This document provides instructions for completing a request for information questionnaire regarding capabilities or transformational technologies that could be integrated into unattended ground sensors for U.S. Customs and Border Protection. Respondents are asked to provide details about proposed capabilities or technologies in areas such as technical feasibility, manufacturability, interoperability, product support, and affordability over the next five to ten years. The questionnaire will be considered in support of the pre-solicitation notice for the CBP Unattended Ground Sensors and Enabling Technology opportunity issued by the Department of Homeland Security's Customs and Border Protection agency. Respondents are to enter applicable data for each proposed capability or technology in columns corresponding to characteristics like technology and manufacturing readiness levels, common standards, price targets, and more, to facilitate evaluation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

Instructions for Completing Request for Information Quetionnaire
1For each capability or transformation technology <Go To Capabilities and Technologies spreadsheet in this Workbook> and enter appropriate data for consideration.
2<Select in Column A which capability or transformational technology> your organization wants to submit an initiative for consideration. Enter your organizations data in the appropriate Row. If your organization has more than one initiative to be considered <ADD A ROW>
3In Column B enter a short description of the capability or transformational technology your organization would benefit UGS
4In Column C enter a hyperlink to data that can talk to the capabilities to be provided. If possible hyperlink should be to a specification, Interface Control Document, or verification data. If hyperlink is not available provide softcopy supporting document(s) to validate assertion. If the capability or technology being proposed is still in development provide a product development schedule that identifies when the capability or technology would be available for integration
5In Columns D through F place an "X" in the cell that specifies if the capability or technology would be applicable to I-UGS, U-UGS, A-UGS, B-UGS. If this applies to multiple types of UGS then please place in "X" in multiple cells.
Technical Feasibility and Maturity (Columns H through M)
Technical Feasibility and Maturity is measured as Technology Readiness Level (TRL), whereas:
In Column H: Specify if the capability or technology will be technically feasible for integration into UGS in FY 2024. ENTER (Y/N)
In Column H: Specify TRL in FY 2024. ENTER 1 through 9.
In Column I: Specify if the capability or technology will be produced and available for integration into UGS in FY 2024 + 5 years. ENTER (Y/N)
In Column J: Specify TRL anticipated in FY 2024 + 5 years. ENTER 1 through 9.
In Column K: Specify if the capability or technology will be produced and available for integration into UGS in FY 2024 + 10 years. ENTER (Y/N)
In Column L: Specify TRL anticipated in FY 2024 + 10 years. ENTER 1 through 9.
Manufacturing/Producibility (Columns N through S).
Manufacturing Readiness is measured as Manufacturing Readiness Level (MRL), whereas:
In Column N: Specify if the capability or technology will be produced and available for integration into UGS in FY 2024. ENTER (Y/N)
In Column O: Specify MRL in FY 2024. ENTER 1 through 9.
In Column P: Specify if the capability or technology will be produced and available for integration into UGS in FY 2024 + 5 years. ENTER (Y/N)
In Column Q: Specify MRL anticipated in FY 2024+ 5 years. ENTER 1 through 9.
In Column R: Specify if the capability or technology will be produced and available for integration into UGS in FY 2024 + 10 years. ENTER (Y/N)
In Column S: Specify MRL anticipated in FY 2024+ 10 years. ENTER 1 through 9.
Interoperability/Interdependency (Columns T through W)
In Column T: Specify if capability or technology being proposed incorporates Common Information Technology, Communications, and Data Standards. ENTER (Y/N)
In Column U: Specify if capability or technology being proposed applies Cursor-on-Target (CoT) Standard for Machine-to-Machine Communications. ENTER (Y/N)
In Column V: Specify if capability or technology being proposed applies Hardware or Software Interfaces for Modularity and Reusability. ENTER (Y/N)
In Column W: Specify if capability or technology being proposed applies Open Architecture Standards for Artificial Intelligence and Machine Learning Algorithms. ENTER (Y/N)
Product Support (Columns X through AA)
In Column X: Specify if Design for Supportability Considered (Y/N). ENTER (Y/N)
In Column Y: Specify Materiel Availability (%). ENTER %
In Column Z: Specify Materiel Reliability (Hrs). ENTER Hours
In Column AA: Specify Mean Time Between Maintenance (Hrs). ENTER Hours
Affordability (Columns AB through AD)
In Column AB: Specify the Current or Forcast Unit Price ($K)
In Column AC: Specify the forecast Unit Price to Procure 10-100 ($K)
In Column AD: Specify the forecast Unit Price to Procure>100 ($K)

Capabilities and Technologies

Technical Feasibility and MaturityManufacturabilty/ProducibilityInteroperability/InterdependencyProduct SupportAffordability
Capability/Trasformative TechnologyDescription of Capability or Transformational Technology that Could be IntegratedINSERT <Hyperlink to Product Specification, ICD, or Verification Data if exists or schedule for product development and testing>Applies to I-UGS (Y/N)Applies to U-UGS (Y/N)Applies to A-UGS (Y/N)Applies to B-UGS (Y/N)Available FY 2024 (Y/N)TRL1 (1-9)Available FY 2024 + 5 Years (Y/N)TRL1 (1-9)Available FY 2024 + 10 Years (Y/N)TRL1 (1-9)Available FY 2024 (Y/N)MRL2
(1-9)Available FY 2024 + 5 Years (Y/N)MRL2
(1-9)Available FY 2024 + 10 Years (Y/N)MRL2
(1-9)Applies Common Information Technology, Communications, and Data Standards (Y/N)Applies Cursor-on-Target (CoT) Standard for Machine-to-Machine Communications (Y/N)Include Hardware or Software Interfaces for Modularity and Reusability (Y/N)Applies Open Architecture Standards for Artificial Intelligence and Machine Learning Algorithms (Y/N)Design for Supportability Considered (Y/N)Materiel Availability (%)Materiel Reliability (Hrs)Mean Time Between Maintenance (Hrs)Current or Forcast Unit Price ($K)Price to Procure 10-100 ($K)Price to Procure>100 ($K)
High Performance Computing
Cloud/Hybrid Cloud
Edge Computing
Network Architecture and Deployment
Data Transfer
Big Data Analytics
Computer Vision
Pattern Recognition
Standardization and Interoperability
Supply Chain
Power
Manpower/Training/Skills
Platform Resilience
Digital Engineering and Modeling
TRL1=Technology Readiness Level
MRL2=Manufacturing Readiness Level