About this file

This document is a complete set of construction documents for the USDA National Center for Animal Health Building 7 Lighting and Controls Upgrade project located at 1920 Dayton Avenue, Ames, Iowa. The project, identified by USDA Contract Number 12505B23F0175, involves upgrading the lighting systems and installing new lighting control infrastructure throughout the facility's three operational levels, with construction documents dated September 25, 2023.

The scope of work includes complete removal and replacement of all existing luminaires on a one-for-one basis while retaining existing electrical wiring, installation of new lighting control devices in locations of existing equipment, and establishment of a centralized lighting control system with networked architecture located on the third-floor mechanical mezzanine. Key technical requirements include compliance with 2021 International Building Code, 2021 International Energy Conservation Code, and 2023 National Electrical Code standards. The project specifies a phased implementation approach coordinated with on-site operations teams to maintain continuous facility operation, with particular emphasis on preserving through-slab penetrations to prevent air transmission between research areas and mechanical spaces. The lighting control system utilizes Paradigm/Unison equipment with BACnet/IP communication protocol to the Building Automation System, including programmable controls for research suite holding areas with capabilities for schedule modification, light level adjustment (measured in footcandles), and moonlight functionality accessible through pass-code-protected graphical user interfaces at each suite entry point. Emergency lighting, exit signage, and washdown-rated equipment are specified throughout, with local override switches providing manual control with 30-minute timeout to return to preprogrammed schedules for cleaning operations.

View the file

Other files for this federal contract opportunity

Other files attached to Lighting Renovation for USDA ARS in Ames, IA (Amended), newest first.
File Type Posted
C05b Attachment 9 Q and A.pdf PDF
C05 SF30 1232SA26Q09620001.pdf PDF
C05a Attachment 8 Specifications Addendum.pdf PDF
C04 SF1442 RFQ 1232SA26Q0962.pdf PDF
C04a Attachment 1 Statement of Work 1160423.pdf PDF
C04f Attachment 6 ARS_372_REQUEST FOR PAYMENT TRANSMITTAL.pdf PDF
C04b Attachment 2 Specifications 1160423.pdf PDF
C04g Attachment 7 SF1413 Subcontractor Acknowlegement.pdf PDF
C04e Attachment 5 ARS_371_CONSTRUCTION PROGRESS.pdf PDF
C04d Attachment 4 Wage Determination.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

D

ORDER DATE:

TASK ORDER NO.:

A

U S

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

COPYRIGHT BAILEY EDWARD 2025 - BED# 23116

DWG. NO.

SHEET OF

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

Agricultural Research Service

KWL

CHK

23116 t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr Suite 2800 Chicago, IL 60601-2308 ©2024 Bailey Edward Design Design Firm License No. 184-001962

TBD

KARLA TEBBEN

BEN A'HEARN

TBDREO

1 8/12/2025 BED 100% CONSTRUCTION DOCUMENTS

12505B23F0175

25 September, 2023 33

Pr in t D at e/ Ti m e:

/1

1/

:1

PM

P:

\P ro je ct F ile s\

-0

0-

U

SD

A

N C

AH

B

LD

G

L

IG

H

TI

N

G R

EN

O

VA

TI

O N

D

ES

IG

N

\0 2_

C

AD

\M

EP

COVER SHEET

USDA NCAH BUILDING 7 LIGHTING RENOVATION

CODE INFORMATION & STANDARDS

2021 INTERNATIONAL BUILDING CODE

2021 INTERNATIONAL ENERGY CONSERVATION CODE

2021 INTERNATIONAL EXISTING BUILDING CODE

2021 INTERNATIONAL MECHANICAL CODE

INDEX - GENERAL

GENERAL PROJECT NOTES

USDA CONTRACT NO.: 12505B23F0175

1. THE CONTRACTOR SHALL COORDINATE, SCHEDULE, TEST AND PROVIDE ANY EFFORT NECESSARY TO RESULT IN A COMPLETE

AND OPERATING SYSTEM.

2. DETAILS SHOWN ARE INDICATIVE OF THE CHARACTER, PROFILES, MATERIAL, AND SYSTEMS REQUIRED FOR THE WORK. THE CONTRACTOR SHALL PROVIDE ALL EQUIPMENT, LABOR, SUNDRIES, TESTING AND REPORTING TO PROVIDE A COMPLETE AND OPERATIONAL SYSTEM. THE CONTRACTOR SHALL INCLUDE THOSE CONDITIONS NOT COVERED BY SPECIFIC DETAILS.

3. WHERE THE DESIGN INTENT CANNOT BE DETERMINED FROM THE DRAWINGS OR SPECIFICATIONS, CONSULT THE

CONTRACTING OFFICER'S REPRESENTATIVE BEFORE PROCEEDING WITH THE WORK.

4. FIELD VERIFY ALL CONDITIONS & DIMENSIONS BEFORE PROCEEDING WITH THIS WORK. IF CONDITIONS VARY FROM INFORMATION WITHIN THE CONTRACT DOCUMENTS, CONSULT THE ARCHITECT OR ENGINEER BEFORE PROCEEDING WITH

THE WORK.

5. THE CONTRACTOR SHALL NOTIFY THE CONTRACTING OFFICER'S REPRESENTATIVE OF ANY AND ALL DISCREPANCIES BETWEEN THE CONTRACT DOCUMENTS AND EXISTING CONDITIONS PRIOR TO PROCEEDING WITH THE WORK. PROVIDE RFI'S

DURING COORDINATION DRAWING EFFORT TO AVOID FIELD REVISIONS.

6. PROVIDE A FULL AND COMPLETE, OPERATING LIGHTING AND LIGHTING CONTROL SYSTEM.

7. ALL PENETRATIONS OF ROOF AND FIRE RATED WALL OR SMOKE PARTITIONS SHALL BE PATCHED & REPAIRED AS REQUIRED TO MAINTAIN THE EXISTING FIRE RATING OR SMOKE INFILTRATION INTEGRITY OF THE FLOOR AND WALL. ALL SLEEVES, WIREWAYS, CABLE TRAYS, PIPES, DUCTWORK, ARE TO BE FIRE SEALED TIGHT TO THE WALL OR FLOOR PENETRATIONS TO

MAINTAIN THE REQUIRED CODE COMPLIANT FIRE RATING.

8. THE CONTRACTOR IS RESPONSIBLE FOR THE TIMELY REMOVAL OF ALL DEMOLITION DEBRIS AND PROTECTION OF EXISTING AREAS WHICH ARE NOT AFFECTED BY THE SCOPE OF WORK. THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THE CONTRACTING OFFICER'S REPRESENTATIVE OF ANY INCIDENTAL DAMAGE ASSOCIATED WITH THEIR EFFORTS. ANY DAMAGE TO THE PREMISES SHALL BE BROUGHT BACK TO ORIGINAL CONDITION AT THE COST OF THE GENERAL CONTRACTOR OR SUBCONTRACTOR INFLICTING THE DAMAGE. RUBBISH SHALL BE REMOVED DAILY AT THE END OF EACH SHIFT.

9. CONTRACTOR RESPONSIBLE FOR PROTECTING EXISTING WALL, CEILING, AND FLOOR FINISHES DURING CONSTRUCTION.

REPAIR ANY DAMAGES RESULTING FROM THIS PROJECT AT NO ADDITIONAL COST TO THE OWNER.

10. ALL SUBSTITUTIONS TO BE REVIEWED AND APPROVED IN WRITING BY ARCHITECT/ENGINEER REFER TO SPECIFICATIONS FOR

SUBSTITUTION PROCEDURES.

11. PROVIDE TEMPORARY PROTECTION FROM DUST, NOISE, DAMAGE, ETC. GRINDING OR HOT WORK SHALL BE ACCOMPANIED WITH SOURCE CAPTURE DEVICES TO REMOVE PARTICULATE AND ODORS. THE CONTRACTOR SHALL OBTAIN DAILY PERMITS

FOR HOT WORK.

12. MAINTAIN EXISTING BUILDING EXITS. THE BUILDING IS TO REMAIN IN COMPLIANCE WITH ALL ASPECTS OF THE LIFE SAFETY CODE DURING THE COURSE OF CONSTRUCTION INCLUDING BUT NOT LIMITED TO EXISTING FIRE ALARM SYSTEM, SMOKE AND

FIRE DETECTION SYSTEM, SPRINKLER SYSTEM, ETC. AS APPLICABLE.

13. INDIVIDUAL DRAWINGS ARE PART OF A LARGER SET OF DRAWINGS WHICH, WHEN COMPLETE CONSIST OF ALL DRAWINGS LISTED BY THE INDEX OF DRAWINGS. THE WORK DESCRIBED BY THE DRAWINGS OF ANY ONE DISCIPLINE MAY BE AFFECTED BY THE WORK DESCRIBED ON DRAWINGS OF ANOTHER DISCIPLINE AND MAY REQUIRE REFERENCE TO DRAWINGS OF ANOTHER DISCIPLINE. PARTIAL SETS OF DRAWINGS ARE INCOMPLETE AND SHALL NOT BE DISTRIBUTED AND UTILIZED BY THE CONTRACTOR. IT IS THE CONTRACTOR'S RESPONSIBILITY TO REVIEW AND COORDINATE THE WORK OF ALL SUBCONTRACTORS, TRADES, AND SUPPLIERS WITH THE REQUIREMENTS OF THE CONTRACT DOCUMENTS BEFORE COMMENCING CONSTRUCTION, AND TO ASSURE THAT ALL PARTIES ARE AWARE OF ALL REQUIREMENTS, REGARDLESS OF

WHERE THE REQUIREMENTS OCCUR ON THE CONTRACT DOCUMENTS.

