of $1,000,000 per occurrence for most policies, including Workers' Compensation (statutory), Commercial General Liability, Business Automobile Liability, Excess/Umbrella Liability, and Professional Liability, with a General Aggregate of $2,000,000 for applicable policies. Pollution Liability coverage of $1,000,000 per occurrence with a $2,000,000 General Aggregate is also required. The contract applies liquidated damages at $250 per day for project delays and includes 5% retainage on construction progress payments. Minority and Women-owned Business Enterprises (M/WBEs) are encouraged to participate with no specific set-aside provisions detailed. Electronic bid submission is required through the Seminole County website, and prospective bidders are cautioned against contacting any county staff or officials except the designated contact person.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT G

MINIMUM INSURANCE REQUIREMENTS

CC-6690-25 PUMP STATION IMPROVEMENTS PHASE 1

The following insurance requirements and limits of liability are required:

A. Workers’ Compensation & Employers’ Liability Insurance:

Workers’ Compensation: Statutory

Employers’ Liability: $ 1,000,000 Each Accident

$ 1,000,000 Disease Aggregate

$ 1,000,000 Disease Each Employee

B. Commercial General Liability Insurance:

$ 1,000,000 Each Occurrence

$ 2,000,000 General Aggregate

$ 2,000,000 Products and Completed Operations

$ 1,000,000 Personal and Advertising Injury

C. Business Automobile Liability

Insurance: $ 1,000,000 Combined Single Limit

(Any Auto or Owned, Hired, and Non-Owned Autos)

D. Excess/Umbrella Liability: $1,000,000 Each Occurrence

E. Pollution Liability: $ 1,000,000 Each Occurrence

$ 2,000,000 General Aggregate

F. Professional Liability: $ 1,000,000 Per Claim

$ 2,000,000 General Aggregate