C04_Attachment 4 - Environment Great Lakes and Energy (EGLE) Memo.pdf
PDF 120 KB Posted
- Attached to
- Indian River Canoe Trail Clearing Federal contract opportunity
- Solicitation number
- 12444526Q0039
- Issued by
- Department of Agriculture Forest Service
About this file
This is a preapplication meeting letter from the Michigan Department of Environment, Great Lakes, and Energy (EGLE) Water Resources Division regarding the proposed Indian River Water Trail (Recreational Segment) project in Schoolcraft and Alger County.
The determination issued on March 1, 2022, concludes that no permit is required under Part 301, Inland Lakes and Streams, of the Natural Resources and Environmental Protection Act for the project as proposed by applicant Brian Hinch. This determination is binding on EGLE for two years from the meeting date, provided the project and location remain unaltered. The letter clarifies several permitting requirements: hand or mechanical removal of woody debris does not require a permit if conducted without impacting stream banks or bottom or releasing excess sediment; any stump removal below the Ordinary High Water Mark requires a permit; significant alterations to water flow, impediment to navigation, or securing structures to the stream bank or bottom require a permit; and tree clearing and cutting should be limited to the minimum necessary for navigation while preserving woody debris. The applicant is advised to avoid work during Lake Sturgeon spawning season (first week of May through fourth week of June) to minimize impact to this state-threatened species. The assigned EGLE submission number is HPF-HGVM-YXCSN. The letter emphasizes that this preapplication meeting determination is not a permit and that final permitting decisions will be made only after review of the complete permit application and any public notice comments.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q and A.pdf | ||
| C04_Attachment 1 - Schedule of Items.pdf | ||
| C04_Attachment 2 - SOO.pdf | ||
| C04_12444526Q0039.pdf | ||
| C04_Attachment 3 - Maps.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1504 WEST WASHINGTON STREET•MARQUETTE, MICHIGAN 49855
Michigan.gov/EGLE • 906-228-4853
STATE OF MICHIGAN
DEPARTMENT OF
ENVIRONMENT, GREAT LAKES, AND ENERGY
MARQUETTE DISTRICT OFFICE
March 1, 2022
VIA E-MAIL
Brian Hinch 400 East Munising Avenue Munising, Michigan 49862
Dear Brian Hinch:
SUBJECT: Preapplication Meeting MiWaters Site Name: 02-Indian River Water Trail (Recreational Segment)- Munising Twp Submission Number: HPF-HGVM-YXCSN Schoolcraft and Alger County
This letter is a follow up to our March 1, 2022, preapplication meeting regarding the proposed Indian River Water Trail project in Schoolcraft and Alger County. The purpose of a preapplication meeting is to provide you with information that will clarify the permit process, answer preliminary questions about your specific project in order to avoid delays at a later date, and to determine, if possible, the need for wetland or inland lakes and streams permits.
During this meeting, we reviewed the need to obtain a permit under Part 301, Inland Lakes and Streams, of the Natural Resources and Environmental Protection Act, 1994 PA 451, as amended (NREPA). The review was based on discussion of the proposed project and/or draft permit application, the proposed site, and potential modifications to the project discussed during our meeting.
A permit is not required for the project as proposed.
This determination is based on the project plan prepared by Brian Finch along with other information provided at the time of this meeting only. Provided that the proposed project and location are not altered, this determination is binding on EGLE for a period of two years from the date of this meeting.
During the meeting, we also discussed a number of issues related to the project, including the following:
• Hand or mechanical removal of woody debris does not require a permit from EGLE.
However, to avoid permitting, the project must be conducted in a manner that will not impact the stream banks or stream bottom and will not release an excess of sediment.
• Any stump removal below the Ordinary High Water Mark would require a permit.
• Any significant alteration in water flow, impediment to navigation, or securing structures to the stream bank or bottom would require permit.
LIESL EICHLER CLARK
DIRECTOR
GRETCHEN WHITMER
GOVERNOR
Brian Hinch March 1, 2022
• Tree clearing and cutting should be limited to the minimum amount necessary to allow for navigation while preserving as much of the woody debris as possible.
• The potential presence of state-threatened Lake Sturgeon. Potential strategies to avoid or minimize impact to Lake Sturgeon include avoiding work during sturgeon spawning from the first week of May to the fourth week of June. We recommend review of the material available on the Michigan Department of Natural Resources' website at Michigan.gov/Threatened and Endangered Species.
Please note that this is not a permit. The WRD cannot indicate during a preapplication meeting whether or not a permit will be issued. The WRD cannot make a decision regarding a permit until it has considered all of the information provided in the final permit application, and, in some instances, has also considered comments received in response to a public notice of the project.
Therefore, the WRD cannot legally tell you whether the project will be permitted in advance of a permit application being submitted and reviewed.
The EGLE submission number assigned to this project is HPF-HGVM-YXCSN. Please keep a record of this submission number and use it when submitting a final application or otherwise corresponding with our office on this project.
We appreciate the opportunity to meet with you or your representative to address these concerns. We have established a submission for this project, and the information submitted to date will be used to facilitate processing of the final application. If you should have follow-up questions before then, please contact me at 906-869-4703; KnollK1@michigan.gov; or EGLE, WRD, Marquette District Office, 1504 West Washington Street, Marquette, Michigan 49855.
Sincerely, Kayla Knoll Water Resources Division
KK:SLS
cc: Larissa Schmock https://www.michigan.gov/dnr/0,4570,7-350-79134_82777-230551--,00.html
File details come from the government source that posted it. Updated .