14. THE CONTRACTOR IS RESPONSIBLE FOR COORDINATING THE WORK OF ALL SUBCONTRACTORS, TRADES, AND SUPPLIERS, THE CONTRACTOR SHALL ENDEAVOR TO IDENTIFY AND NOTIFY THE ARCHITECT OF ANY CONFLICTS BETWEEN THE WORK OF DIFFERENT PARTIES AT THE EARLIEST POSSIBLE DATE SO AS TO ALLOW REASONABLE AND ADEQUATE TIME FOR THE CONFLICT TO BE RESOLVED WITHOUT DELAYING THE WORK. ALL DEVIATIONS FROM THAT WHICH IS REQUIRED BY THE

CONTRACT DOCUMENTS MUST BE APPROVED IN ADVANCE BY THE OWNER.

15. THE CONTRACTOR SHALL COORDINATE LOCATIONS FOR STORAGE OF CONSTRUCTION MATERIALS, DUMPSTER ,TOOL STORAGE, AND LAY-DOWN SPACE WITH THE CONTRACTING OFFICER'S REPRESENTATIVE AND FIELD CONDITIONS.

16. THE CONTRACTOR SHALL MANAGE KICK-OFF AND PROGRESS MEETINGS EVERY OTHER WEEK, PROVIDE AGENDA RFI LOG, SUBMITTAL LOG, AND THREE WEEK LOOK AHEAD 24 HOURS IN ADVANCE OF THE MEETING. PROVIDE MINUTES FOR REVIEW

WITHIN 48 HOURS OF THE MEETING.

17. THE DRAWINGS REPRESENT DESIGN INTENT. THEY ARE SCALED GRAPHIC REPRESENTATIONS OF A LARGE BUILDING. THE DRAWINGS ARE DIAGRAMMATIC AND DO NOT SHOW ALL OFFSETS, FITTINGS, SUPPORTS, OR DEVICES TO RESULT IN A SUCCESSFUL INSTALLATION. THE CONTRACTOR SHALL COORDINATE WITH THE FIELD CONDITIONS, TRADES, AND EQUIPMENT

MANUFACTURES TO PROVIDE A FULL AND COMPLETE INSTALLATION.

18. SCHEDULE EFFORTS WITH COR. IDENTIFY LOCATIONS OWNER NEEDS TO REMOVE OR RELOCATE ITEMS TO FACILITATE

WORK.

19. PERFORMANCE OF ANY PATCHES SHALL ACCOMMODATE BIO-SAFTEY WASHDOWN REQUIREMENTS.

20. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ENSURING THAT DELIVERIES ARE MADE TO THE PROJECT SITE. DELIVERIES SHALL NOT BE MADE TO ANY OTHER BUILDING, USDA WAREHOUSE, OR OTHER LOCATION ON CAMPUS.

SCOPE OF WORK

1. THE PROJECT SHALL BE EXECUTED IN PHASES SO THAT RESEARCH CAN CONTINUE DURING CONSTRUCTION.

RESEARCH SUITES SHALL BE DECONTAMINATED BY THE USDA PRIOR TO COMMENCING WITH CONSTRUCTION IN THE

SUITE. THE CONTRACTOR SHALL DEVELOP AND SUBMIT A PHASING PLAN.

2. VISIT THE SITE TO WALK THROUGH THE SUITES, PLAN FOR COMPLETION OF CONSTRUCTION, PLAN FOR

STORAGE/STAGING, CHOOSE A DUMPSTER LOCATION AND BECOME FAMILIAR WITH THE SITE.

3. PROVIDE PRODUCT DATA SUBMITTALS, QUALIFICATIONS, CONTROL SHOP DRAWINGS, SCHEDULE, AND OTHER

DOCUMENTS REQUIRED BY THE SPECIFICATIONS.

4. PROVIDE EFFORTS TO REMOVE THE LIGHTS AND LIGHTING CONTROLS. DISPOSE OF ITEMS IN AN APPROPRIATE MANNER. RECYCLE METALLIC MATERIALS TO THE GREATEST EXTENT POSSIBLE. REFER TO SPECIFICATIONS FOR APPROPRIATE DISPOSAL. THE CONTRACTOR SHALL PROVIDE LOAD TICKETS/RECEIPT COPIES TO THE COR

5. PROVIDE AND INSTALL LIGHTS AND LIGHTING CONTROLS. REPAIR FINISHES DAMAGED OR EXPOSED DURING

CONSTRUCTION. FINISHES SHALL MATCH OR BLEND WITH THE PRE-ALTERATION FINISHES.

6. THE CONTRACTOR SHALL HIRE A VENDOR CERTIFIED TO INSTALL JOHNSON CONTROLS INCORPORATED METASYS BUILDING AUTOMATION SYSTEMS TO EXTEND THE BAS AS NECESSARY TO MONITOR THE LIGHTING CONTROLS. PROVIDE ENGINEERING, FIELD VERIFICATION, PROGRAMMING, AND GRAPHIC USER INTERFACE SO THAT ALARMS ARE TRANSMITTED FROM THE LIGHTING CONTROLS TO THE BUILDING AUTOMATION SYSTEM TO NOTIFY THE USDA

ENGINEERS OF A FAULT.

7. AT THE END OF EACH PHASE CONTRACTOR EFFORTS SHALL BE REVIEWED AND CORRECTIONS COMPLETED PRIOR TO

TURNOVER TO THE USDA.

8. PROVIDE EFFORTS TO COMMISSION THE LIGHTING UPGRADES AND THE LIGHTING CONTROLS UPGRADE. VERIFY

SEQUENCES OF OPERATIONS IS ACCOMMODATED BY CONTROLS AND PROGRAMMING.

9. SUBMIT TRAINING AGENDA FOR REVIEW. TRAINING SHALL BE RECORDED BY A PROFESSIONAL VIDEOGRAPHER.

10. PROVIDE CLOSEOUT DOCUMENTS INCLUDING WARRANTY, AS-BUILT DOCUMENTS, TESTING REPORTS, AND

COMMISSIONING REPORT.

SEQUENCE OF EFFORTS

1. SUBMIT NECESSARY FRONT END PAPERWORK, BONDS, INSURANCE.

2. OBTAIN ANY SECURITY CLEARANCES OR BACKGROUND CHECKS NECESSARY TO ACCESS FACILITY.

3. SUBMIT QUALIFICATION DATA FOR TECHNICAL TRADES. REFER TO PROJECT MANUAL.

4. VISIT THE SITE TO VERIFY EXISTING CONDITIONS AND PLAN FOR COMPLETION OF CONSTRUCTION.

5. DEVELOP AND SUBMIT COORDINATED SHOP DRAWINGS WITH SIGN OFF FROM THE TRADES. PROVIDE PRODUCT DATA.

DEVELOP STRATEGY FOR TEMPORARY LIGHTING. SUBMIT PLAN, NARRATIVE, ETC.

6. DEVELOP A SCHEDULE THAT OUTLINES KEY MILESTONES FOR EACH AREA OF THE BUILDING.

7. THE SCOPE OF WORK IN THE RESEARCH SUITES SHALL BE EXECUTED IN PHASES SO THAT RESEARCH IS ABLE TO CONTINUE. CONTRACTOR SHALL HAVE ACCESS TO A SINGLE SUITE AT ANY GIVEN TIME. THE CONTRACTOR SHALL GIVE NOTICE THAT THE PHASE IS COMPLETED AND SHALL OBTAIN NOTICE FROM THE USDA TO MOVE ON TO THE NEXT PHASE.

8. COORDINATE WITH THE USDA TO ENSURE THAT THE SPACES HAVE BEEN CLEARED AND DECONTAMINATED. VERIFY THAT SPACE PRESSURIZATION CONTROLS THROUGH THE BUILDING AUTOMATION SYSTEM HAVE BEEN ADJUSTED BY THE USDA

FOR THE ACTIVE CONSTRUCTION AREA. ENSURE THAT BUILDING PRESSURIZATION HAS

9. REMOVE LIGHTS AND CONTROLS FROM THE PHASE AREA.

10. PROVIDE AND INSTALL LIGHTS AND CONTROLS WITHIN THE PHASE AREA.

11. PROVIDE COMMISSIONING SERVICES WITHIN THE PHASED AREA. PROVIDE THE FINAL CX REPORT WITH CLOSEOUT.

12. COORDINATE WITH THE USDA TO ENSURE THAT BUILDING PRESSURIZATION HAS BEEN RETURNED TO NORMAL

OPERATION FOR EACH OF THE COMPLETED PHASES.

13. PERFORM TRAINING AFTER EACH PHASE HAS BEEN COMMISSIONED. THE FINAL TRAINING SESSION SHALL BE RECORDED

BY A PROFESSIONAL VIDEOGRAPHER.

14. PROVIDE CLOSEOUT DOCUMENTS.

15. PERFORM ANY WARRANTY WORK.

2023 NATIONAL ELECTRIC CODE

G000 COVER SHEET

G001 LOWER LEVEL GENERAL PLAN

PROJECT SUMMARY

UPGRADE THE LIGHTING AND THE LIGHTING CONTROLS SYSTEM. EXTEND THE BUILDING

AUTOMATION SYSTEM TO MONITOR THE LIGHTING CONTROLS.

