This is a specifications document for a roof replacement project at the Nebraska National Forests & Grasslands, Chadron Work Center Shop, located 3 miles south of Chadron, Nebraska in Dawes County. The project has a 30-day completion schedule and includes removal, disposal, and replacement of existing roofing systems on government facilities.
The base bid items require removal of existing asphalt shingle roofing to deck on the West Shop (approximately 3,914 square feet), installation of new asphalt shingle roofing system with high-grade synthetic underlayment, ice dam material, vent jacks, gutter apron, and drip edge, plus disposal of all construction waste at a sanitary landfill. Optional bid items include the same scope of work for the East Shop (approximately 2,250 square feet) and an as-quantity item for removal and replacement of rotten deck material measured per 32-square-foot sheet. The specifications require Owens Corning TruDefinition Duration STORM Impact Resistant or Malarkey Class 4 shingles (color to be determined by the Contracting Officer), ASTM D8257 synthetic underlayment, ASTM D1970 ice and water shield, and galvanized roofing nails. The contractor must submit product data for approval minimum 10 days prior to work start, provide a comprehensive written Safety Plan in compliance with OSHA standards, maintain daily site cleanliness with magnetic sweeping for remaining nails upon completion, salvage and reinstall existing gutters and downspouts, and inspect all deck and flashing materials with direction from the Contracting Officer for replacement of damaged areas. Contractor compensation includes all materials, labor, equipment, and mobilization costs, with payment made upon completion of each item in full accordance with specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A0001_Chadron WC Shop Roof Replacement Project.pdf | ||
| C05_Attach 3-Drawings Chadron.pdf | ||
| C05_Attach 5- WD_NE20260079_05.18.26.pdf | ||
| 1240LT26Q0149-Chadron.pdf | ||
| C05_Attach 1-SOI.xlsx | XLSX spreadsheet | |
| C05_Attach 2- SOW.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NEBRASKA NATIONAL FORESTS & GRASSLANDS
PINE RIDGE RANGER DISTRICT
DAWES COUNTY, NE
SPECIFICATIONS
for
CHADRON WORK CENTER SHOP
ROOF REPLACEMENT PROJECT
5/2026
SCHEDULE OF ITEMS
NEBRASKA NATIONAL FORESTS & GRASSLANDS
PINE RIDGE RANGER DISTRICT
CHADRON WORK CENTER SHOP ROOF REPLACEMENT
Item Number Description Type
Msrmt Unit Quantity Unit Price Total
Chadron Work Center West Shop Roof Replacement See drawings for approximate roof measurements
THE FOLLOWING ARE BASE BID ITEMS:
001 Remove existing asphalt shingle roofing system to deck LS LS 1 $ $
002 Provide and install new asphalt shingle roofing system LS LS 1 $ $
003 Disposal LS LS 1 $ $
Total Base Amount $
THE FOLLOWING IS AN OPTION BID ITEM:
Remove rotten deck material, provide and install new deck material
AQ
Sheet of decking/32sq ft
1 $ $
Item Number Description Type
Msrmt Unit Quantity Unit Price Total
Chadron Work Center East Shop Roof Replacement See drawings for approximate roof measurements
THE FOLLOWING ARE OPTION BID ITEMS:
005 Remove existing asphalt shingle roofing system to deck LS LS 1 $ $
006 Provide and install new asphalt shingle roofing system LS LS 1 $ $
007 Disposal LS LS 1 $ $
Total Options Amount
TOTAL of BASE and OPTIONS = $
INDEX
DIVISION 1 - GENERAL REQUIREMENTS
SECTION 01010 - SUMMARY OF THE WORK
SECTION 01170 – ACCIDENT PREVENTION
SECTION 01350 - DEMOLITION AND REMOVAL
SECTION 01530 – BARRIERS
SECTION 01600 - USE OF GOVERNMENT FACILITIES, UTILITIES, ETC.
