C05 RFI Log 001-020 answered.docx

DOCX document 23 KB Posted

Attached to
249E Road Surfacing & Stabilization - Apache-Sitgreaves NF, AZ Federal contract opportunity
Solicitation number
127EAX26Q0071
Issued by
Department of Agriculture Forest Service

About this file

This file is an RFI (Request for Information) Log containing 20 questions and answers related to a road surfacing and stabilization project. The solicitation (127EAX26Q0071) involves reestablishing the road template on NFSR 249E in the Apache-Sitgreaves National Forest, Arizona, covering approximately 5.29 miles from AZ-273 westward to the intersection with NFSR 116, including turnouts and parking areas. Work is preferably completed in one mobilization, with scheduling coordinated through the Forest Service, though work should not occur during winter months when conditions are suboptimal for lignin application. The contractor is responsible for all water procurement—no water may be sourced from lakes, streams, or rivers, with nearby sources available in Springerville or Alpine at approximately 25 miles haul distance.

Key operational requirements include obtaining a Forest Service camping permit (issuable within days of work schedule submission), identifying and certifying compliant 1-inch minus aggregate sources independently, adhering to existing haul routes without creating new roads or off-road turnarounds, and recognizing that Big Lake road access (AZ 261 and AZ 273) is closed December through April. The acquisition is a Total Small Business Set-Aside under NAICS 237310 (Highway, Street, and Bridge Construction) with a $45.0M size standard threshold. Pricing is acceptable as lump sum or unit price per contract line item without required cost breakdowns by work component. The RFI questions due date is August 21, 2026, and proposal due date is September 3, 2026. A single qualified individual may serve concurrently as Quality Control Manager, Site Safety and Health Officer, and Superintendent, provided all qualification requirements are met and the individual is satisfactory to the Contracting Officer.

View the file

Other files for this federal contract opportunity

Other files attached to 249E Road Surfacing & Stabilization - Apache-Sitgreaves NF, AZ, newest first.
File Type Posted
C05 127EAX26Q0071 0001.pdf PDF
C04 127EAX26Q0071.pdf PDF
C04 Attachment 3 MAP.pdf PDF
C04 Attachment 1 Statement of Work.docx DOCX document
C04 Attachment 8 BioPreferred.pdf PDF
C04 Attachment 9 Wage Determination AZ20260023 Mod 1.pdf PDF
C04 Attachment 2 Sched of Items.pdf PDF
C04 Attachment 5 Aggregate Specifications.pdf PDF
C04 Attachment 4 Spec Aggregates for Earthwork.pdf PDF
C04 Attachment 6 Specs FP-14.docx DOCX document
C04 Attachment 7 Fire Plan.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI LOG

Project Name:249E Road Surfacing and Stabilization - Apache-Sitgreaves NF
Solicitation No.127EAX26Q0071
Solicitation Date 4 Aug 2026RFI Close Date 21 Aug 2026
RFI #
DESCRIPTION
RESPONSE
001
Will all the work be allowed to be performed in one mobilization?
Yes. This is preferred. Contractors should not begin work until the lignin has been ordered and prepared to be utilized for the contract.
002
Is there a specific time of the year you want this work to be performed?
Time can be scheduled with the Forest Service. It is expected the delivery of the lignin may take some time. Work should not be done during the winter as conditions are not optimal for use of lignin and ground work.
003
Water - Would we be allowed to pull water out of Cresent or Big Lake?
No. Contractor is responsible for hauling water to the site. WATER CANNOT BE PULLED FROM CRESCENT OR BIG LAKE OR ANY STREAMS. Contractor shall include relevant water costs in the line items they are incidental for in their bids.
004
Water 2 - If no to above is there a known source that water usually comes from for these projects?
Water can be purchased in the town of Springerville or Alpine or other locations. Haul is ~1hr to the site. Contractor can also potentially work out some kind of agreement to purchase water from the reservation/Sunrise Ski Resort.
005
Are we limited to finishing a certain length of roadway in its entirety prior to starting another area, or do we have access to the entire length of roadway?
The base line item is for the length of the NFSR 24 from start to the NFSR 24/26 intersection. This will be required for the contract. The option items listed in the Schedule of Items includes unit costs per 0.1 miles and 1 miles of additional work where award will be conditional on contractor bid and government funding available.
006
Another project in the same area is out for solicitation (NFSR 24).

0. Will that project need to be completed prior to the start of this one?

0. Access to that project will require truck traffic over a portion of this project!

ii. Of course, it would be nice if the same contractor was low on each.

There is the NFSR 24 stabilization and preservation project. A) no the project will not need to be completed prior to the start of this one. I) The contract will be scheduled so no overlap shall occur.