AREA MAP

LOCATION MAP

NATIONAL CENTER FOR ANIMAL HEALTH

1920 DAYTON AVENUE, AMES, IA 50010

G002 FIRST FLOOR GENERAL PLAN

G003 PENTHOUSE GENERAL PLAN

INDEX - ELECTRICAL

USDA NATIONAL CENTER FOR

ANIMAL HEALTH (NCAH)

ELECTRICAL COVERSHEET

LEVEL 01 DEMOLITION PLAN - OVERALL - LIGHTING

LEVEL 01 DEMOLITION PLAN - AREA A - LIGHTING

LEVEL 01 DEMOLITION PLAN - AREA B - LIGHTING

LEVEL 01 DEMOLITION PLAN - AREA C - LIGHTING

LEVEL 02 DEMOLITION PLAN - OVERALL - LIGHTING

LEVEL 02 DEMOLITION PLAN - AREA A - LIGHTING

LEVEL 02 DEMOLITION PLAN - AREA B - LIGHTING

LEVEL 02 DEMOLITION PLAN - AREA C&D - LIGHTING

LEVEL 03 DEMOLITION PLAN - OVERALL - LIGHTING

LEVEL 03 DEMOLITION PLAN - AREA A - LIGHTING

LEVEL 03 DEMOLITION PLAN - AREA B - LIGHTING

LEVEL 03 DEMOLITION PLAN - AREA C - LIGHTING

LEVEL 01 PLAN - OVERALL - LIGHTING

LEVEL 01 PLAN - AREA A - LIGHTING

LEVEL 01 PLAN - AREA B - LIGHTING

LEVEL 01 PLAN - AREA C - LIGHTING

LEVEL 02 PLAN - OVERALL - LIGHTING

LEVEL 02 PLAN - AREA A - LIGHTING

LEVEL 02 PLAN - AREA B - LIGHTING

LEVEL 02 PLAN - AREA C&D - LIGHTING

LEVEL 03 PLAN - OVERALL - LIGHTING

LEVEL 03 PLAN - AREA A - LIGHTING

LEVEL 03 PLAN - AREA B - LIGHTING

LEVEL 03 PLAN - AREA C - LIGHTING

ELECTRICAL DETAILS

LIGHTING CONTROL SYSTEM DETAILS

LIGHTING CONTROL SYSTEM CONTACT SCHEDULES

ELECTRICAL SCHEDULES

E000 E101 E101A E101B E101C E102 E102A E102B E102C E103 E103A E103B E103C E201 E201A E201B E201C E202 E202A E202B E202C E203 E203A E203B E203C E400 E401 E402 E600

G000

TASK ORDER NO.:

A

U S

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

COPYRIGHT BAILEY EDWARD 2025 - BED# 23116

DWG. NO.

SHEET OF

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

Agricultural Research Service

KWL

CHK

23116 t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr Suite 2800 Chicago, IL 60601-2308 ©2024 Bailey Edward Design Design Firm License No. 184-001962

TBD

KARLA TEBBEN

BEN A'HEARN

TBDREO

1 8/12/2025 BED 100% CONSTRUCTION DOCUMENTS

12505B23F0175

25 September, 2023 33

Pr in t D at e/ Ti m e:

/1

1/

:1 ro je ct F ile s\

-0

0-

U

SD

A

N C

AH

B

LD

G

L

IG

H

TI

N

G R

EN

O

VA

TI

O N

D

ES

IG

N

\0 2_

C

AD

\M

EP

LOWER LEVEL GENERAL PLAN

SCALE: 1/16" = 1'-0"

0 8' 16' 32'

GENERAL PLAN - LOWER LEVEL

G001

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

%%UPLAN NOTES

AutoCAD SHX Text

1. THE CONTRACTOR SHALL VISIT THE SITE TO BECOME THE CONTRACTOR SHALL VISIT THE SITE TO BECOME FAMILIAR WITH THE FACILITY, VERIFY THE EXISTING CONDITIONS, AND PLAN FOR COMPLETION ON THE PROJECT. 2. THE CONTRACTOR SHALL DEVELOP A SCHEDULE WITH THE CONTRACTOR SHALL DEVELOP A SCHEDULE WITH MILESTONE TO DEMONSTRATE COMPLETION OF IMPORTANT TASK AND PHASING. 3. THE PROJECT SHALL BE EXECUTED IN PHASES SO THAT A THE PROJECT SHALL BE EXECUTED IN PHASES SO THAT A PORTION OF THE RESEARCH SUITES ARE AVAILABLE FOR RESEARCHERS. COORDINATE SHUT DOWN OF RESEARCH SUITES WITH THE USDA. INCLUDE THE PHASING IN THE PROJECT SCHEDULE. 4. PROVIDE PRODUCT DATA, QUALIFICATIONS, SHOP DRAWINGS PROVIDE PRODUCT DATA, QUALIFICATIONS, SHOP DRAWINGS AND SUBMITTALS FOR REVIEW AND COMMENT. 5. EFFORTS SHALL BE PERFORMED IN A SAFE, NEAT AND EFFORTS SHALL BE PERFORMED IN A SAFE, NEAT AND ORDERLY FASHION BY SKILLED CRAFT WORKERS EXPERIENCED IN THE SPECIFIC TRADE. 6. THE USDA SHALL DECONTAMINATE RESEARCH PRIOR TO THE USDA SHALL DECONTAMINATE RESEARCH PRIOR TO CONTRACTOR ACCESS TO THE SPACE. THE CONTRACTOR SHALL COORDINATE ACCESS TO THE RESEARCH SPACES WITH THE USDA. 7. COORDINATE LOCATIONS FOR DUMPSTER, DELIVERY AND COORDINATE LOCATIONS FOR DUMPSTER, DELIVERY AND STORAGE OF EQUIPMENT WITH THE USDA. PROVIDE DUMPSTER SERVICE AND TEMPORARY FACILITY TO STORE PRODUCTS THAT HAVE BEEN DELIVERED AND ARE AWAITING INSTALLATION. 8. CLEAR THE WORK SITE AT THE END OF EACH SHIFT TO CLEAR THE WORK SITE AT THE END OF EACH SHIFT TO ENSURE THE FACILITY IS FREE OF CONSTRUCTION DEBRIS. 9. THE CONTRACTOR SHALL PATCH AND REPAIR FINISHES THE CONTRACTOR SHALL PATCH AND REPAIR FINISHES IMPACTED BY THE WORK EFFORTS. COORDINATE SEQUENCING OF WORK AMONGST THE TRADES. 10. SUBMIT CLOSEOUT DOCUMENTS INCLUDING TESTING SUBMIT CLOSEOUT DOCUMENTS INCLUDING TESTING REPORTS, AS-BUILT DRAWINGS, WARRANTY, OPERATIONS MANUAL AND LOAD TICKETS/RECEIPTS FROM RECYCLED MATERIALS. 11. PROVIDE TEMPORARY LIGHTING DURING CONSTRUCTION PROVIDE TEMPORARY LIGHTING DURING CONSTRUCTION EFFORTS TO ACCOMMODATE SHUT DOWNS OF CIRCUITS DURING LIGHTING UPGRADES.

AutoCAD SHX Text

%%UKEYNOTES

AutoCAD SHX Text

1. UPGRADE LIGHT FIXTURE. REPAIR FINISHES DISRUPTED UPGRADE LIGHT FIXTURE. REPAIR FINISHES DISRUPTED BY REMOVAL AND REPLACEMENT. 2. UPGRADE EMERGENCY LIGHT FIXTURE. REPAIR FINISHES UPGRADE EMERGENCY LIGHT FIXTURE. REPAIR FINISHES DISRUPTED BY REMOVAL AND REPLACEMENT. 3. UPGRADE THE OCCUPANCY SENSOR. REPAIR FINISHES UPGRADE THE OCCUPANCY SENSOR. REPAIR FINISHES DISRUPTED BY EFFORTS TO UPGRADE.

AutoCAD SHX Text

%%ULEGEND

AutoCAD SHX Text LIGHT FIXTURE NIGHT LIGHT FIXTURE BATTERY EMERGENCY FIXTURE EMERGENCY FIXTURE WITH REMOTE BATTERY EXIT SIGN OCCUPANCY SENSOR

AutoCAD SHX Text

OS

TASK ORDER NO.:

A

U S

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

COPYRIGHT BAILEY EDWARD 2025 - BED# 23116

DWG. NO.

SHEET OF

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

Agricultural Research Service

KWL

CHK

23116 t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr Suite 2800 Chicago, IL 60601-2308 ©2024 Bailey Edward Design Design Firm License No. 184-001962

TBD

KARLA TEBBEN

BEN A'HEARN

TBDREO

1 8/12/2025 BED 100% CONSTRUCTION DOCUMENTS

12505B23F0175

25 September, 2023 33

Pr in t D at e/ Ti m e:

/1

1/

:1 ro je ct F ile s\

-0

0-

U

SD

A

N C

AH

B

LD

G

L

IG

H

TI

N

G R

EN

O

VA

TI

O N

D

ES

IG

N

\0 2_

C

AD

\M

EP

FIRST FLOOR GENERAL PLAN

SCALE: 1/16" = 1'-0"

0 8' 16' 32'

GENERAL PLAN - FIRST FLOOR

G002

AutoCAD SHX Text b

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text f

AutoCAD SHX Text d

AutoCAD SHX Text r

AutoCAD SHX Text p

AutoCAD SHX Text s

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text d

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text r

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text HL3-11k

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text P

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text L

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

MH

AutoCAD SHX Text

MH

AutoCAD SHX Text

MH

AutoCAD SHX Text

AREA WITHIN BORDERS REPRESENT THE RESEARCH SUITES.

AutoCAD SHX Text

RESEARCH VESTIBULE

AutoCAD SHX Text

RESEARCH VESTIBULE

AutoCAD SHX Text

RESEARCH VESTIBULE

AutoCAD SHX Text

RESEARCH VESTIBULE

AutoCAD SHX Text

RESEARCH VESTIBULE

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

ANIMAL HOLDING

AutoCAD SHX Text

%%UKEYNOTES

AutoCAD SHX Text

1. UPGRADE LIGHT FIXTURE. REPAIR FINISHES DISRUPTED UPGRADE LIGHT FIXTURE. REPAIR FINISHES DISRUPTED BY REMOVAL AND REPLACEMENT. 2. UPGRADE EMERGENCY LIGHT FIXTURE. REPAIR FINISHES UPGRADE EMERGENCY LIGHT FIXTURE. REPAIR FINISHES DISRUPTED BY REMOVAL AND REPLACEMENT. 3. UPGRADE THE OCCUPANCY SENSOR. REPAIR FINISHES UPGRADE THE OCCUPANCY SENSOR. REPAIR FINISHES DISRUPTED BY EFFORTS TO UPGRADE. 4. UPGRADE EXTERIOR LIGHTS, REPAIR FINISHES UPGRADE EXTERIOR LIGHTS, REPAIR FINISHES DISRUPTED BY EFFORTS TO UPGRADE. 5. UPGRADE CONTROLS FOR THE LIGHTING.UPGRADE CONTROLS FOR THE LIGHTING.