SECTION 01900 - MEASUREMENT AND PAYMENT
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
SECTION 07311 - ASPHALT SHINGLES
SECTION 07620 - METAL FLASHING AND EDGES
01010-2
DIVISION 1 - GENERAL REQUIREMENTS
SECTION 01010 - SUMMARY OF THE WORK
GENERAL
1.01 Scope: The intent of this section is to outline in a general sense the work required under this Project. It is not intended to provide detailed specifications for materials, labor, and workmanship. These are covered in other sections of these specifications.
1.02 Location of the Work: The work for this project is at the Nebraska National Forests &
Grasslands, Chadron Work Center (WC) Shop located at the 16524 Highway 385 approximately 3 miles south of Chadron, Nebraska.
1.03 Description of the Work: The work to be performed includes removal, disposal, and replacement of existing roofing system and the reuse of the existing downspouts and gutters:
BASE ITEM:
A. Remove existing Chadron WC West Shop Roof system to deck: Approximately 3,914 sqaure feet;
1. Remove and dispose of existing asphalt shingle roofing system to deck. Inspect deck and flashing and replace/repair rotted or damaged materials as directed by the Contracting Officer (CO) prior to installing new roofing system.
B. Provide and install new asphalt shingle roofing system including: high grade synthetic underlayment; ice dam material on eves and ridges; vent jacks; gutter apron; drip edge;
and other appurtenances as identified by the specifications and the materials manufacturers.
C. Disposal: Remove all construction waste/debris from site and dispose at appropriate sanitary landfill.
OPTION ITEM:
A. Remove existing Chadron WC East Shop Roof system to deck: Approximately 2,250 sqaure feet;
1. Remove and dispose of existing asphalt shingle roofing system to deck. Inspect deck and flashing and replace/repair rotted or damaged materials as directed by the Contracting Officer (CO) prior to installing new roofing system.
01010-3
B. Provide and install new asphalt shingle roofing system including: high grade synthetic underlayment; ice dam material on eves and ridges; vent jacks; gutter apron; drip edge;
and architcutral shingles.
C. Disposal: Remove all construction waste/debris from site and dispose at sanitary landfill.
The Contractor will provide all materials and labor necessary to perform the work required on this project. Quantities provided are only an approximation of actual and do not include wastage. The Contractor shall be responsible for field verifying all dimensions and quatities of materials required before bidding on this project.
1.04 Disposal Site: The Contractor shall dispose of all waste at a sanitary landfill. All permits and related costs associated with disposal of waste shall be the responsibility of the Contractor.
1.05 Storage: The Contractor shall be responsible for protecting all equipment and supplies intended for use in this project. Government will designate storage area.
1.06 Clean-up: The Contractor shall maintain a clean work site daily. All debris and waste materials shall be removed and discarded daily. The Contractor shall be diligent to make every effort not to allow debris to be blown or scattered around on site.
A. On completion of the work on the project and after removal of all debris, the Contractor shall sweep the entire work site with a magnet to pick up all remaining nails.
B. On completion of the work on the project, the work site shall be left in clean condition satisfactory to the Contracting Officer.
1.07 Construction Schedule: The Contractor shall have 30 days to perform all work required on this contract.
A. The Contractor shall, at the pre-work conference, submit a construction schedule showing the proposed scheduling of all work items to be completed.
1.08 Construction Safety: ALL construction activities shall be performed in accordance to all applicable OSHA standards or regulations. Some of the safety hazards that may be encountered while working on this site will be use of ladders, lifts, hoists, various hand tools, working on a sloped surfaces, use of fall protection equipment and use of applicable PPE. See SECTION 01170 - ACCIDENT PREVENTION.
A. The Contractor shall, prior to beginning work on this project, submit a written Safety
Plan specific to the work to be performed and possible hazards associated with this project. See SECTION 01170 - ACCIDENT PREVENTION.
