This is a Schedule of Items for a road surfacing and stabilization services contract with the Springerville Ranger District of Apache-Sitgreaves National Forests in Apache County, Arizona, under solicitation NFSR 249E.

The contract includes four base line items: (1) Mobilization and Bonding as a lump sum for one unit; (2) Roadway Aggregate 1" minus with an estimated quantity of 12,617 tons, including haul, placement, stabilization, and compaction using Method 2 per SOW C.5, Table 31-2, Gradation G; (3) Road Reconditioning for 5.29 miles; and (4) Dust Palliative Type 80/20 Lignin Sulfonate/Magnesium Chloride Blend at 1.0 gallon per yard for an estimated 68,276 gallons. Water is incidental to items 302.01, 303.01, and 312.01. The schedule also includes three optional line items that correspond to the base items with reduced quantities: 239 tons of roadway aggregate, 0.1 mile of road reconditioning, and 1,291 gallons of dust palliative. Option items will be awarded in 0.1-mile increments, as funding allows, and prior to issuance of the Notice to Proceed. Contractors are required to submit unit prices and total prices for each line item to calculate the Base Items Total and optional pricing.

View the file

Other files for this federal contract opportunity

Other files attached to 249E Road Surfacing & Stabilization - Apache-Sitgreaves NF, AZ, newest first.
File Type Posted
C05 127EAX26Q0071 0001.pdf PDF
C05 RFI Log 001-020 answered.docx DOCX document
C04 127EAX26Q0071.pdf PDF
C04 Attachment 3 MAP.pdf PDF
C04 Attachment 5 Aggregate Specifications.pdf PDF
C04 Attachment 1 Statement of Work.docx DOCX document
C04 Attachment 8 BioPreferred.pdf PDF
C04 Attachment 9 Wage Determination AZ20260023 Mod 1.pdf PDF
C04 Attachment 4 Spec Aggregates for Earthwork.pdf PDF
C04 Attachment 6 Specs FP-14.docx DOCX document
C04 Attachment 7 Fire Plan.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Schedule of Items Section B - Services and Prices

NFSR 249E Road Surfacing and Stabilization

Springerville Ranger District

Apache-Sitgreaves National Forests

Apache County, Arizona

B-1 Schedule of items

Item No. Description Pay Unit Est.

Quantity Unit Price Total Price

151.01 Mobilization and Bonding

Lump

Sum 1 $ $

302.01 Roadway Aggregate 1" minus

(SOW C.5, Table 31-2, Gradation G).

Includes haul, placement, stabilization and compaction Method 2. Water is incidental to this line item

Ton 12617 $ $

303.01 Road Reconditioning. Water is incidental to this

line item

Mile 5.29 $ $

312.01 Dust Palliative, Type 80/20 Lignin

Sulfonate/Mag Chloride Blend, 1.0 gal/yd.

Water is incidental to this line item

Gallon 68276 $ $

Base Items Total $

Option Items

Item No. Description Pay Unit Est.

Quantity Unit Price Total Price

O302.01 Roadway Aggregate 1" minus

(SOW C.5, Table 31-2, Gradation G).

Includes haul, placement, stabilization and compaction Method 2. Water is incidental to this line item

Ton 239 $ $

O303.01 Road Reconditioning. Water is incidental to this line item Mile 0.1 $ $

O312.01 Dust Palliative, Type 80/20 Lignin

Sulfonate/Mag Chloride Blend, 1.0 gal/yd.

Water is incidental to this line item

Gallon 1291 $ $

Note: Option Items will be awarded in 0.1 mile $ increments, will be awarded as funding allows, and will be awarded prior to Notice to Proceed