About this file
This file is an Evaluation Factors document for the Humboldt Pacific Crest Trail Bridge Replacement solicitation. The document establishes the criteria by which the government will evaluate offeror quotes for this U.S. Department of Agriculture Forest Service project. The solicitation is a Total Small Business Set-Aside with a magnitude range between $500,000 and $1,000,000. Quotes are due December 11, 2026, at 1700 Mountain Time, submitted electronically to the Contracting Officer at lonnie.root@usda.gov. The anticipated award date is December 10, 2026, with a Period of Performance from July 1, 2027, to October 29, 2027 (120 days). A bid bond equal to 20% of the quote is required.
The project involves replacing the Pacific Crest Trail bridge over the West Fork West Walker River in the Hoover Wilderness within Humboldt-Toiyabe National Forest. Due to the remote location with no motorized access, the site visit is conducted via Zoom; however, offerors may visit the site at their convenience. A virtual pre-bid meeting is scheduled for Friday, November 6, 2026, at 10:00 a.m. PST via Microsoft Teams, during which a video of the site will be shared. Vendor questions should be emailed to the Contracting Officer Representative, Jordan Burge, Civil Engineer, at jordan.burge@usda.gov. The evaluation factors document itself establishes the specific scoring criteria the government will use to assess proposals, though the detailed evaluation factors are contained within this attachment file.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C04 R2_1240LT27Q0026_SOW.pdf | ||
| C04a R2 SOI.xls | XLS spreadsheet | |
| C04b R2_Drawings_PCT TRAIL BRIDGEup.pdf | ||
| C04g R2_QA 11_05_2026_PCT_Bridge.doc | DOC document | |
| C04c DOL Wage_CA20260020 07.30.2026_1240LT27Q0026.txt | TXT text file | |
| C04b Drawings_PCT TRAIL BRIDGE_1240LT27Q0026.pdf | ||
| C04e - Past Performance Data Sheet_1240LT27Q0026.pdf | ||
| C04 1240LT27Q0026_SOW.pdf | ||
| C04a SOI_1240LT27Q0026.xls | XLS spreadsheet | |
| C04d Experience Questionnaire _1240LT27Q0026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Evaluation criteria for consideration in addition to price. Proposals which do not demonstrate technical acceptability will not be considered for award.
Factor 1. Technical Capability/Approach. When evaluating the Technical Approach to Performing the Work, the government will assess the reasonableness of the contractor’s proposed approach to performing the work. The proposed approach must contain:
· Technical proposal thoroughly describing how the work will be completed. The proposal should highlight the means and methods for all types of construction required under this solicitation and address challenges associated with project. Address key components including but not limited to: handling/transport of materials and people, tools and other challenges in remote location, pedestrian traffic control, safety plan identifying risks associated with project, erosion and pollution control.
· Provide a proposed schedule of work detailing the timeframes when major portions of the work will take place. The schedule should be accompanied by a narrative explaining the schedule of work items.
· Resources (key personnel, equipment, and key subcontractors) which are planned for use on the project. An equipment list should be provided and described. Key personnel and their qualifications should be detailed in the approach.
Factor 2. Experience. The Government will assess the specialized experience and skill of the firm within the past five years with a focus on experience that is relevant to the specified project. Relevant experience includes:
· Trail construction or reconstruction
· Bridge construction
· Construction projects requiring helicopter, pack transport or other logistical transportation challenges
· Construction projects in remote areas, on steep and challenging terrain
· Prior experience with government contracts
· Other experience submitted will be considered
Factor 3. Past Performance. The Government will evaluate each offeror's experience based on recent, relevant past performance. Contractors should submit three recent, relevant projects, similar in scope and magnitude to the work described in Factor 1, Technical Capability/Approach. The projects submitted for review should have been completed within the last 3 years. Each project submitted shall include the following:
· The project name, contract number & location
· Brief description
· Dollar value including all modifications.
· Customer name, email and phone number
· CPARS print out, if available
File details come from the government source that posted it. Updated .