01010-3
1.09 The Contractor shall submit product data for all materials to be used in the performance of work under this contract to the CO for approval prior to purchasing materials. All submittals shall be delivered to the CO at minimum 10 days prior to starting work to allow time for approval.
1.10 Drawings: Construction drawings accompanying these specifications form a part of this contract and are as follows:
1 – Title Page;
2 – Roof Elevations
END OF SECTION 01010
01170-4
SECTION 01170
ACCIDENT PREVENTION
PART 1 - GENERAL
1.01 DESCRIPTION
A. The work of this Section consists of establishing an effective Accident Prevention
Program and providing a safe environment for all personnel and visitors.
B. Safety Requirements: All work conducted under this contract shall be in accordance with the Occupational Safety and Health Administration (OSHA) regulations for construction safety (29 CFR part 1926 and 29 CFR part 1910), as stated in Section I (Contract Clauses), FAR 52.236-13.
1.02 SUBMITTALS
A. Accident Prevention Program: The Contractor shall submit for approval at least 10 days prior to beginning on-site work a written Safety Plan. The Contracting Officer (CO) will review the proposed Safety Plan for compliance with OSHA and project requirements. If the Safety Plan requires any revisions or corrections, the Contractor shall resubmit the Safety Plan within 10 days of notification by the CO. No progress payments will be processed until the Safety Plan has been received and approved.
1. The Safety Plan shall include:
a. Name of responsible supervisor to carry out the program.
b. Documentation or schedule of weekly and monthly safety meetings.
c. Training, both initial and continuing.
d. First aid procedures.
e. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, government personnel, and the Contractor's employees. Identify the work included under each phase by reference to SPECIFICATION SECTION.
Emergency Response: Planning for possible emergency situations, such as accidents, floods, fires, cave-ins, slides, explosions, power outages, and storms.
Such planning shall take into consideration the nature of construction, site conditions, degree of exposure of persons and property, and evacuation
01170-5 procedures, and shall include emergency contact name(s) and phone numbers and route(s) to the nearest emergency response facility.
f. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.
g. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.
B. Upon request by the CO, the Contractor shall submit a brief report of safety meetings, of safety inspections, and/or proof of employees' qualifications to perform assigned duties in a safe manner.
1.03 QUALITY ASSURANCE
A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the
General Provisions:
1. In case of conflicts between Federal, State, and local safety and health requirements, the most stringent shall apply.
2. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites.
3. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees:
1. The Contractor shall ensure that employees are physically qualified to perform their assigned duties in a safe manner.
2. The Contractor shall not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
a. At the discretion of the CO, employees whose ability or alertness appears to be impaired because of drugs, fatigue, illness, intoxication, or other conditions may be asked to remove himself/herself from the site.
b. The presence of an employee whose ability or alertness appears to be impaired because of drugs, fatigue, illness, intoxication, or other conditions may result in a suspension of work.
01170-6
3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment.
a. The Contractor shall provide operating instructions for all equipment.
b. The Contractor shall require newly hired operators be tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
1.04 ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires.
1. In the case that a reportable accident occurs, the Contractor shall notify the CO immediately or as soon as practically possible.
2. Within 7 days of a reportable accident, the Contractor shall fill out and forward to the CO a DI-134 form.
a. DI-134 forms may be obtained from CO.
B. All Other Accidents: The Contractor shall report all other accidents to the CO as soon as possible.
1. The Contractor shall assist the CO and other officials as required in the investigation of the accident.
PART 2 – PRODUCTS
2.01 FIRST AID FACILITIES: Provide adequate facilities for the number of employees and the type of construction at the site.
2.02 PERSONNEL PROTECTIVE EQUIPMENT (PPE): PPE shall meet the requirements of
NIOSH and MSHA, where applicable, as well as ANSI.
2.03 BARRIERS: See SECTION 01530 BARRIERS.
PART 3 – EXECUTION
3.01 EMERGENCY INSTRUCTIONS: The Contractor shall post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
01170-7
3.02 ESCAPE ROUTES: The Contractor shall provide and maintain adequate escape routes at all times in accordance with the Life Safety Code (NFPA 101-91).