AutoCAD SHX Text

%%ULEGEND

AutoCAD SHX Text LIGHT FIXTURE NIGHT LIGHT FIXTURE BATTERY EMERGENCY FIXTURE EMERGENCY FIXTURE WITH REMOTE BATTERY EXIT SIGN OCCUPANCY SENSOR EXTERIOR LIGHT FIXTURE

OS

TASK ORDER NO.:

A

U S

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

COPYRIGHT BAILEY EDWARD 2025 - BED# 23116

DWG. NO.

SHEET OF

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

Agricultural Research Service

KWL

CHK

23116 t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr Suite 2800 Chicago, IL 60601-2308 ©2024 Bailey Edward Design Design Firm License No. 184-001962

TBD

KARLA TEBBEN

BEN A'HEARN

TBDREO

1 8/12/2025 BED 100% CONSTRUCTION DOCUMENTS

12505B23F0175

25 September, 2023 33

Pr in t D at e/ Ti m e:

/1

1/

:2 ro je ct F ile s\

-0

0-

U

SD

A

N C

AH

B

LD

G

L

IG

H

TI

N

G R

EN

O

VA

TI

O N

D

ES

IG

N

\0 2_

C

AD

\M

EP

SCALE: 1/16" = 1'-0"

0 8' 16' 32'

LIGHTING - MEZZANINE

FIRST FLOOR GENERAL PLAN

G003

AutoCAD SHX Text

OS

AutoCAD SHX Text

OS

AutoCAD SHX Text

AutoCAD SHX Text P

AutoCAD SHX Text P

AutoCAD SHX Text P

AutoCAD SHX Text P

AutoCAD SHX Text P

AutoCAD SHX Text

LOCATION OF BUILDING AUTOMATION SYSTEM

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

TYPICAL

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

CNTL

AutoCAD SHX Text

CNTL

AutoCAD SHX Text

%%UKEYNOTES

AutoCAD SHX Text

1. UPGRADE LIGHT FIXTURE. REPAIR FINISHES DISRUPTED UPGRADE LIGHT FIXTURE. REPAIR FINISHES DISRUPTED BY REMOVAL AND REPLACEMENT. 2. UPGRADE EMERGENCY LIGHT FIXTURE. REPAIR FINISHES UPGRADE EMERGENCY LIGHT FIXTURE. REPAIR FINISHES DISRUPTED BY REMOVAL AND REPLACEMENT. 3. UPGRADE THE OCCUPANCY SENSOR. REPAIR FINISHES UPGRADE THE OCCUPANCY SENSOR. REPAIR FINISHES DISRUPTED BY EFFORTS TO UPGRADE. 4. THE LIGHTING CONTROL SYSTEM SHALL BE UPGRADED THE LIGHTING CONTROL SYSTEM SHALL BE UPGRADED AND TIED INTO THE BUILDING AUTOMATION SYSTEM, COORDINATE EFFORTS AMONGST THE CONTRACTORS AND USDA STAKEHOLDERS.

AutoCAD SHX Text

%%ULEGEND

AutoCAD SHX Text LIGHT FIXTURE NIGHT LIGHT FIXTURE BATTERY EMERGENCY FIXTURE EMERGENCY FIXTURE WITH REMOTE BATTERY EXIT SIGN OCCUPANCY SENSOR MAIN CONTROLLER FOR LIGHTING CONTROLS

AutoCAD SHX Text

OS

CNTL

1. THE COMPLETE INSTALLATION SHALL BE IN ACCORDANCE WITH THE ADA STANDARDS FOR

ACCESSIBLE DESIGN. REFER TO THE ADA GUIDELINES FOR ALL CONFIGURATION DETAILS ON

THIS PAGE FOR ADDITIONAL INFORMATION.

2. CIRCUIT NUMBERS ARE SHOWN FOR CIRCUIT IDENTIFICATION. CIRCUITING SHALL AGREE

WITH NUMBERING ON THE PANEL PROVIDED. COMMON NEUTRALS MAY NOT BE USED FOR

BRANCH CIRCUITS. BALANCE THE LOAD ON PANEL AS EVENLY AS POSSIBLE BETWEEN EACH

PHASE.

3. SURFACE MOUNT ALL LIGHTING CONTROL DEVICES AT +42" FROM FLOOR (CENTERLINE

DIMENSION), EXCEPT WHERE OTHERWISE NOTED.

4. ALL MATERIALS USED TO SEAL PENETRATIONS OF FIRE RATED WALLS AND FLOORS SHALL

BE TESTED AND CERTIFIED AS A SYSTEM PER ASTM E814 STANDARDS FOR FIRE TESTS OF

THROUGH-PENETRATION FIRESTOPS. REFER TO 26 05 03 FOR ADDITIONAL INFORMATION AND

REQUIREMENTS SPECIFIC TO FIRESTOPPING.

5. CONTRACTOR SHALL COORDINATE THE LOCATION OF ALL CEILING MOUNTED DEVICES AND

EQUIPMENT WITH LUMINAIRES, SPRINKLER, AND CEILING DIFFUSERS. OCCUPANCY/VACANCY

SENSORS SHALL BE LOCATED NO CLOSER THAN 3 FEET TO AN AIR SUPPLY DIFFUSER OR

RETURN GRILLE.

6. ELECTRICAL AND TECHNOLOGY EQUIPMENT SHALL BE MOUNTED TO AVOID IMPEDANCE OF,

OPERATION OF, AND/OR ACCESS TO ELECTRICAL AND MECHANICAL EQUIPMENT. ALL

MOUNTING OF ELECTRICAL AND TELECOMMUNICATIONS EQUIPMENT, ON EQUIPMENT

SUPPLIED BY ANOTHER CONTRACTOR, SHALL BE APPROVED IN ADVANCE BY THE OTHER

CONTRACTOR.

7. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL OPENINGS REQUIRED IN WALLS. ALL

OPENINGS SHALL BE REPAIRED TO MATCH EXISTING BY A QUALIFIED CONTRACTOR AT THE

EXPENSE OF THIS CONTRACTOR. ALL CONDUITS THROUGH WALLS SHALL BE GROUTED OR

SEALED INTO OPENINGS. CONTRACTOR WILL BE RESPONSIBLE FOR MEETING BIOSAFETY

REQUIREMENTS AS LAID OUT BY COR FOR ANY PATCHES.

8. EACH CONTRACTOR IS RESPONSIBLE FOR DAMAGE CAUSED BY THEIR ACTIONS TO THE

WALLS, FLOORS, CEILINGS, AND ROOFS. THE CONTRACTOR WHOSE WORK CAUSES DAMAGE

IS RESPONSIBLE FOR PATCHING TO MATCH ORIGINAL CONSTRUCTION, FIRE RATING, AND

FINISH. CONTRACTOR WILL BE RESPONSIBLE FOR MEETING BIOSAFETY REQUIREMENTS AS

LAID OUT BY COR FOR ANY PATCHES.

ELECTRICAL INSTALLATION NOTES:

1. EXISTING CONDITIONS ARE SHOWN BASED ON INFORMATION OBTAINED FROM FIELD

SURVEYS, EXISTING BUILDING DOCUMENTS. CONTRACTOR SHALL REVIEW EXISTING

CONDITIONS AND REPORT CONFLICTS.

2. NOT ALL EXISTING EQUIPMENT, LUMINAIRES, AND CONDUIT ARE SHOWN. CONTRACTOR

SHALL REVIEW EXISTING CONDITIONS AND REPORT CONFLICTS.

3. ELECTRICAL CONTRACTOR SHALL REVIEW EXISTING CONDITIONS TO VERIFY ACCESSIBILITY

TO THE AREAS OF THEIR WORK INCLUDING WALLS, FLOOR, CEILINGS, CEILING TILES/GRID,

AND ROOF. ELECTRICAL CONTRACTOR IS RESPONSIBLE TO PROVIDE CUTTING, REMOVAL,

PATCHING, AND REINSTALLATION OF AFFECTED AREAS ASSOCIATED WITH THEIR WORK BY

COORDINATING WITH THE GENERAL CONTRACTOR OR QUALIFIED CONTRACTOR.

4. WHERE EXISTING ELECTRICAL SYSTEMS ARE LOCATED IN AREAS THAT CONFLICT WITH NEW

EQUIPMENT, PIPING, OR DUCTWORK TO BE INSTALLED, EACH CONTRACTOR SHALL EITHER

ARRANGE NEW EQUIPMENT, CONDUIT, OR DUCTWORK IN SUCH A FASHION THAT IT DOES

NOT CONFLICT WITH EXISTING SYSTEMS, OR REWORK EXISTING ELECTRICAL SYSTEMS TO

ALLOW FOR INSTALLATION OF NEW EQUIPMENT, PIPING, OR DUCTWORK.

ELECTRICAL RENOVATION NOTES:

THESE NOTES APPLY TO ALL ELECTRICAL SHEETS AND TRADES, INCLUDING BUT NOT LIMITED

TO, LIGHTING, POWER, FIRE ALARM, AND OTHER LOW VOLTAGE SYSTEMS.

ELECTRICAL PHASING NOTES:

THESE NOTES APPLY TO ALL ELECTRICAL SHEETS AND TRADES, INCLUDING BUT NOT LIMITED

TO, LIGHTING, POWER, FIRE ALARM, AND OTHER LOW VOLTAGE SYSTEMS.

