C04_Attachment 2 Photos and Specifications 1232SA26Q0981.pdf

PDF 947 KB Posted

Attached to
Metal Awning Structure Federal contract opportunity
Solicitation number
1232SA26Q0981
Issued by
Department of Agriculture Agricultural Research Service

About this file

This document consists of construction and electrical design specifications and site plans for a new awning structure installation at a USDA ARS Pecan Breeding/Genetics facility. The project encompasses a 125-foot by 36-foot awning to be constructed on the south side of an existing 40-foot by 100-foot building, with an additional 36-foot depth extension area for the new awning footprint.

The concrete foundation requirements include round piers extending 48 inches below grade with bell bottoms and #4 reinforcing bar, utilizing 3,000-pound concrete with top pads extending minimum 2 inches below grade. Vertical support columns are spaced every 4 inches apart, and base anchors must meet metal building structure requirements with rebar extending into top pads and fully encased after pouring. The site plan indicates five existing column supports within the building footprint, receptacle and lighting locations, and a 100-ampere electrical panel. The electrical layout specifications show required loads (LP#10, LP#2, LP#1, LP#3) distributed across the awning structure, with provisions for new lighting circuits, existing light removal, and transformer connections. Site preparation includes extending concrete and caliche 4 feet past the new awning with a 4-inch slab base 12 inches wide perimeter, installation of a sliding gate on the north side, and replacement or stretching of existing perimeter fencing as necessary. No response dates, award information, or pricing terms are specified in these technical specifications.

View the file

Other files for this federal contract opportunity

Other files attached to Metal Awning Structure, newest first.
File Type Posted
C05_Sol_1232SA26Q0981_Amd_0001.pdf PDF
C04_Attachment 4 - RFI Questions and Answers.pdf PDF
C04_Solicitation_1232SA26Q0981.pdf PDF
C04_Attachment 1 SOW 1232SA26Q0981.doc DOC document
C04_Site Visit Information 1232SA26Q0981.pdf PDF
C04_Attachment 3 Wage Determination TX20260235.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1: Aerial view of site.

Location of new awning

Attachment 2: 3D image

Notes:

1. Round pier to be a depth of 48" from grade, belled at the bottom and reinforced with #4 Bar.

2. 3000# concrete

3. Top pad to extend a minimum of 2" below grade.

4. Finished surface elevation of top pad to be determined by framing dimensions as to allow the finished roof line to be a continuation of the existing roof line.

5. Where portal framing is used the top pad and pier should be configured to accommodate for the additional column and base plate.

6. Base Anchors to meet requirements of metal building structure

7. Extend pier rebar into top pad

8. Rebar to be installed and supported as to not make ground contact and be fully encased after pour

1'

3'-10"

Grade

2'-6"

1'-6"

1'

Attachment 3: Concrete footing

Verticals to be spaced every 4" apart

attachment 1 aerial view
Attachment 2 3DBuild.DXF
Attachment 3 Concrete footing
Attachment 4 AwningGradeMeasurments
attachment 5 Electrical
Attachment 6 New layout

File details come from the government source that posted it. Updated .