3.03 PROTECTIVE EQUIPMENT: The Contractor shall inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
A. The Contractor shall inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
3.04 SAFETY MEETINGS
A. Pre-Work Safety Meeting: Prior to beginning work, the Contractor shall conduct a Pre- Work Safety Meeting to discuss planned operations, types of equipment to be used, and any task or site specific safety hazards associated with the work to be conducted under this contract.
1. ALL personnel, including supervisors, workers, and subcontractors who will be performing work under this contract shall attend the pre-work safety meeting.
2. The Contractor shall notify the CO a minimum of 48 hours prior to holding the Pre-
Work Safety Meeting so that he/she may attend.
B. As a minimum, the Contractor should conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted and documented by a qualified supervisor or foreman and attended by all construction personnel at the worksite.
1. Documentation of the weekly "toolbox" safety meetings, including the date and time of the meeting, subject discussed, and a list of individuals in attendance shall be provided to the CO upon request.
C. Conduct monthly safety meetings, as required by the CO, for all levels of supervision.
1. The Contractor shall notify the CO a minimum of 48 hours prior to holding the monthly safety meeting so that he/she may attend.
2. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention program.
3.05 HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. A hard hat area will be designated by the CO.
01170-8
1. The hard hat area shall be posted by the Contractor in a manner satisfactory to the
CO.
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times.
1. The Contractor should provide hard hats for use by visitors.
2. Personnel and/or visitors not wearing hard hats will not be permitted on site.
3.06 TRAINING
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage.
1. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
2. The Contractor shall maintain a file of Safety Data Sheets (SDSs) for all hazardous materials that are present on site.
a. SDSs shall be kept in conspicuous locations at the work site.
END OF SECTION 01170
01350-9
SECTION 01350 - DEMOLITION AND REMOVAL
1.01 Scope: Applies to the removal and replacement of items in the existing buildings.
1.02 Protection: The existing walls, floors, ceilings, and other building components not subject to removal or remodeling shall be protected from damage. Any damage shall be repaired to its original condition.
1.03 Removal: Removal shall be by qualified craftsmen.
1.04 Disposal: All debris and materials to be removed shall be disposed of at an approved landfill.
1.05 Salvage: Any materials to be removed and that are salvageable and not otherwise indicated for resuse, shall become the property of the Contractor and shall be removed from the job site.
EXECUTION
2.01 General Removal:
A. Removal shall be done in a neat, workmanlike manner so as to prevent or minimize damage to remaining components and surfaces.
B. Provide straight and plumb terminations on remaining components. Cut and trim flush with adjoining surfaces.
C. Finish disturbed areas to match existing surfaces. Touch-up and clean as required to provide surfaces suitable for finishing.
D. Carefully remove and store materials and equipment to be reused or relocated to prevent damage and reinstall as the work progresses.
• All gutters and downspouts shall be salvaged and reused on the buildings that they are currently on. This project does not include the supply and installation of new gutters and downspouts. All gutters and downspouts shall be reinstalled by the contractor.
E. Any materials or equipment damaged beyond repair will be replaced with the same size, shape, and quality material as existing, at no additional expense to the Government.
01350-10
2.02 Existing Roof Removal:
A. Remove existing shingles and underlayment to the deck.
1. Insure the protection of the public and employees when removing the old shingles from the roofs. Provide appropriate barriers and shields until the removal is complete.
2. Completely remove all shingles, felts, etc. down to the bare wood sheathing.
3. Wood sheathing and fascia shall be inspected for damage and/or rot. If damaged areas are identified, the Contractor shall notify the Contracting office immediately.
Work shall not procede in the area where damage existsarea until approved by the Contracting Officer.
4. Metal flashing and gutters fascia shall be inspected for damage. If damaged areas are identified, the Contractor shall notify the Contracting office immediately. Work shall not procede in the area where damage exists until approved by the Contracting Officer.