1. COORDINATE WITH OWNER AND BAILEY EDWARDS PRIOR TO ANY WORK ON PROJECT TO

DEVELOP A PHASING SCHEDULE DUE TO THE SENSITIVE NATURE OF THE RESEARCH IN THIS

FACILITY.

2. ELECTRICAL DRAWINGS DEPICT THE INTENT OF THE FINAL DESIGN. THE ELECTRICAL

DRAWINGS DO NOT DEPICT THE MEANS AND METHODS TO MEET THE REQUIREMENTS OF

THE PHASING CRITERIA.

3. REVIEW PROJECT PHASING PLANS TO COORDINATE DEMOLITION WORK, OUTAGES, ETC.

WITH AFFECTED ADJACENT AREAS.

4. PROVIDE TEMPORARY LIGHTING, POWER, FIRE ALARM, AND OTHER LOW VOLTAGE

SYSTEMS, ETC. AS NEEDED TO MAINTAIN SERVICE TO ALL AREAS DURING ALL PHASES OF

PROJECT.

PLAN OR DETAIL NUMBER

PLAN OR DETAIL NAME

PLAN OR DETAIL SCALE

DETAIL REFERRED TO BY SECTION CUT

SHEET DETAIL IS LOCATED ON

NAME

VIEW NAME

1/8" = 1'-0"

M101

SIMSIM

INDICATES SIMILAR DETAIL REFERENCED

IN MULTIPLE LOCATIONS

LEVEL NAME

10'-0" HEIGHT ABOVE

PROJECT 0'-0"

1 KEYNOTE: INDICATES NOTE USED TO

DESCRIBE ADDITIONAL INFORMATION

ABOUT WORK REQUIRED, SPECIFIC

TO THE SHEET AND/OR DETAIL

N O R

HT

INDICATES DIRECTION OF TRUE NORTH

VIEW KEY

LINE TYPE AND TAG KEY:

NEW WORK BY THIS CONTRACTOR (WIDE LINE)

NEW

EXISTING TO BE REMOVED (SHORT DASHED PATTERN)

NEW UNDERFLOOR OR UNDERGROUND (LONG DASHED PATTERN)

EXISTING TO REMAIN OR WORK BY OTHERS (NARROW LINE)

EXISTING

EXISTING TO BE REMOVED BY OTHERS (SHORT DASHED PATTERN)

EXISTING UNDERFLOOR OR UNDERGROUND (LONG DASHED PATTERN)

HALFTONING DOES NOT MODIFY SCOPE.

'TAG'-E TAGS WITH DASH 'E' INDICATES THE REFERENCED OBJECT IS EXISTING

TAG-1 UNDERLINED TAG INDICATES OBJECT IS IN-SCOPE. IF NEW, ADDITIONAL

INFORMATION IS AVAILABLE IN A SCHEDULE, MATERIAL LIST, OR SYMBOL LIST

INDICATES AN EXISTING SYSTEM'S POINT OF CONNECTION/REMOVAL

T101

TEMPERATURE CONTROLS CONTRACTORT.C.C.

SECURITY CONTRACTORS.C.

AUDIO/VISUAL CONTRACTORA.V.C.

NURSE CALL CONTRACTORN.C.C.

CIVIL CONTRACTORC.C.

ASBESTOS ABATEMENT CONTRACTOR

FIRE PROTECTION CONTRACTORF.P.C.

HEATING CONTRACTORH.C.

PLUMBING CONTRACTORP.C.

GENERAL CONTRACTORG.C.

MECHANICAL CONTRACTORM.C.

VENTILATION CONTRACTORV.C.

ELECTRICAL CONTRACTORE.C.

A.C.

CONTRACTOR ABBREVIATION KEY

ABBR: DESCRIPTION:

TECHNOLOGY CONTRACTORT.C.

CONSTRUCTION MANAGERC.M.

FOOD SERVICE CONTRACTORF.S.C.

CONTACT PERSONS:

PROJECT MANAGER

LIGHTING AND CONTROLS:

RYNE OBENAUF, BAILEY EDWARDS

CHRIS WOJTAL, IMEG

DESCRIPTION: PERSON:

BUILDING CODE: IBC 2021 EDITION

ELECTRICAL CODE: NEC 2023 EDITION

ENERGY CONSERVATION CODE: IECC 2021

HEALTH DEPARTMENT CODE: CURRENT EDITION

LOCAL BUILDING CODE: CURRENT EDITION

APPLICABLE CODES

CONTRACTOR SHALL COMPLY WITH APPLICABLE CODES AND LOCAL AMENDMENTS

INCLUDING, BUT NOT LIMITED TO, THE FOLLOWING:

SW-1P

26 09 34

SW-1P-EM

SW-2P

SW-3W

SW-1P-WP

SW-O

SW-O2

OC 26 09 34

SW-1P-K

SW-2P-K

SW-3W-K

SW-4W-K

ELECTRICAL SYMBOL LIST

SYMBOL: SPEC

TAG:

SPEC

SECTION:

DESCRIPTION:

SW-#B LIGHTING CONTROL STATION - DEFAULT

DIMMED CONTROL - # DEFINES MINIMUM

QUANTITY OF CONTROL SCENES, PLUS OFF,

REFER TO LIGHTING SEQUENCE OF

OPERATIONS WHEN NOT DEFINED.

SUBSCRIPTS:

BLANK = DIMMING CONTROL

S = SWITCHED CONTROL

W = WIRELESS WITH BATTERY

# = UNIQUE ID WHEN APPLICABLE

26 09 34#B

LCD SW-LCD LCD LIGHTING CONTROL - CUSTOM

PROGRAMMING

SUBSCRIPTS:

BLANK = DIMMING CONTROL

S = SWITCHED CONTROL

# = UNIQUE ID WHEN APPLICABLE

26 09 34

SW-D

SW-D3

SW-DML

SW-DO

SWITCH

SUBSCRIPTS:

BLANK = SINGLE POLE

2 = TWO POLE

3 = THREE WAY

4 = FOUR WAY

D = DIMMER - STAND ALONE

D3=DIMMER - THREE WAY WITH S3 TYPE

DML=DIMMER - MULTI-LOCATION FADE

CONTROL [NTS: RESIDENTIAL USE -

DIFFERS FROM #B PUSH BUTTON DIMMER]

DO=DIMMER - OCCUPANCY/VACANCY

SENSORS - DUAL TECHNOLOGY

ULTRASONIC/ACOUSTIC AND PIR

W = WEATHERPROOF

O = DUAL TECHNOLOGY OCCUPANCY SENSOR

WITH WALL SWITCH

O2=OCCUPANCY SENSOR AND DUAL SWITCH

K = SINGLE POLE - KEY LOCK

K2=TWO POLE - KEY LOCK

K3=THREE WAY - KEY LOCK

K4=FOUR WAY - KEY LOCK

E = SINGLE POLE - EMERGENCY

3E=THREE WAY - EMERGENCY

4E=FOUR WAY - EMERGENCY

P = SINGLE POLE - RED PILOT LIGHT

L = SINGLE POLE - LIGHTED HANDLE

M = THREE POSITION MOMENTARY

60= LOCAL TIMER - SPRING WOUND

T = LOCAL TIMER - USER ADJUSTABLE

X = SINGLE POLE - EXPLOSION PROOF

SW-4W

SW-3W-EM

SW-4W-EM

SW-1P-PL

SW-1P-LH

SW-1P-M

SW-1P-060

SW-1P-ADJ

SW-1P-EX

OCCUPANCY SENSOR - CEILING MOUNTED

SUBSCRIPTS:

BLANK = DUAL TECHNOLOGY

A = ULTRASONIC - TWO SIDED CORRIDOR

COVERAGE

P = PASSIVE INFRARED - 360° COVERAGE

P2=PASSIVE INFRARED - 100° COVERAGE

U = ULTRASONIC - 360° COVERAGE

HA=HIGHBAY - ISLE COVERAGE

HB=HIGH BAY

W = WIRELESS WITH BATTERY

SW-OC-D

SW-OC-A

SW-OC-P

SW-OC-P2

SW-OC-U

SW-OC-HA

SW-OC-HB

SW-OC-W

PC

SW-LS-PC 26 09 33 PHOTO CELL

LINEAR LUMINAIRES

TROFFER

WALL SCONCE LUMINAIRE

DOWNLIGHT LUMINAIRE

AIMABLE OR WALL WASH LUMINAIRE

INDUSTRIAL LUMINAIRE

SINGLE FACE EXIT SIGN

DOUBLE FACE EXIT SIGN

EMERGENCY UNIT

WALL BRACKET LUMINAIRE

ELECTRICAL SYMBOL LIST

SYMBOL: TAG: SPEC

SECTION:

DESCRIPTION:

WALL/CEILING EMERGENCY EXIT SIGN

REFER TO LUMINAIRE

SCHEDULE

LUMINAIRE

F1 = FIXTURE TAG

1 = CIRCUIT NUMBER

a = SWITCH DESIGNATION z1=ZONE DESIGNATION

"NL" INDICATES LUMINAIRE IS UNSWITCHED FOR NIGHT LIGHT.

"SE" INDICATES LUMINAIRE IS SWITCHED/CONTROLLED DURING NORMAL

OPERATION AND OPERATES FROM EMERGENCY CIRCUIT UPON LOSS OF POWER.

