About this file

This is a Fire Plan form (R6-FS-6300-55) used by the USDA Forest Service Region 6 in conjunction with related contracting forms (R6-FS-6300-52, R6-FS-6300-53, and R6-FS-6300-54) for federal forest service contracts.

The document establishes fire prevention and suppression responsibilities and procedures for contractors working in Forest Service project areas. The contractor is required to take all reasonable and practical action to prevent and suppress fires within the project area, with suppression action to commence immediately upon discovery of or awareness of any fire. The plan identifies key personnel including the contractor's fire matters representative, the Contracting Officer's Representative, and Forest Service inspector(s), along with their contact information. The contractor must designate one or more fireguards responsible for fire detection and suppression. The form specifies whether employees may smoke in the project area and whether open fires are permitted, both requiring written authorization from the Contracting Officer's Representative if allowed. Fire reporting procedures are documented with designated Forest Service employee contacts. The Forest Service retains the authority to counsel the contractor on suppression actions and may supplement contractor efforts or assume control of fire suppression operations if a fire is not suppressed by the contractor and requires appreciable reinforcements. The plan includes sections for identifying contractor employees with firefighting qualifications and special fire assignments, available equipment by description and type, and the total number of employees capable of performing firefighting duties. The document requires joint signature by both the contractor and Contracting Officer's Representative upon completion.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contractor Contractor Number

Project Name Contract Performance Period

Contractor’s Representative for Fire Matters

Telephone Number Name Title Office Residence

Contracting Officer’s Representative

Telephone Number Name Title Office Residence

Forest Service Inspector(s)

Telephone Number Name Title Office Residence

Action by Contractor

The Contractor shall take all reasonable and practical action to prevent and suppress fires in the project area. The Contractor shall take suppression action immediately upon discovery of or becoming aware of such fires.

R6-FS-6300-55 (04/01)

USDA Forest Service – Region 6

FIRE PLAN

(For use with Forms R6-FS-6300-52) R6-FS-6300-53 and R6-FS-6300-54

Action by Forest Service

The Forest Service may counsel with the Contractor on suppression action and will, when necessary, supplement the Contractor’s efforts by furnishing personnel and equipment not available to the Contractor. In the event that a fire is not suppressed by the Contractor and will require appreciable reinforcements, the Forest Service may take over suppression of the fire and may employ the Contractor’s personnel and equipment.

Fire Prevention and Suppression

Predicted fire precautions class may be obtained from the following local sources:

The Contractor has employed or designated the following named individual(s) as fireguard, whose duty is the detection and suppression of fires.

Telephone Number Name Title Office Residence

Contractor will [ ], will not [ ], permit employees to smoke while in the project area. Open fires will [ ], will not [ ], be permitted by the Contractor. Although these activities may be permitted by the contractor, it is understood that neither shall be allowed without being authorized in writing by the Contracting Officer’s Representative.

Fires shall be reported to one of the following Forest Service employees:

Telephone Number Name Address or Location Office Residence

Contractor’s Employees Processing Special Fires Qualifications

Best Fire Other Name Assignment Qualifications

Total number of employees who could perform firefighting duties

Description, Type, Number Make, Model, Size

Joint Preparation of this fire plan is acknowledged:

Contractor or Designated Representative Contracting Officer’s Representative

Date Date

Attachment 2 - Project Specifications.pdf
Preface
101 - Terms¸ Format¸ and Definitions
101.01 Meaning of Terms.
101.03 Abbreviations.
101.04 Definitions.
102 - Bid¸ Award¸ and Execution of Contract
Delete Section 102.
103 - Scope of Work
Delete Subsections 103.02, 103.03, 103.04, 103.05.
104 - Control of Work
Delete Subsections 104.01, 104.02, 104.04.
104.06 Use of Roads by Contractor.
105 - Control of Material
105.02(c) Contractor-located sources.
106 - Acceptance of Work
106.01 Conformity with Contract Requirements.
106.02 Visual Inspection.
107 - Legal Relations and Responsibility to the Public
107.02 Protection and Restoration of Property and Landscape.
Delete Subsection 107.05.
108 - Prosecution and Progress
Delete Section 108.
109 - Measurement and Payment
Delete Subsections 109.06, 109.07, 109.08, 109.09.
109.01 Measurement of Work.
109.02 Measurement Terms and Definitions.
152 - Construction Survey and Staking
152.04 General.
152.05 Survey and Staking Requirements.
Table 152-1 Construction Survey and Staking Tolerances
155 - Schedules for Construction Contracts
Delete Section 155.
156 - Public Traffic
Section 156. – PUBLIC TRAFFIC
157 - Soil Erosion and Sediment Control
157.04 General.
201 - Clearing and Grubbing
Section 201. — CLEARING AND GRUBBING
201.01 Description
201.04 Clearing
201.06 Disposal.
202 - Additional Clearing and Grubbing
Section 202. — ADDITIONAL CLEARING AND GRUBBING
203 - Removal of Structures and Obstructions
203.05 Disposing of Material.
204 - Excavation and Embankment
Section 204. — EXCAVATION AND EMBANKMENT
301 - Untreated Aggregate Courses
301.03 General.
301.05 Compacting.
633 - Permanent Traffic Control
633.02 Material.
633.03 General.
633.05 (a) Fabrication.
703 - Aggregate
703.05 Subbase, Base, Surface Course, and Screened Aggregate.
704 - Soil
704.03 Backfill Material.
6330-1000 – Precast Concrete Vaulted Toilet
6330-1000.01 Work
6330-1000.02 Materials
6330-1000.03 Construction
6330-1000.04 Existing Concrete Vault Toilets along Scenic Highway
6330-1000.05 Measurement
6330-1000.06 Payment
64603-0800 – FIXTURE, KIOSK
64603-0800.01 Work
64603-0800.02 Materials
64603-0800.03 Construction
64603-0800.04 Measurement
64603-0800.05 Payment