5. Remove all vent and pipe boots and replace with new boots.
6. The Contractor shall expose only the portion of the roof that can be removed and replaced on any given day. At the end of each work day, the roof shall be covered so that moisture cannot enter and cause damage to the rafters, roof insulation, and/or interior of the building.
END OF SECTION 01350
01530-11
SECTION 01530 – BARRIERS
1.01 Scope: Install and maintain suitable barriers as necessary to insure the protection of the public, employees and facilities.
PRODUCTS
2.01 General: Material may be new or used but shall be suitable for intended purpose. Fences and barriers shall be structurally adequate and neat in appearance.
2.02 Barricades and Signs: ANSI d6.1 (MUTCD), Part VI.
3.01 Protection of Public:
A. Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry to the work area.
B. Erect and maintain barricades and warning signs in accordance with ANSI D6.1.
C. It is not anticipated that public protection will be an issue as the worksite is within a fenced area, but contractor shall be aware of surroundings and ensure that public safety is maintained.
END OF SECTION 01530
01600-12
SECTION 01600 - USE OF GOVERNMENT FACILITIES, UTILITIES, ETC.
1.01 Scope: Applies to Government facilities at the worksites available for use by the
Contractor.
1.02 Storage Area: A storage area will be made available for materials and equipment at the project location. The Government shall not be responsible for for the Contractor’s equipment and/or materials left on Government property
1.03 Utilities:
A. Drinking water will be available at the worksite.
B. Electrical power will be available at the worksite.
1.04 Toilet facilities are available on site.
END OF SECTION 01600
01900-13
SECTION 01900 - MEASUREMENT AND PAYMENT
1.01 Scope: Applies to method of measurement and basis of payment for work items included under this contract.
1.02 Work: Furnishing all labor, materials, equipment, and other incidentals necessary to successfully complete the project or any portion of it, and carrying out all duties and obligations imposed by the contract on the Contractor.
1.03 Payment: Payment shall be made by the Government for each item completed by the Contractor. Government may have work for all or part of this project completed by independent Contractor(s). The Government has the option to complete various items for this project in phases. Payment shall be in full compensation for all work related to each particular item completed in accordance with these SPECIFICATIONS.
A. Damaged deck, fascia, and/or flashing shall be replaced as required via a modification to the contract and shall be approved by the Contracting Officer prior to performing the required work. Payment for replacement of damaged materials shall be in full compensation of the work completed and shall not exceed the agreed upon amount.
PAYMENT
2.01 Measurement: Completely in place and functional for each item of work performed by the Contractor.
2.02 Payment: Payment will be made at the full bid price for each item for which the Contractor has agreed to perform work. Payment shall include compensation for all materials, labor, equipment, mobilization, and any incidentals necessary to complete the work.
END OF SECTION 01900
07311-14
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
SECTION 07311 - ASPHALT SHINGLES
1.01 Scope: Applies to complete asphalt shingle roofing and underlayment installation.
1.02 Handling, Storage and Protection.
A. Deliver materials in manufacturer's original, unopened containers with labels intact and legible.
B. Never stack shingle bundles more than 4 feet high.
C. Do not store asphalt roof products in direct contact with the ground.
D. Never leave the materials exposed to the weather. Cover them with tarpaulins or plastic bags that are vented to provide free air circulation.
1.03 Job Conditions: Apply roofing materials only in dry weather. Do not apply roofing materials when ambient temperature is below 40 degrees F (4 degrees C). Ensure wood sheathing is dust and dirt free and dry. Ensure all nails and other fasteners are set flush with deck sheathing before applying underlayment materials.
2.01 Shingles: Shingles shall be Owens Corning TruDefinition Duration STORM Impact
Resistant, Malarkey Class 4 shingles or an approved equal. Color to be determined by the
CO.