*IF LABEL IS ORIENTED HORIZONTALLY A SLASH WILL SEPARATE THIS

INFORMATION. EX: F1 / 1 / a / NL

LUMINAIRE CIRCUIT AND CONTROL KEY

THE DESIGN DOCUMENTS DESCRIBE THE OPERATIONAL PERFORMANCE REQUIREMENTS OF THE

LIGHTING CONTROL SYSTEM. THE PROJECT MAY REQUIRE ONE OR MORE LIGHTING CONTROL

STRATEGIES FOR THE PROJECT. REFER TO THE ELECTRICAL SYMBOL KEY, SPECIFICATION

SECTION 26 09 34 LIGHTING CONTROL SYSTEMS, AND THE DRAWINGS TO DETERMINE THE

DESIGN APPLICATION FOR EACH SPACE. THE POTENTIAL STRATEGICS ARE AS FOLLOWS:

1. STANDALONE LIGHTING CONTROL DEVICES: INDEPENDENT (STANDALONE) DEVICES

TRADITIONALLY OPERATING AT LINE OR LOW VOLTAGE, FIELD CONFIGURABLE WITH

OTHER STANDALONE DEVICES TO PROVIDE AN OVERALL LIGHTING CONTROL SYSTEM.

2. ROOM BASED LIGHTING CONTROLS: INTEGRATED SYSTEM COMPRISED OF SWITCH

STATIONS, SENSORS, ROOM CONTROLLERS, CONTROL PANELS, AND ACCESSORIES,

OPERATING AT LINE AND/OR LOW VOLTAGE, CONFIGURED AS AN INTEGRATED OVERALL

‘INTELLIGENT’ LIGHTING CONTROL SYSTEM. LIGHTING CONTROL ZONES AND POWER

CIRCUITS COMMONLY ALIGN.

3. NETWORK BASED LIGHTING CONTROLS: INTEGRATED SYSTEM COMPRISED OF SWITCH

STATIONS, SENSORS, ROOM CONTROLS, CONTROL PANELS, DIMMER RACKS, AND

ACCESSORIES, OPERATING AT LINE AND/OR LOW VOLTAGE, CONFIGURED AS AN

INTEGRATED OVERALL 'INTELLIGENT' LIGHTING CONTROL SYSTEM FOR ADVANCED

ARCHITECTURALLY BASED LIGHTING CONTROL SYSTEMS. LIGHTING CONTROL ZONES

COMMONLY ASSOCIATED WITH ONE OR MORE BRANCH POWER CIRCUITS WITHIN THE

SAME CONTROL ZONE.

LIGHTING CONTROL SYSTEM DESIGNATION: THE FOLLOWING KEY MAY BE USED AS AN EXAMPLE

TO DETERMINE THE DESIGNATED LIGHTING CONTROL SYSTEM FOR EACH SPACE. REFER TO

ELECTRICAL COVERSHEET FOR ELECTRICAL SYMBOLS LIST AND DEVICE SPECIFICATION

TAG. REFER TO THE SPECIFICATIONS FOR ADDITIONAL INFORMATION.

1. STANDALONE LIGHTING CONTROL DEVICES: CONTROL STATION COMMONLY

DEFINED BY AN ALPHA CHARACTER WITH SUBSCRIPTS.

A. EXAMPLE SYMBOL “S”, SPECIFICATION TAG "SW-1P", DESCRIPTION "SWITCH-

SINGLE POLE SWITCH".

B. EXAMPLE CONTROL DESIGNATION: a, b, c (WHEN REQUIRED TO CLARIFY DESIGN

INTENT).

C. SINGLE POLE LIGHT SWITCH "SA" CONTROLS LUMINAIRES WITH THE SUBSCRIPT

“a” WITHIN THE SAME SPACE.

D. REFER TO THE LIGHT CONTROL SEQUENCE OF OPERATION TAG {L#-##} FOR A

COMPLETE DESCRIPTION OF THE LIGHTING CONTROL REQUIREMENTS.

2. ROOM BASED LIGHTING CONTROLS: CONTROL STATION COMMONLY DEFINED BY A

RECTANGLE SYMBOL.

A. EXAMPLE CONTROL STATION: SYMBOL “#B”, TAGGED "SW-#B", DESCRIPTION

"LIGHTING CONTROL STATION".

B. EXAMPLE PANEL/RACK/CABINET: TAGGED "LCPR#", DESCRIPTION "ROOM BASED

LIGHTING CONTROL PANEL/RACK/CABINET.

C. EXAMPLE CONTROL DESIGNATIONS: a, b, c D. LIGHTING CONTROL STATION “#B” a,b CONTROLS LUMINAIRES WITH THE

SUBSCRIPT “a” AND “b” WITHIN THE SAME SPACE

E. REFER TO THE LIGHT CONTROL SEQUENCE OF OPERATION TAG {L#-##} FOR A

COMPLETE DESCRIPTION OF THE LIGHTING CONTROL AND PRE-PROGRAMMED

SCENE SELECTION REQUIREMENTS.

3. NETWORK BASED LIGHTING CONTROLS: CONTROL STATION COMMONLY DEFINED BY A

RECTANGLE SYMBOL.

A. EXAMPLE SYMBOL “#B”, TAGGED "SW-#B", DESCRIPTION "LIGHTING CONTROL

STATION".

B. EXAMPLE PANEL/RACK/CABINET: TAGGED "LCPN", DESCRIPTION "NETWORK

BASED LIGHTING CONTROL PANEL/RACK/CABINET.

C. EXAMPLE CONTROL DESIGNATIONS: z1, z2, z3 D. LIGHTING CONTROL STATION “#B” z1 CONTROLS LUMINAIRES WITH THE

SUBSCRIPT “z1”. LUMINAIRES WITH A z1 DESIGNATION MAY OR MAY NOT BE

SERVED BY THE SAME BRANCH LIGHTING CIRCUIT.

E. REFER TO THE LIGHT CONTROL SEQUENCE OF OPERATION TAG {L#-##} FOR A

COMPLETE DESCRIPTION OF THE LIGHTING CONTROL AND PRE-PROGRAMMED

SCENE SELECTION REQUIREMENTS.

BOTH LUMINAIRES ARE CONTROLLED BY THE SAME CONTROL STATION, SAME

LIGHTING CONTROL ZONE Z1, BUT POWERED BY DIFFERENT BRANCH LIGHTING

CIRCUITS.

LIGHTING SYSTEM DESCRIPTION KEY:

LIGHTING CONTROL NOTES:

{L#-##} INDICATES THE LIGHTING SEQUENCE OF OPERATION FOR THE SPACE. REFER TO THE

LIGHTING SEQUENCE OF OPERATION MATRIX ON SHEET E600.

{#B} LIGHTING CONTROL STATION. THE “#” INDICATES THE MINIMUM QUANTITY OF INDIVIDUAL

BUTTONS WHEN DEFINED. LIGHTING CONTROL STATION SHALL BE CAPABLE OF ON/OFF

CONTROL FOR CLEANING AS INDICATED ON DRAWINGS AND DESCRIBED IN THE LIGHTING

SEQUENCE OF OPERATION MATRIX. REFER TO DRAWINGS AND LUMINAIRE SUBSCRIPTS TO

DETERMINE IF A ROOM BASED CONTROLLER (a,b,c SUBSCRIPTS) OR NETWORK CONTROL SYSTEM (z1, z2, z3) IS REQUIRED.

{ z##} INDICATES THE LIGHTING ZONES FOR THE SPACE. PROVIDE SEPARATE CONTROL OF EACH

CONTROLLED ZONE. LUMINAIRES ASSOCIATED WITH THE SAME ZONE SHALL OPERATE

TOGETHER WITHIN THE SAME PROGRAMMED SCENE.

LIGHTING CONTROL SUBSCRIPTS:

1. LOWER CASE ALPHA SUBSCRIPTS “a, b, c” INDICATE LINE VOLTAGE OR ROOM BASED

LIGHTING CONTROL SYSTEMS. REFER TO DRAWINGS TO DETERMINE IF LINE VOLTAGE

CONTROL (S, S3, S4, ETC) OR {#B} ROOM BASED CONTROLLER SYSTEM (#B) IS

REQUIRED.

2. LOWER CASE ALPHA NUMERIC SUBSCRIPTS “z1, z2, z3” INDICATE NETWORK BASED

LIGHTING CONTROL SYSTEM.

EMERGENCY LIGHTING OVERRIDE CONTROL (UL924 AND UL1008): LIGHTING CONTROL

EQUIPMENT COUPLED WITH REMOTE EMERGENCY POWER SOURCES (EXTERNAL TO THE

LUMINAIRE) REQUIRE ALCR (UL924) OR BCELTS (UL1008) DEVICES FOR EMERGENCY (LIFE

SAFETY) COMPLIANCE. AN EMERGENCY LIGHTING CONTROL BYPASS IS REQUIRED FOR EVERY

INDIVIDUAL LIGHTING CONTROL ZONE-CIRCUIT BUT NOT SHOWN ON THE PLANS. REFER TO THIS

SPECIFICATION FOR ALCR AND BCELTS DESCRIPTIONS. REFER TO THE SEQUENCE OF

OPERATION LIGHTING CONTROL DESCRIPTIONS ON THE PLANS FOR ADDITIONAL

REQUIREMENTS.

