This is a Questions and Answers document from a pre-bid meeting held on November 5, 2026, for the Humboldt Pacific Crest Trail Bridge Replacement project (Solicitation 1240LT27Q0026). The document addresses inquiries from pre-bid attendees representing construction firms and subcontractors regarding the replacement of a trail bridge over the West Fork West Walker River in the Hoover Wilderness within the Humboldt-Toiyabe National Forest. Key project parameters include a 120-day installation timeline beginning July 1, 2027, helicopter-dependent logistics for a remote site with no motorized access, and mandatory compliance with Minimum Requirements Analysis Framework (MRAF) wilderness regulations and Leave No Trace principles. The bridge will be constructed using a glulam deck design; alternative steel truss designs are not acceptable. All materials must be slung in by helicopter from a designated staging area at coordinates 38.355768, -119.515171, located south of Highway 108 near Leavitt Lake, approximately 8 miles from the site. Helicopter landing near the bridge site is not feasible; landings up to one mile away are acceptable.

The document clarifies critical technical requirements and constraints: the new bridge is 2 feet longer with slightly wider dimensions but identical sill width; posts must be pressure-treated while horizontal railings remain untreated; shop drawings and calculations from the bridge fabricator require Forest Service approval; and chainsaws may be used to fell standing dead trees and hazard trees near the site with Contracting Officer Representative (COR) approval. Fire restrictions, weather contingencies, and wildlife considerations govern the July 1 start date, though pre-July work may be permitted if non-disruptive to wildlife. The contractor bears responsibility for site safety, traffic control directing hikers to an established detour with creek ford for stock, and removal of the existing bridge structure. Rock removal via jackhammer and expansive polymer are permissible; explosives are prohibited. Recommended bridge fabricators include Western Wood Structures and Permapost; Leavitt Meadows Pack Station is identified as a local packing resource. Forest Service contact is COR Jordan Burge (jordan.burge@usda.gov).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PCT trail bridge replacement project

Pre-bid attendees wishing to share contact information:

Treeline Construction

Brian Ketron, President - (209) 769-9130, briank@treelineconst.com Gary Linowski, Vice President - (707) 363-4992, garyl@treelineconst.com Jenna Chandler, CFO - (415) 815-8176, jenna@treelineconst.com Bruce Elliott

Accelerated Construction and Metal

Email: belliott@accelmetal.com

Phone: 209-846-7998

DJ Stidman DCS Innovations LLC

Mobile: 916-717-5886

Email: dj@dcsllcco.com

Ginny Talbot

Clear Water Mechanical LLC

Phone: 360-487-6151 Email: ginny@clearwatermechanical.org Wilamut Construction

Email: info@wilamutconstruction.com Phone: (615) 686-3880 Tyler Reynolds

Easy Street Gravel

Phone: 503-269-8323

Email: tyler@easystreetgravel.com Kevin Joell Sierra Trail Works sierratrailworks@gmail.com

Questions and discussion from Pre-Bid virtual meeting held on 11-5-2026:

· Here is the link with videos, photos, and old bridge drawings that were discussed during the meeting:

https://usfs-public.box.com/s/1nrudtpidlbvjnrs37ffzf0mefimog21

· Please provide the names of packers you’re aware of.

Leavitt Meadows Pack Station is the name of the business that is very familiar with this area.

An additional note: for bridge fabrication, we have worked with Western Wood Structures and Permapost often, although there may be other suitable fabricators.

· Are e-bikes allowed on the PCT?

No bicycles of any sort are allowed in the wilderness. The Minimum Requirements Analysis Framework (MRAF) for working in the wilderness only allows the prohibited activities in the vicinity of the bridge, not along the rest of the trail.

· Is the new bridge wider?

Yes, the new bridge is slightly wider, however the sills are the same width. FYI, the sills will be located in a different place because the new bridge is 2 feet longer.

· Do you have the as-built of the old bridge?

Yes. In the solicitation is an update with a link. Here you will find the old plans, along with videos of the site. Please note that the actual bridge may have slight differences from the plan set provided. Is anything ever built exactly how it was drawn?

· Is there a place at the site for the helicopter to land?

I have discussed this with our Aviation Manager, and he did not feel confident that he would be able to land. The safe assumption would be that all loads will have to be slung in.

· Are you allowed to transport personnel?