2.02 Flashing: Refer to Section 7620.
2.03 Underlayment: ASTM D8257, High grade synthetic underlayment.
2.04 Eave Underlayment: ASTM D226, mineral surface roll 36" width with 19" salvage.
2.05 Polyethylene Asphalt Sheeting (Waterproof Underlayment)
A. Self adhering membrane of rubberized asphalt integrally bonded to polyethylene sheeting, complying with ASTM D 1970.
B. Material shall conform to the following requirements:
07311-15
1. Thickness: 40 mils.
2. Tensile Strength: 250 psi (ASTM D 412)
3. Elongation: 250 percent (ASTM D 412)
4. Pliability: Unaffected (ASTM D 146)
5. Color: Gray-black
C. "Ice and Water Shield" by Grace Construction Products Division meets the above specifications or an approved equal.
2.06 Roll Roofing: ASTM D226, mineral surface roll 36” wide with 19” salvage.
2.07 Nails: Galvanized or zinc-coated roofing nails with 7/16 inch diameter head. Length of nails shall be sufficient to penetrate shingles and roof deck.
2.08 Asphalt Plastic Cement: ASTM D2822, Type1.
2.09 Lap Cement: As recommended by the manufacturer.
3.01 Drip Edges: Refer to Section 7620
3.02 Flashings: Refer to Section 7620
3.03 Polyethylene/Rubberized Asphalt Sheeting:
A. Ice dam material shall be applied per manufacturer’s recommendations.
B. For ice dam protection at eaves, Contractor shall install ice dam protection to extend 24 inches inside exterior wall line.
C. Cover deck a minum of 18 inches on either side of ridges.
1. Install 2 courses of 36 inch wide sheeting and overlap to obtain a minumim of 18 inches coverage on either side of the roof ridge.
D. Overlap all ends and edges a minmum of 6 inches.
E. Roll lower edge firmly with hand roller to ensure adhesion to the deck.
3.04 Underlayment: Cover the entire roof with high grade synthetic underlayment before the shingles are laid. Lay the underlayment parallel to the eaves, lapping each course at least 2 inches over the underlying course. Secure the underlayment with only enough nails to hold it in place. If two or more pieces are required to continue a course, lap the ends at least 4
07311-16 inches. End laps in a succeeding course should be located at least 6 feet from end laps in the preceding course. Lap the underlayment 1 foot from both sides over all hips and ridges.
3.05 Shingle Application:
A. Lay shingles with a starter course at the eave line. Starter course may be either a row of shingles trimmed to the shingle manufacturer's recommendations or a strip of mineral surfaced roll roofing at least 7 inches wide.
1. If self-sealing shingles are used for the starter strip, remove the tab portion of each shingle and position the remaining strip with the factory-applied adhesive face up along the eaves. Trim at least 3 inches from the end of the first shingle in the starter strip to ensure that the cutouts of the first course of shingles are not placed over the starter strip joints. Fasten starter strips parallel to the eaves along a line 3 to 4 inches above the eaves. Position the fasteners so that they will not be exposed under the cutouts in the first course.
2. If roll roofing is used for the starter strip, nail along a line 3 to 4 inches above the eaves. Space the nails 12 inches apart. If more than one piece of roofing must be used, lap the end joint 2 inches and cement it.
B. Start the first regular shingle course with a full length strip shingle. The second course then starts with a shingle that has six inches removed, the third course with a shingle that has 12 inches removed and so on through the sixth course which starts with a shingle that has 30 inches removed. Adjacent shingles in each course are all full length.
The seventh course again starts with a full length single and the pattern is repeated every sixth course
3.06 Fastening:
A. Use the correct type and size of fasteners as specified by the shingle manufacturer's recommendation.
B. Use the manufacturer’s recommended number of fasteners per shingle for maximum wind resistance.
C. Do not drive fasteners into known holes or cracks in the roof deck.
D. Do not break the shingle surface with the fastener head.
E. Repair faulty fastening immediately.
F. If a fastener does not penetrate the deck properly, remove the fastener and repair the hole in the shingle with bituminous plastic cement or replace the entire shingle. Then place another fastener nearby.