REFER TO SHEET E600 FOR LUMINAIRE SCHEDULE

REFER TO SHEET E401 FOR LIGHTING CONTROL ONE-LINE DIAGRAM

LUMINAIRE

aF# a

CONTROL

LUMINAIRE

a,bF# a

CONTROLLUMINAIRE

F# b #B

LUMINAIRE

z1F# z1

CONTROLLUMINAIRE

F# z1

#B

LIGHTING CONTROL NOTES:

ELECTRICAL SHEET INDEX

E000 ELECTRICAL COVERSHEET

E101 LEVEL 01 DEMOLITION PLAN - OVERALL - LIGHTING

E101A LEVEL 01 DEMOLITION PLAN - AREA A - LIGHTING

E101B LEVEL 01 DEMOLITION PLAN - AREA B - LIGHTING

E101C LEVEL 01 DEMOLITION PLAN - AREA C - LIGHTING

E102 LEVEL 02 DEMOLITION PLAN - OVERALL - LIGHTING

E102A LEVEL 02 DEMOLITION PLAN - AREA A - LIGHTING

E102B LEVEL 02 DEMOLITION PLAN - AREA B - LIGHTING

E102C LEVEL 02 DEMOLITION PLAN - AREA C&D - LIGHTING

E103 LEVEL 03 DEMOLITION PLAN - OVERALL - LIGHTING

E103A LEVEL 03 DEMOLITION PLAN - AREA A - LIGHTING

E103B LEVEL 03 DEMOLITION PLAN - AREA B - LIGHTING

E103C LEVEL 03 DEMOLITION PLAN - AREA C - LIGHTING

E201 LEVEL 01 PLAN - OVERALL - LIGHTING

E201A LEVEL 01 PLAN - AREA A - LIGHTING

E201B LEVEL 01 PLAN - AREA B - LIGHTING

E201C LEVEL 01 PLAN - AREA C - LIGHTING

E202 LEVEL 02 PLAN - OVERALL - LIGHTING

E202A LEVEL 02 PLAN - AREA A - LIGHTING

E202B LEVEL 02 PLAN - AREA B - LIGHTING

E202C LEVEL 02 PLAN - AREA C&D - LIGHTING

E203 LEVEL 03 PLAN - OVERALL - LIGHTING

E203A LEVEL 03 PLAN - AREA A - LIGHTING

E203B LEVEL 03 PLAN - AREA B - LIGHTING

E203C LEVEL 03 PLAN - AREA C - LIGHTING

E400 ELECTRICAL DETAILS

E401 LIGHTING CONTROL SYSTEM DETAILS

E402 LIGHTING CONTROL SYSTEM CONTACT SCHEDULES

E600 ELECTRICAL SCHEDULES

GRAND TOTAL: 29

A

B

C

D

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

D A

U S

Agricultural Research Service

BEN A'HEARN

ORDER DATE:

TASK ORDER NO.:

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

DWG. NO.

SHEET

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr

Suite 2800

Chicago, IL

60601-2308

©2024 Bailey Edward Design

Design Firm License No. 184-001962

TBD

KARLA TEBBEN

TBD

12505B23F0175

OF

E000

ELECTRICAL COVERSHEET

CW

KS

23005300.02 5

1 08/12/2025 BED 100% CONSTRUCTION DOCUMENTS

OC

OC

D

OC

D

OC

D

OC

D

A R

E A

C

A R

E A

B

AREA A

AREA B

A R

E A

B

A R

E A

D

A

B

C

D

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

D A

U S

Agricultural Research Service

BEN A'HEARN

ORDER DATE:

TASK ORDER NO.:

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

DWG. NO.

SHEET

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr

Suite 2800

Chicago, IL

60601-2308

©2024 Bailey Edward Design

Design Firm License No. 184-001962

TBD

KARLA TEBBEN

TBD

12505B23F0175

OF

E101

LEVEL 01 DEMOLITION PLAN - OVERALL -

LIGHTING

CW

KS

23005300.02 6

N O R

HT

1/16" = 1'-0"1

LEVEL 01 DEMOLITION PLAN - OVERALL - LIGHTING

OC

D

A

B

C

D

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

D A

U S

Agricultural Research Service

BEN A'HEARN

ORDER DATE:

TASK ORDER NO.:

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

DWG. NO.

SHEET

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr

Suite 2800

Chicago, IL

60601-2308

©2024 Bailey Edward Design

Design Firm License No. 184-001962

TBD

KARLA TEBBEN

TBD

12505B23F0175

OF

E101A

LEVEL 01 DEMOLITION PLAN - AREA A -

LIGHTING

CW

KS

23005300.02 7

N O R

HT

1/8" = 1'-0"1

LEVEL 01 DEMOLITION PLAN - AREA A - LIGHTING

DEMOLITION PLANS - GENERAL NOTES

1. REMOVE ALL EXISTING LUMINAIRES AND REPLACE WITH NEW

LUMINAIRES IN A "ONE FOR ONE" SCENARIO. ALL ELECTRICAL

WIRING SHALL REMAIN AND BE REUSED WITH NEW LUMINAIRES.

CAP AND MAINTAIN FOR SAFETY BETWEEN DEMOLITION AND NEW

WORK PHASES.

2. ENSURE THAT ALL THROUGH-SLAB PENETRATIONS REMAIN INTACT

TO ENSURE NO TRANSMISSION OF AIR BETWEEN RESEARCH AREAS

AND MECHANICAL SPACES. IF PENETRATIONS ARE MODIFIED

CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING THAT THE

PENETRATION HAS BEEN RESEALED.

3. REMOVE EXISTING LIGHTING CONTROL EQUIPMENT IN EACH SPACE.

THIS PERTAINS TO ALL SWITCHES, OCCUPANCY SENSORS AND

OTHER EQUIPMENT. THESE SHALL BE REPLACED IN-KIND.

4. FACILITY OWNER RETAINS FIRST RIGHT TO RETAIN ANY EXISTING,

FUNCTIONAL LUMINAIRES. IF THE OWNER REFUSES THESE

LUMINAIRES AND MATERIAL THEY SHALL BE DISPOSED OF IN

ACCORDANCE WITH GUIDELINES IN SPECIFICATION SECTION 26 05

00.

5. COORDINATE WITH ON-SITE OWNERS TEAM FOR PHASING OF

DEMOLITION AND NEW WORK.

OC

D

OC

D

A

B

C

D

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

D A

U S

Agricultural Research Service

BEN A'HEARN

ORDER DATE:

TASK ORDER NO.:

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

DWG. NO.

SHEET

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr

Suite 2800

Chicago, IL

60601-2308

©2024 Bailey Edward Design

Design Firm License No. 184-001962

TBD

KARLA TEBBEN

TBD

12505B23F0175

OF

E101B

LEVEL 01 DEMOLITION PLAN - AREA B -

LIGHTING

CW

KS

23005300.02 8

N O R

HT

1/8" = 1'-0"1

LEVEL 01 DEMOLITION PLAN - AREA B - LIGHTING

DEMOLITION PLANS - GENERAL NOTES

1. REMOVE ALL EXISTING LUMINAIRES AND REPLACE WITH NEW

LUMINAIRES IN A "ONE FOR ONE" SCENARIO. ALL ELECTRICAL

WIRING SHALL REMAIN AND BE REUSED WITH NEW LUMINAIRES.

CAP AND MAINTAIN FOR SAFETY BETWEEN DEMOLITION AND NEW

WORK PHASES.

2. ENSURE THAT ALL THROUGH-SLAB PENETRATIONS REMAIN INTACT

TO ENSURE NO TRANSMISSION OF AIR BETWEEN RESEARCH AREAS

AND MECHANICAL SPACES. IF PENETRATIONS ARE MODIFIED

CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING THAT THE

PENETRATION HAS BEEN RESEALED.

3. REMOVE EXISTING LIGHTING CONTROL EQUIPMENT IN EACH SPACE.

THIS PERTAINS TO ALL SWITCHES, OCCUPANCY SENSORS AND

OTHER EQUIPMENT. THESE SHALL BE REPLACED IN-KIND.

4. FACILITY OWNER RETAINS FIRST RIGHT TO RETAIN ANY EXISTING,

FUNCTIONAL LUMINAIRES. IF THE OWNER REFUSES THESE

LUMINAIRES AND MATERIAL THEY SHALL BE DISPOSED OF IN

ACCORDANCE WITH GUIDELINES IN SPECIFICATION SECTION 26 05

00.

5. COORDINATE WITH ON-SITE OWNERS TEAM FOR PHASING OF

DEMOLITION AND NEW WORK.

A R

E A

C

A R

E A

B

AREA A

A

B

C

D

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

D A

U S

Agricultural Research Service

BEN A'HEARN

ORDER DATE:

TASK ORDER NO.:

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

DWG. NO.

SHEET

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr

Suite 2800

Chicago, IL

60601-2308

©2024 Bailey Edward Design

Design Firm License No. 184-001962

TBD

KARLA TEBBEN

TBD

12505B23F0175

OF

E101C

LEVEL 01 DEMOLITION PLAN - AREA C -

LIGHTING

CW

KS

23005300.02 9

N O R

HT

1/8" = 1'-0"1

LEVEL 01 DEMOLITION PLAN - AREA C - LIGHTING

DEMOLITION PLANS - GENERAL NOTES

1. REMOVE ALL EXISTING LUMINAIRES AND REPLACE WITH NEW

LUMINAIRES IN A "ONE FOR ONE" SCENARIO. ALL ELECTRICAL

WIRING SHALL REMAIN AND BE REUSED WITH NEW LUMINAIRES.

CAP AND MAINTAIN FOR SAFETY BETWEEN DEMOLITION AND NEW

WORK PHASES.

2. ENSURE THAT ALL THROUGH-SLAB PENETRATIONS REMAIN INTACT

TO ENSURE NO TRANSMISSION OF AIR BETWEEN RESEARCH AREAS

AND MECHANICAL SPACES. IF PENETRATIONS ARE MODIFIED

CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING THAT THE

PENETRATION HAS BEEN RESEALED.

3. REMOVE EXISTING LIGHTING CONTROL EQUIPMENT IN EACH SPACE.

THIS PERTAINS TO ALL SWITCHES, OCCUPANCY SENSORS AND

OTHER EQUIPMENT. THESE SHALL BE REPLACED IN-KIND.

4. FACILITY OWNER RETAINS FIRST RIGHT TO RETAIN ANY EXISTING,

FUNCTIONAL LUMINAIRES. IF THE OWNER REFUSES THESE

LUMINAIRES AND MATERIAL THEY SHALL BE DISPOSED OF IN

ACCORDANCE WITH GUIDELINES IN SPECIFICATION SECTION 26 05

00.