Per the MRAF and contract, that is allowed. However, if the helicopter cannot land then you cannot count on that being the method of transporting personnel. Regarding the MRAF and the solicitation evaluation criteria, minimizing impact to wilderness will be a consideration, and that will translate to minimizing number of flights in. We had to include the helicopter flight path and staging area. I will update the solicitation to include that.

· Do you know the weight of the existing bridge joists?

The old plans will give you a good enough idea to estimate those weights.

· Are there designated crew camp areas?

You can camp anywhere along the trail, utilizing the “Leave No Trace” principals.

· Is the winter recreation area an option for staging as it doesn’t seem a good idea to cross the highway with the helicopter?

The proposed staging area is at the corral south of highway 108. Coordinates: 38.355768°, -119.515171°. The flight path from here does not cross the highway. Other flight paths would be considered. One participant suggested the Leavitt Meadows Pack Station, as it would shorten the flight distance.

· Is there an engineer’s estimate?

We typically provide a price range. I will ask the Contracting Officer if we can provide that.

· Is there a flat area for the crew to camp?

There are quite a few suitable locations on the west approach.

· What is the material weight limit for the helicopter per load?

This is not restricted by the contract. This will be between the contractor and their helicopter service.

· What fire restrictions are there?

That will vary as local fire restrictions vary. The contractor will be responsible for following Forest Service restrictions at the time of construction.

· How long is the hike from Leavitt Lake to the site?

Approximately 8 miles. There is a high-clearance road in the area that can be utilized from the highway to Leavitt Lake.

· Is this section of the PCT going to be closed to hikers, and or is there an alternate crossing?

There will not be a legal closure, but the contractor may restrict access to the site for safety. We will work on a re-route for hikers.

· Are there any other erosion control measures required?

The contractor shall use best management practices (BMPs) to protect the creek, but we’re relatively far away from the stream, so no specific erosion controls are required.

· Are you opposed to expansive polymer use?

Expansive polymer may be utilized. No explosives.

· Is there going to be a lot of jack hammering of rock?

There definitely could be. However, this can be minimized based on the elevation the bridge is set. The higher the bridge is set, the more approach work buildup may be required, especially on the western approach. The lower the bridge is set, the more rock removal may be required on the eastern approach.

· Is the material already on the site to ramp up to the bridge?

Yes, there is plentiful granite near the site. Please reference the drawings, which shows large rock to be used for the approach retention.

· Regarding the approach rail: is the dry stack wall going to be close to the existing post mount on bed rock and building up the dry stack wall around it? Is the whole dry stack wall coming out and being rebuilt?

Yes. The rail posts are on the inside of that wall, so the approaches will need to be completely reconstructed. The design calls for a longer rail post that will be connected into bedrock. These posts will have to be reinforced with compacted approach fill, for the best longevity possible.

· July start date: Is that related to snow?

That is related to wildlife. There is some flexibility in that, and you could address that in your technical proposal. Perhaps there is some work that can be done that is not disruptive to wildlife that would be allowed to be performed before July.

· Can trees be cut for construction?

Update: a line item in the Schedule of Items has been added for this. Felling of hazard trees will be required.

Questions that came in via email.

*Please note: if you don’t see your question here, it was answered during the pre-bid meeting. See notes above.

· Would you consider accepting a bid for a prefabricated steel truss pedestrian bridge?

We considered this during the design phase, but decided upon a glulam deck design to give as much flexibility as possible for helicopter capacities. So please bid per the design.

· It appears that the current steel trusses are only attached to the backing planks+stiffener and not to the sill except for gravity. Looking for confirmation on this to aid in removal. This may be answered when the old bridge plans are posted.

The open web joists are welded to bearing plates that are bolted into the sills. I added a close-up photo in the link, along with the old plans.

· Do you know how the current sills are bolted to the concrete/bedrock? It appears there may be as many as 8 anchor bolts per side?

Per the 1976 plans, the vertical bolts are only 10” long. This would suggest that they do not penetrate into the rock or concrete. And the bill of hardware does not specify any anchor bolts. Please note, conditions on site may vary from the plans provided.

· Can you confirm that chainsaws will be allowed to fall standing dead trees in the area of the bridge site? This was discussed in the pre-bid meeting, I'm just looking for confirmation.

Yes, this will be allowed at and near the bridge site.

