C04a SOI_1240LT27Q0026.xls
XLS spreadsheet 29 KB Posted
- Attached to
- HUMBOLT PACIFIC CREST TRAIL BRIDGE REPLACEMENT
- Solicitation number
- 1240LT27Q0026
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Schedule of Items for a federal construction solicitation related to bridge replacement on the Pacific Crest Trail. The solicitation (1240LT27Q0026) is issued by the Department of Agriculture Forest Service for the Humboldt-Toiyabe National Forest in Mono County, California, with the objective of replacing a trail bridge over the West Fork West Walker River in the Hoover Wilderness. The project consists of five base line items measured on a lump-sum basis: mobilization including helicopter transport, full removal of the existing bridge and components, structure excavation and backfill for approaches and foundation, approach railing (30 linear feet), and design, fabrication, transport, and installation of a 35-foot glulam deck panel bridge. No unit prices or total pricing are shown in the schedule provided.
Key dates for this procurement include a site visit scheduled for November 3, 2026, conducted via Zoom due to the remote location; questions and answers due by November 4, 2026; and quotes due by November 28, 2026, at 1700 Mountain Time. The anticipated award date is December 10, 2026, with a period of performance from July 1, 2027, through October 29, 2027 (120 days). The Contracting Officer Representative is Jordan Burge, Civil Engineer, Forest Service, who can be contacted at jordan.burge@usda.gov. Offerors are permitted to conduct site visits at their convenience in addition to the scheduled Zoom site visit.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Schedule of Items
| SCHEDULE OF ITEMS | ||||||
| Pacific Crest Trail (PCT) | ||||||
| Humboldt-Toiyabe National Forest | ||||||
| Mono County, California | ||||||
| FSM 2400 | ||||||
| Base Items | ||||||
| Item Number | Description | Method of Measurement | Unit | Quantity | Unit Price | Total |
| 90701 | Mobilization (includes helicopter) | LSQ | LS | 1 | ||
| 91101 | Full removal of existing bridge and all components | LSQ | LS | 1 | ||
| 91102 | Structure excavation and backfill (including approaches and bridge foundation) | LSQ | LS | 1 | ||
| 93701 | Approach railing | AQ | LF | 30 | ||
| 96101 | 35' glulam deck panel bridge: design, fabricate, transport, and install | LSQ | LS | 1 | ||
| Total | $0 |
File details come from the government source that posted it. Updated .