5. COORDINATE WITH ON-SITE OWNERS TEAM FOR PHASING OF

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

P C

A R

E A

C

A R

E A

B

AREA A

AREA B

A R

E A

B

A R

E A

D

A

B

C

D

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

D A

U S

Agricultural Research Service

BEN A'HEARN

ORDER DATE:

TASK ORDER NO.:

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

DWG. NO.

SHEET

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr

Suite 2800

Chicago, IL

60601-2308

©2024 Bailey Edward Design

Design Firm License No. 184-001962

TBD

KARLA TEBBEN

TBD

12505B23F0175

OF

E102

LEVEL 02 DEMOLITION PLAN - OVERALL -

LIGHTING

CW

KS

23005300.02 10

N O R

HT

1/16" = 1'-0"1

LEVEL 02 DEMOLITION PLAN - OVERALL - LIGHTING

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

P C

A

B

C

D

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

D A

U S

Agricultural Research Service

BEN A'HEARN

ORDER DATE:

TASK ORDER NO.:

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

DWG. NO.

SHEET

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr

Suite 2800

Chicago, IL

60601-2308

©2024 Bailey Edward Design

Design Firm License No. 184-001962

TBD

KARLA TEBBEN

TBD

12505B23F0175

OF

E102A

LEVEL 02 DEMOLITION PLAN - AREA A -

LIGHTING

CW

KS

23005300.02 11

N O R

HT

1/8" = 1'-0"1

LEVEL 02 DEMOLITION PLAN - AREA A - LIGHTING

DEMOLITION PLANS - GENERAL NOTES

1. REMOVE ALL EXISTING LUMINAIRES AND REPLACE WITH NEW

LUMINAIRES IN A "ONE FOR ONE" SCENARIO. ALL ELECTRICAL

WIRING SHALL REMAIN AND BE REUSED WITH NEW LUMINAIRES.

CAP AND MAINTAIN FOR SAFETY BETWEEN DEMOLITION AND NEW

WORK PHASES.

2. ENSURE THAT ALL THROUGH-SLAB PENETRATIONS REMAIN INTACT

TO ENSURE NO TRANSMISSION OF AIR BETWEEN RESEARCH AREAS

AND MECHANICAL SPACES. IF PENETRATIONS ARE MODIFIED

CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING THAT THE

PENETRATION HAS BEEN RESEALED.

3. REMOVE EXISTING LIGHTING CONTROL EQUIPMENT IN EACH SPACE.

THIS PERTAINS TO ALL SWITCHES, OCCUPANCY SENSORS AND

OTHER EQUIPMENT. THESE SHALL BE REPLACED IN-KIND.

4. FACILITY OWNER RETAINS FIRST RIGHT TO RETAIN ANY EXISTING,

FUNCTIONAL LUMINAIRES. IF THE OWNER REFUSES THESE

LUMINAIRES AND MATERIAL THEY SHALL BE DISPOSED OF IN

ACCORDANCE WITH GUIDELINES IN SPECIFICATION SECTION 26 05

00.

5. COORDINATE WITH ON-SITE OWNERS TEAM FOR PHASING OF

DEMOLITION AND NEW WORK.

AREA B

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

OC

D

A

B

C

D

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

D A

U S

Agricultural Research Service

BEN A'HEARN

ORDER DATE:

TASK ORDER NO.:

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

DWG. NO.

SHEET

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr

Suite 2800

Chicago, IL

60601-2308

©2024 Bailey Edward Design

Design Firm License No. 184-001962

TBD

KARLA TEBBEN

TBD

12505B23F0175

OF

E102B

LEVEL 02 DEMOLITION PLAN - AREA B -

LIGHTING

CW

KS

23005300.02 12

N O R

HT

1/8" = 1'-0"1

LEVEL 02 DEMOLITION PLAN - AREA B - LIGHTING

DEMOLITION PLANS - GENERAL NOTES

1. REMOVE ALL EXISTING LUMINAIRES AND REPLACE WITH NEW

LUMINAIRES IN A "ONE FOR ONE" SCENARIO. ALL ELECTRICAL

WIRING SHALL REMAIN AND BE REUSED WITH NEW LUMINAIRES.

CAP AND MAINTAIN FOR SAFETY BETWEEN DEMOLITION AND NEW

WORK PHASES.

2. ENSURE THAT ALL THROUGH-SLAB PENETRATIONS REMAIN INTACT

TO ENSURE NO TRANSMISSION OF AIR BETWEEN RESEARCH AREAS

AND MECHANICAL SPACES. IF PENETRATIONS ARE MODIFIED

CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING THAT THE

PENETRATION HAS BEEN RESEALED.

3. REMOVE EXISTING LIGHTING CONTROL EQUIPMENT IN EACH SPACE.

THIS PERTAINS TO ALL SWITCHES, OCCUPANCY SENSORS AND

OTHER EQUIPMENT. THESE SHALL BE REPLACED IN-KIND.

4. FACILITY OWNER RETAINS FIRST RIGHT TO RETAIN ANY EXISTING,

FUNCTIONAL LUMINAIRES. IF THE OWNER REFUSES THESE

LUMINAIRES AND MATERIAL THEY SHALL BE DISPOSED OF IN

ACCORDANCE WITH GUIDELINES IN SPECIFICATION SECTION 26 05

00.

5. COORDINATE WITH ON-SITE OWNERS TEAM FOR PHASING OF

DEMOLITION AND NEW WORK.

A R

E A

C

A R

E A

B

C

D

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

D A

U S

Agricultural Research Service

BEN A'HEARN

ORDER DATE:

TASK ORDER NO.:

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

DWG. NO.

SHEET

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr

Suite 2800

Chicago, IL

60601-2308

©2024 Bailey Edward Design

Design Firm License No. 184-001962

TBD

KARLA TEBBEN

TBD

12505B23F0175

OF

E102C

LEVEL 02 DEMOLITION PLAN - AREA C&D -

LIGHTING

CW

KS

23005300.02 13

N O R

HT

1/8" = 1'-0"1

LEVEL 02 DEMOLITION PLAN - AREA C - LIGHTING

N O R

HT

1/8" = 1'-0"2

LEVEL 02 DEMOLITION PLAN - AREA D - LIGHTING

DEMOLITION PLANS - GENERAL NOTES

1. REMOVE ALL EXISTING LUMINAIRES AND REPLACE WITH NEW

LUMINAIRES IN A "ONE FOR ONE" SCENARIO. ALL ELECTRICAL

WIRING SHALL REMAIN AND BE REUSED WITH NEW LUMINAIRES.

CAP AND MAINTAIN FOR SAFETY BETWEEN DEMOLITION AND NEW

WORK PHASES.

2. ENSURE THAT ALL THROUGH-SLAB PENETRATIONS REMAIN INTACT

TO ENSURE NO TRANSMISSION OF AIR BETWEEN RESEARCH AREAS

AND MECHANICAL SPACES. IF PENETRATIONS ARE MODIFIED

CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING THAT THE

PENETRATION HAS BEEN RESEALED.

3. REMOVE EXISTING LIGHTING CONTROL EQUIPMENT IN EACH SPACE.

THIS PERTAINS TO ALL SWITCHES, OCCUPANCY SENSORS AND

OTHER EQUIPMENT. THESE SHALL BE REPLACED IN-KIND.

4. FACILITY OWNER RETAINS FIRST RIGHT TO RETAIN ANY EXISTING,

FUNCTIONAL LUMINAIRES. IF THE OWNER REFUSES THESE

LUMINAIRES AND MATERIAL THEY SHALL BE DISPOSED OF IN

ACCORDANCE WITH GUIDELINES IN SPECIFICATION SECTION 26 05

00.

5. COORDINATE WITH ON-SITE OWNERS TEAM FOR PHASING OF

DEMOLITION AND NEW WORK.

A R

E A

C

A R

E A

B

A R

E A

OC

D

A R

E A

C

A R

E A

B

AREA A

AREA B

A R

E A

B

A R

E A

D

A

B

C

D

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

D A

U S

Agricultural Research Service

BEN A'HEARN

ORDER DATE:

TASK ORDER NO.:

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

DWG. NO.

SHEET

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr

Suite 2800

Chicago, IL

60601-2308

©2024 Bailey Edward Design

Design Firm License No. 184-001962

TBD

KARLA TEBBEN

TBD

12505B23F0175

OF

E103

LEVEL 03 DEMOLITION PLAN - OVERALL -

LIGHTING

CW

KS

23005300.02 14

N O R

HT

1/16" = 1'-0"1

LEVEL 03 DEMOLITION PLAN - OVERALL - LIGHTING

A

B

C

D

BUILDING 7 LIGHTING AND CONTROLS UPGRADE

D A

U S

Agricultural Research Service

BEN A'HEARN

ORDER DATE:

TASK ORDER NO.:

DESCRIPTIONBYDATENO.

BAILEY EDWARD

DESIGN

EPM:

AOE:

BED PROJECT NO.:

CHECKED BY:

PROJECT MANAGER:

REAL PROPERTY:

SAFETY & HEALTH:

USDA

DWG. NO.

SHEET

AMES, IA 50010

1920 DAYTON AVENUE

NATIONAL CENTER FOR ANIMAL

HEALTH- BUILDING 7

t 312.440.2300 f 312.440.2303 www.baileyedward.com

35 East Wacker Dr

Suite 2800

Chicago, IL

60601-2308

©2024 Bailey Edward Design

Design Firm License No. 184-001962

TBD

KARLA TEBBEN

TBD

12505B23F0175

OF

E103A

LEVEL 03 DEMOLITION PLAN - AREA A -

LIGHTING

CW

KS

23005300.02 15

N O R

HT

1/8" = 1'-0"1

LEVEL 03 DEMOLITION PLAN - AREA A - LIGHTING

DEMOLITION PLANS - GENERAL NOTES