· Landing a helicopter near the bridge site was discussed in the pre-bid meeting. Is there a distance from the bridge site that the approval for this was granted? i.e, would it be acceptable to land 1/4 mile from the site, or 1/2 mile if those are the closest suitable spots?

Yes, up to a ½ mile from the bridge site would be acceptable.

· Has an established detour been scouted already and/or is there an acceptable creek ford nearby for stock? I assume that the USFS will not be closing the trail for the duration of the project? Is there a need for a temporary bridge or trail to be built to accommodate the public during construction?

We are finalizing a detour that will have an acceptable creek ford for stock. The contractor will not be responsible for temporary crossing or trail to be constructed. However, the contractor will be responsible for site safety, including directing hikers away from the construction site to this detour (traffic control). With the contractor’s help, we’ll post detour information in key locations.

· How soon before the working period is the Notice To Proceed expected to be issued?

We’re flexible. It can be issued on the day the contractor starts, or before, as requested. Time needed to fabricate the bridge will not count against the 120 day installation timeline.

· Are additional shop drawings required, or shall the contractor follow those provided in the drawings document, as well as provide their own?

Shop drawings and calculations will be required from the bridge fabricator. The contractor will provide this as a contract submittal, to be approved by the Forest Service. These will adhere to the contract drawings. The contract/construction drawings have additional information beyond the fabrication information.

· Is there a USFS provided staging area for contractor equipment, vehicles and material during the project? Can removed & old bridge material be stored there until demob of the project?

Yes, the helicopter staging area has been designated (coordinates provided in previous question) and is adjacent to Highway 108. Yes, contractor equipment and materials, including the old bridge, may be stored there until demobilization.

· Is there a helipad/helispot or staging area that the agency has in mind or typically uses to launch aircraft missions from in this area? If so, is that helipad accessible by semi truck and can Material be stored near the heli site before & after flight days or until final demob?

See answer to previous question. Yes, it is accessible to semi-trucks and material may be stored in the same open location.

· Are treatments applied by the contractor in the shop (ex 3 coats of Copper Naphthenate) acceptable for railings and posts to preserve a rustic appearance, or is factory, pressure treated material prefered for these to conform to the UC4A standard? If factory treated material is to be used for, is there a requirement on the appearance of that material (color, indenations, etc) to preserve the wilderness character of the bridge?

Posts are to be pressure treated, but horizontal railing is not to be treated at all. Please see notes on Sheet 2 of the drawings for all timber treatment requirements. Appearance is typical of FS standard trail bridges and not specific to wilderness requirements for character.

· Once given notice to proceed, what is the contingency in case of fire closures, other natural disasters? In those cases is there a provision for a timeline extension until the closure is lifted and/or work is possible, or a provision to be allowed in to finish work after the hazard has passed?

The CO can issue a stop work order to pause the contract timeline if required. And yes, if a delay is out of the contractor’s control, such as wildfire closure in the area, an extension could be issued to extend the Period of Performance.

· Aside from snow, are trails in the area generally cleared and maintained to the work site by mid summer?

Typically, but not necessarily. The Forest Service, PCTA, and others perform maintenance on the trail, but there are a lot of trail priorities, so this portion of trail may not yet see maintenance, depending on the year.

· If trees need to be felled at the work site to make helicopter operations safe - is it acceptable for the contractor to identify and perform that work? If not, are there agency personnel?

Yes, they may be felled, with the approval of the COR.

· Is there an area nearby the worksite (within a 1/2 mile) to set up a long term work camp?

Yes, the contractor may choose a site. There are quite a few open and flat areas within ½ mile of the bridge. The contractor will have to follow the principles of Leave No Trace.

· July 1st is a date where helicopter companies will begin fire contracts with no availability until November of the same year. Is there any chance that the successful bidder could fly everything in the last week of June to guarantee the project completion? This would also minimize the amount of flights due to using a larger ship (blackhawk) up front.

This would be considered but would need approval from Forest Service wildlife biologists prior to starting.

· If we have to use a smaller ship (MD530) for the Bridge Timbers we will need to limit the Glulam width size down to 8 3/4" x 16" to keep the weight under 1200 lbs. Would it be OK to redesign with 8 of these?

Yes, as long as the fabricator’s engineer approves and stamps the plan, this will be acceptable.