07311-17
3.07 Nailing: Do not nail into or above factory-applied adhesives. Wherever possible, make sure that no cutout or end joint is less than 2 inches from a nail in an underlying course.
Start nailing from the end nearest the shingle just laid and proceed across. This will prevent buckling. To prevent distortion, do not attempt to realign a shingle by shifting the free end after two nails are in place. Drive nails straight so that the edge of the nail head does not cut into the shingle. Nail heads should be driven flush with the shingle surface, not sunk in it.
END OF SECTION 07311
07620-18
SECTION 07620- METAL FLASHING AND EDGES
1.01 Scope: Applies to the replacing damaged sheet metal flashing and drip edge as necessary for weathertight installation as specified herein.
2.01 Galvanized Sheet Steel: Fed. Spec QQ-S-775D, Type I, Class D.
2.02 Bituminous Plastic Cement: Fed. Spec. SS-C-153B, Type I.
2.03 Nails: Standard commercial quality, zinc-coated, sizes and types as required.
2.04 Screws: Standard commercial quality, zinc-coated, sizes and types as required.
3.01 Drip Edges:
A. Drip edges should extend 3 inches back from roof edge and bend downward over fascia.
B. Apply drip edge directly to roof deck along eaves and over underlayment along rakes.
3.02 Flashing:
A. Water Infiltration: Provide sheet metal flashing and trim that do not allow water infiltration to building interior.
B. Install sheet metal flashing and trim to withstand wind loads, structural movement, thermally induce movement, and exposure to weather without failing, rattling, leaking, and fastener disingagement.
3.03 Roof Penetrations:
A. Pipe Flashing: Form flashing around pipe penetrations and asphalt shingles. Fasten and seal to asphalt shingles as recommended by manufacturer.
1. Vent pipe jacks shall fit snuggly to prevent water infiltration around pipe.
a. Lead: Bend lead over top of pipe and insert inside pipe.
07620-19
b. Metal or rubber pipe jack: Caulk around top of pipe jack to seal around the pipe.
2. Cut shingles to fit around the pipe and embed in asphalt plastic cement where they overlap the flange.
3. The lower part of the flange shall overlap the lower shingles.
END OF SECTION 07620
07630-20
| 1.01 DESCRIPTION |
| A. The work of this Section consists of establishing an effective Accident Prevention Program and providing a safe environment for all personnel and visitors. |
| B. Safety Requirements: All work conducted under this contract shall be in accordance with the Occupational Safety and Health Administration (OSHA) regulations for construction safety (29 CFR part 1926 and 29 CFR part 1910), as stated in Section I (... |
| 1.02 SUBMITTALS |
| A. Accident Prevention Program: The Contractor shall submit for approval at least 10 days prior to beginning on-site work a written Safety Plan. The Contracting Officer (CO) will review the proposed Safety Plan for compliance with OSHA and project r... |
| 1. The Safety Plan shall include: |
| a. Name of responsible supervisor to carry out the program. |
| b. Documentation or schedule of weekly and monthly safety meetings. |
| c. Training, both initial and continuing. |
| d. First aid procedures. |
| e. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, government personnel, and the Contractor's employees. Identify the work included unde... |
| Emergency Response: Planning for possible emergency situations, such as accidents, floods, fires, cave-ins, slides, explosions, power outages, and storms. Such planning shall take into consideration the nature of construction, site conditions, degre... |
| f. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements. |
| g. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials. |
| B. Upon request by the CO, the Contractor shall submit a brief report of safety meetings, of safety inspections, and/or proof of employees' qualifications to perform assigned duties in a safe manner. |
| 1.03 QUALITY ASSURANCE |
| A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the General Provisions: |
| 1. In case of conflicts between Federal, State, and local safety and health requirements, the most stringent shall apply. |
| 2. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. |
| 3. Failure to comply with the requirements of this section and related sections may result in suspension of work. |
| B. Qualifications of Employees: |
