This is an Excel spreadsheet documenting equipment currently in place at the facilities subject to the renovation projects.
The file serves as an inventory attachment for the Building 206 Lab Upgrade and Building 233 Breakroom Renovation solicitation. It functions as a reference document for offerors to understand existing equipment and infrastructure at Naval Undersea Warfare Center (NUWC) Keyport facilities in Keyport, Washington. The spreadsheet provides detailed information about equipment locations, specifications, and current conditions that contractors should account for during project planning and execution. This inventory is essential for offerors to accurately scope work, identify potential conflicts with existing installations, plan around operational equipment, and develop comprehensive pricing for the renovation and upgrade work. The equipment listing helps ensure that quotations address site-specific conditions and that contractors understand the existing infrastructure they will be working within or around during the construction and renovation activities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C7_PPI_Answers_Amendment0001.docx | DOCX document | |
| C7_Att12_206_233_SOW_Rev1.pdf | ||
| N0025326Q0011_Amendment0001.pdf | ||
| C7_PPI_Answers_Amendment0001.docx | DOCX document | |
| C7_Att02_Wage_Determination.pdf | ||
| Solicitation - N0025326Q0011.pdf | ||
| C7_Att05_OPSEC_Guide.pdf | ||
| C7_Att10_Safety_Data_Sheet.docx | DOCX document | |
| C7_Att03_Safety_Requirements_for_Contractors.pdf | ||
| C7_Att04_Contractors_Guide_to_Env_Compliance.pdf | ||
| C7_Att06_Schedule_of_Values.xlsx | XLSX spreadsheet | |
| C7_Att12_Bldg206_and_Bldg233_SOW.pdf | ||
| C7_Att11_OSHA_Calculating_Injury_and_Illness_Incident_Rate.pdf | ||
| C7_Att07_Past_Performance_References.docx | DOCX document | |
| C7_Att09_PPI_Form.docx | DOCX document | |
| C7_Att08_Bid_Form.xlsx | XLSX spreadsheet |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Installed Equipment
| Contract No: | N0025326Q0011 (Solicitation Number) | ||||||||||||||
| Project Title: | Bldg. 206 Lab Upgrade and 233 Restroom Renovation | ||||||||||||||
| Asset Number | Description | Long Description | Building No. | Room No. | Asset Qty | UOM | Replacement Cost | Supplier/Vendor | Manufacture | Model No. | Serial No. | Manufacture Warranty Expiration Date | Installation Date | Equipment Removed | |
| New Asset Number | |||||||||||||||
| (Note 4) | Description of Equipment or materials Installed | ||||||||||||||
| (Note 3) | Additional Relevant Information (e.g. size, capacity, limits, etc…) | Building # | Room Number of installed equipment | Quantity | |||||||||||
| (Note 1) | Standard Unit of Measure for asset installed | Cost (material and labor to remove (if applicable) and install asset | |||||||||||||
| (Note 2) | Name/Address/Email/ | ||||||||||||||
| Phone Number | Manufacturer | Model number of installed equipment | Serial number of installed equipment | MM/DD/YYYY | |||||||||||
| (Where no Manufacture Warranty use Contract Warranty Date) | MM/DD/YYYY | ||||||||||||||
| Asset Number of removed asset |
(if no label present on asset this column is Not Applicable) (Note 3)
| Notes: |
| 1. When installing assets with a unit of issue of "EACH", there must be a separate line item for each asset. |
| 2. Costing data is to include the cost (labor and material) of removing the old asset and installing the new asset. |
| 3. Enter equipment installed in column B and equipment removed in column O. |
| 4. This column is not necessary for the final submittal from the contrator. FMS will create asset number when they receive the spreadsheet from the government. |
Example
| Contract No: | NXXXXX-21-C-XXXX | ||||||||||||||
| Project Title: | Bldg. 206 Lab Upgrade | ||||||||||||||
| Asset Number | Description | Long Description | Building No. | Room No. | Asset Qty | UOM | Replacement Cost | Supplier/Vendor | Manufacture | Model No. | Serial No. | Manufacture Warranty Expiration Date | Installation Date | Equipment Removed | |
| New Asset Number | |||||||||||||||
| (Note 4) | Description of Equipment or materials Installed | ||||||||||||||
| (Note 3) | Additional Relevant Information (e.g. size, capacity, limits, etc…) | Building # | Room Number of installed equipment | Quantity | |||||||||||
| (Note 1) | Standard Unit of Measure for asset installed | Cost (material and labor to remove (if applicable) and install asset | |||||||||||||
| (Note 2) | Name/Address/Email/ | ||||||||||||||
| Phone Number | Manufacturer | Model number of installed equipment | Serial number of installed equipment | MM/DD/YYYY | |||||||||||
| (Where no Manufacture Warranty use Contract Warranty Date) | MM/DD/YYYY | ||||||||||||||
| Asset Number of removed asset |
(if no label present on asset this column is Not Applicable) (Note 3)
| Breathing Air Filter | located behind cabinet next to AHU-1 op switch | 5094 | 101 | 1 | EA | $2,400.00 | Atlas - 1234 Street Way, America WA 98383 atlas@msn.com/ | ||
| 360-123-4567 | Atlas Copco | FTX345BU | STB0004356 | 3/12/21 | 3/12/17 | 5094-0-101-154A-40-1H | |||
| Breathing Air Filter | located behind cabinet next to AHU-1 op switch | 5094 | 101 | 1 | EA | $2,400.00 | Atlas - 1234 Street Way, America WA 98383 atlas@msn.com/ | ||
| 360-123-4567 | Atlas Copco | FTX345BU | STB0004357 | 3/12/21 | 3/12/17 | 5094-0-101-154A-40-1J | |||
| CARPET | 5094 | 116, 117, 118 | 300 | SQFT | $4,200.00 | Carpets - 156 Lumber Way, |
Bert WA 98317 carpets@msn.com
| 360-266-0154 | Mohawk | MOHAWH - STRBU | N/A | 3/21/19 | 3/12/17 | N/A |
| Notes: | ||||||
| 1. When installing assets with a unit of issue of "EACH", there must be a separate line item for each asset. | ||||||
| 2. Costing data is to include the cost (labor and material) of removing the old asset and installing the new asset. | ||||||
| 3. Enter equipment installed in column B and equipment removed in column O. | ||||||
| 4. This column is not necessary for the final submittal from the contrator. FMS will create asset number when they receive the spreadsheet from the government. |
File details come from the government source that posted it. Updated .