007
Will questions from other contractors be distributed among all contractors that inquire on this project?
Questions received from contractors are transcribed verbatim to this RFI log and distributed as an amendment to this solicitation in SAM.gov.
008
SOW Sec. C.3 / Att. 4 & 5 (Aggregate Specs); Does the Government maintain an approved source list or require independent testing/certification for the 1-inch minus aggregate (Table 31-2, Grading G), or is the Offeror solely responsible for identifying and certifying a compliant aggregate source prior to award?
There is no approved source list or required testing for the 1-inch minus aggregate the offeror is solely responsible for identifying and using a compliant aggregate source.
009
SOW Sec. C.3 (Water Availability); Government water is stated as not available on site. Can the Government confirm the nearest approved water source(s) in Springerville or Alpine, the estimated haul distance to the project site, and whether any water rights or withdrawal permits are required?
The government does not have approved water sources. There are no specific testing needed for the water to be used on the project. However, the contractor cannot use any water from the lakes, streams, or rivers. Nearby water sources such as Springerville have a haul distance of approximately 25 miles. It takes a bit less than a hour. Water from Sunrise Ski Resort is approximately 20 miles away. You should not require water rights, but you will need to purchase the water.
010
SOW Sec. C.3 (Haul Roads); Since creation of new roads or turnarounds is not allowed, can the Government designate the specific existing haul routes and staging/turnout areas contractors may use, along with any weight, width, or seasonal access restrictions on those routes?
Most of the roads are the NFSR249E have no weight or width restrictions. Access to the Big Lake roads (AZ 261 and AZ 273) where the site is at are closed December through April. It may be easier for the contractor to have haul trucks continue on the NFSR116 to the AZ-273 after dropping off loads as this way they would not need to worry about turning. Contractor may existing road intersections to turn such as intersection with Railroad cove (NFSR 249G), South cove (NFSR 249F), or NFSR 68. Contractors are not permitted to have haul trucks drive off existing roads (ex. Into surrounding fields) to turn.
011
Solicitation p.1 (Site Visit); Since no organized site visit is scheduled, can the Government provide recent site photographs/video or a point of contact to arrange an informal, unescorted site visit prior to the proposal due date?
Road conditions are variable as the road receives high traffic use as a popular recreation road. The Forest Service regularly blades the road. Contractors can drive the road as work is for the entire length of the NFSR 249E. COR can be contacted for a site visit prior to the proposal date. Email is Elal.Segev@usda.gov.
012
SOW Sec. C.3 (Unstable Areas); Can the Government provide any existing geotechnical data, prior road condition assessments, or an estimate of the extent (linear footage/area) of soft or unstable areas anticipated to require excavation/undercut repair prior to aggregate placement?
No excavation/undercut repair prior to aggregate placement is expected.
013
SOW Sec. C.3 (Camping Permit); What is the anticipated processing time for the Forest Service district-issued camping permit referenced in the SOW, and could this affect the Contractor's ability to mobilize and begin performance within the mandatory 10-calendar-day NTP window?
The camping permit can be issued within a few days of being given notice of when work will begin. Permit can be issued when contractor submits the schedule for the work. It should not affect the contractor’s ability to mobilize or begin work.
014
Attachment 7 - Industrial Fire Plan; Can the Government confirm the anticipated Industrial Fire Precaution Level (IFPL) restrictions expected during the performance period, including any equipment shutdown hours, spark arrestor requirements, or water tender staffing requirements?
Since the work is anticipated to begin early spring there should be no fire restrictions expected. If it happens this fall there are currently no fire restrictions.
015
Solicitation p.1 (Key Dates); Please confirm whether the August 21, 2026 questions-due date and the September 3, 2026 proposal-due date remain current, or whether any amendment has been issued adjusting these dates.
Information to include any changes to this solicitation will be published as an amendment in SAM.gov.
016
Attachment 2 - Schedule of Items; The Schedule of Items appears to consolidate haul, placement, stabilization, and compaction into a single roadway line item (CLIN 0001). Can the Government confirm whether a lump-sum/unit price per CLIN is acceptable, or whether a cost breakdown by work component must be submitted with the quotation?
Lump sum/unit price per contract line item is acceptable. We do not need a cost breakdown by work components.
017
Solicitation p.16 (FAR 52.217-6 / 52.217-7); The solicitation incorporates FAR 52.217-6 and 52.217-7 (Option for Increased Quantity / Separately Priced Line Item). Can the Government confirm whether an option exists to increase the scope or quantity of this requirement (e.g., additional roadway mileage or a substantially expanded quantity), and if so, provide the associated CLIN structure, estimated option quantities, and the option exercise period?
Any option to increase the scope or quantity of this requirement (e.g., additional roadway mileage or a substantially expanded quantity) will be captured in an amendment with revised or new attachments as applicable.
018
SOW Sec. C.3 (Permits); Beyond the camping permit, can the Government identify any other permits anticipated for this scope of work (e.g., state DOT encroachment, county road use, dust/air quality, or other environmental permits), and confirm whether any permit fees are known in advance?
No other permits are anticipated for the scope of work beyond the camping permit. There should be no
019
Attachment 8 – BioPreferred; Can the Government confirm which specific product categories under the BioPreferred program apply to this project (e.g., only the stabilization product, or also other consumables such as fuels/lubricants)?
Refer to Clause 52.223-2, 52.223-23, and Welcome to the Biopreferred Program Catalog USDA website.
020
Solicitation p.6, FAR 52.236-6 / Project Staffing; May one qualified individual serve concurrently as the Quality Control Manager (QCM), Site Safety and Health Officer (SSHO), and Superintendent for this project, provided the individual meets all applicable qualification, availability, and on-site performance requirements for each role? If not, please identify which positions must be staffed by separate individuals.
Pursuant to FAR 52.236‑6, ‘Superintendence by the Contractor,’ a single competent individual serving as superintendent, who has the authority to act on behalf of the Contractor, may perform multiple roles as assigned and must be satisfactory to the Contracting Officer.