| 1. The Contractor shall ensure that employees are physically qualified to perform their assigned duties in a safe manner. |
| 2. The Contractor shall not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury. |
| a. At the discretion of the CO, employees whose ability or alertness appears to be impaired because of drugs, fatigue, illness, intoxication, or other conditions may be asked to remove himself/herself from the site. |
| b. The presence of an employee whose ability or alertness appears to be impaired because of drugs, fatigue, illness, intoxication, or other conditions may result in a suspension of work. |
| 3. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. |
| a. The Contractor shall provide operating instructions for all equipment. |
| b. The Contractor shall require newly hired operators be tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment. |
| 1.04 ACCIDENT REPORTING |
| A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. |
| 1. In the case that a reportable accident occurs, the Contractor shall notify the CO immediately or as soon as practically possible. |
| 2. Within 7 days of a reportable accident, the Contractor shall fill out and forward to the CO a DI-134 form. |
| a. DI-134 forms may be obtained from CO. |
| B. All Other Accidents: The Contractor shall report all other accidents to the CO as soon as possible. |
| 1. The Contractor shall assist the CO and other officials as required in the investigation of the accident. |
| 2.01 FIRST AID FACILITIES: Provide adequate facilities for the number of employees and the type of construction at the site. |
| 2.02 PERSONNEL PROTECTIVE EQUIPMENT (PPE): PPE shall meet the requirements of NIOSH and MSHA, where applicable, as well as ANSI. |
| 2.03 BARRIERS: See SECTION 01530 BARRIERS. |
| 3.01 EMERGENCY INSTRUCTIONS: The Contractor shall post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site. |
| 3.02 ESCAPE ROUTES: The Contractor shall provide and maintain adequate escape routes at all times in accordance with the Life Safety Code (NFPA 101-91). |
| 3.03 PROTECTIVE EQUIPMENT: The Contractor shall inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual. |
| A. The Contractor shall inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation. |
| 3.04 SAFETY MEETINGS |
| A. Pre-Work Safety Meeting: Prior to beginning work, the Contractor shall conduct a Pre-Work Safety Meeting to discuss planned operations, types of equipment to be used, and any task or site specific safety hazards associated with the work to be cond... |
| 1. ALL personnel, including supervisors, workers, and subcontractors who will be performing work under this contract shall attend the pre-work safety meeting. |
| 2. The Contractor shall notify the CO a minimum of 48 hours prior to holding the Pre-Work Safety Meeting so that he/she may attend. |
| B. As a minimum, the Contractor should conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted and documented by a qualified supervisor or foreman and attended by all construction personnel at the worksite. |
| 1. Documentation of the weekly "toolbox" safety meetings, including the date and time of the meeting, subject discussed, and a list of individuals in attendance shall be provided to the CO upon request. |
| C. Conduct monthly safety meetings, as required by the CO, for all levels of supervision. |
| 1. The Contractor shall notify the CO a minimum of 48 hours prior to holding the monthly safety meeting so that he/she may attend. |
| 2. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the accident prevention progra... |
| 3.05 HARD HATS AND PROTECTIVE EQUIPMENT AREAS |
| A. A hard hat area will be designated by the CO. |
| 1. The hard hat area shall be posted by the Contractor in a manner satisfactory to the CO. |
| B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times. |
| 1. The Contractor should provide hard hats for use by visitors. |
| 2. Personnel and/or visitors not wearing hard hats will not be permitted on site. |
| 3.06 TRAINING |
| A. First Aid: Provide adequate training to ensure prompt and efficient first aid. |
| B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. |
| 1. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury. |
| 2. The Contractor shall maintain a file of Safety Data Sheets (SDSs) for all hazardous materials that are present on site. |
| a. SDSs shall be kept in conspicuous locations at the work site. |