Summary: Statement of Work - Chino Emergency Repairs

This Statement of Work outlines emergency repairs to three buildings at the Chino Valley Forest Office and Administration Site in Prescott National Forest, Arizona, following monsoonal storm damage. The project requires complete asbestos abatement, roof replacement, drywall and insulation replacement, door replacement, ceiling replacement, gutter and downspout installation, siding replacement, window frame repair, window caulking, and metal roof maintenance across the Chino Yard Office (Building 8810516A), Supervisor's Office (Building 8810516B), and Chino Shop (Building 8810564A). The contractor must supply all materials, equipment, labor, transportation, and incidentals necessary for project completion. Work must commence within 10 days of the notice to proceed and be completed within 60 days from the project start date. The contractor must provide an OSHA 30-HR certified safety inspector, site superintendent, quality control representative, and traffic control supervisor during construction, operating Monday through Friday from 7:00 a.m. to 5:00 p.m. The contractor is responsible for providing temporary portable restrooms and maintaining all staging areas, with restoration of the site to prior condition required upon completion.

The 13 base bid items include mobilization, asbestos abatement, roof replacement with SBS-modified bituminous membrane roofing, drywall and insulation replacement (608 square feet exterior walls and 176 square feet interior walls), door replacement, ceiling replacement (264 square feet drywall and 80 square feet acoustic tiles), metal roof maintenance on both the Supervisor's Office and Shop, Z-bar flashing installation, upper window frame repair with wood epoxy filling, window caulking (112 total windows), yard office gutters and downspouts (26 linear feet gutters, 40 linear feet downspouts), and siding replacement (approximately 74 square feet total). Three optional bid items are available if additional funds exist: exterior painting on the Yard Office, weather stripping installation on two shop garage doors, and door sweep replacement on the shop manway door. All submittals require Contracting Officer's Representative approval before work begins, with a 10-day processing period specified. The Forest Service provides non-potable water, electricity, and cell phone capability on-site but furnishes no materials or items. Construction scheduling must include detailed task breakdowns, key milestones, labor and material procurement timelines, and contingency buffers for weather and unforeseen conditions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOUTHWEST REGION, R03

PRESCOTT NATIONAL FOREST

Chino Emergency Repairs

STATEMENT OF WORK

U.S. FOREST SERVICE

10/22/2026

TABLE OF CONTENTS

1.0GENERAL INFORMATION4
1.1 EMERGENCY JUSTIFICATION4
1.2 WORK SUMMARY4
1.3 PROJECT LOCATION5
1.4 PERFORMANCE PERIOD & WORK RESTRICTIONS5
1.5 POINTS OF CONTACT5
1.6 CONTRACTOR STAGING5
1.7 USE OF PREMISES6
1.8 UTILITIES & SANITATION SERVICES6
1.9 PROTECTION OF NATURAL RESOURCES7
1.10 SUPERVISION, QUALITY CONTROL, AND SAFETY7
1.11 GOVERNMENT FURNISHED ITEMS AND MATERIALS7
1.12 CONSTRUCTION SCHEDULE7
1.13 SUBMITTALS7
2.0 PROJECT SCOPE8
2.1 SCOPE8
2.2 BASE BID ITEMS8
2.3 OPTION BID ITEMS11
2.4 SCOPE ATTACHMENTS12
ATTACHMENT A13
ATTACHMENT B14
ATTACHMENT C94
ATTACHMENT D100
ATTACHMENT E111
ATTACHEMENT F116
ATTACHMENT G120

1.0 GENERAL INFORMATION

1.1 EMERGENCY JUSTIFICATION

During recent monsoonal storm events at the Chino Valley Forest Office and Administration Site, located at 735 North US Highway 89 in Chino Valley, Arizona, there was damage sustained to three of the buildings 8810516A-Chino Yard Office, 8810516B-Supervisor’s Office and 8810564A-Chino Shop.

Damages to the Chino Yard Office include the destruction of the roof, major water damage to interior walls and the ceilings. This building was tested for Asbestos and was found to have 5% chrysotile asbestos in the roofing materials and will need to be abated prior to the roof being replaced. This building provides permanent office spaces for four (4) full-time employees, which include the Forest Safety Manager, the Timber Staff Officer, the acting Assistant Fire Staff Officer, and the Forest Fire and Fuels Planner, who have all been displaced. The long-term displacement of these employees will disrupt and impede the effectiveness of strategic planning for the reduction of forest fuels and could lead to extreme fire conditions that could impact the lives of the public that live adjacent to our forest. These employees are also supporting local logging and biomass markets that support the rural prosperity of the local community.

The Chino Shop sustained damage to the metal roof, and some minor water intrusion beneath the door and around the two garage doors. This building provides office space to four (4) full-time and ten (10) season fire and fuels employees, as well as providing storage for all their firefighting equipment, who provide forest fuels reduction in the forest around this community and who support wildfire suppression during local fire events. Although these employees have not been displaced, if damage is not mitigated immediately, the building will become unoccupiable which could lead to delays responding to wildfires in the community.

The Supervisor’s Office sustained water intrusion from the upper windows and some minor damage to the metal roof. While investigating the roof damage it was found that the upper roof did not have a z-bar flashing. This building provides office space to 12 full-time employees, which include the Forest Supervisor, Deputy Forest Supervisor, the Forest Leadership Team, the Public Affairs Officer, the Fire Staff Officer and others. Currently these employees are not displaced; however, if these issues are not resolved quickly, the water intrusion could worsen, causing mold growth and impacting the health of the employees.

1.2 WORK SUMMARY

This project consists of providing all materials, equipment, labor, transportation, and incidentals for completion of the repair storm damage sustained on three buildings at this site.

The repairs are to include roof replacement, dry wall and insulation replacement, a door replacement, ceiling and insulation replacement, installation of gutters and downspouts, and to replace a portion of the side of the Chino Yard Office; to perform maintenance to the metal roofs on the Supervisor’s office and the Chino Shop; to repair window frames on upper windows, to caulk ALL of windows, and to install a Z bar at the roof line on the Supervisor’s Office; and to gutters and downspouts on the Chino Shop.

This project could also include, if additional funds are available, optional bid items. The optional bid items are exterior painting on the Yard Office; replace the weather stripping on two garage doors and a door sweep on a manway; and if mold is found in the Supervisor’s Office to replace the dry wall and insulation.

1.3 PROJECT LOCATION

The Supervisor’s Office is located at 735 N Highway 89, Chino Valley, AZ 86323, LAT: 34.756125°, LONG: - 112.453483°, and is accessible on paved roads. From the intersection of Highway 89A and Highway 89 in Prescott, AZ, travel north on Highway 89 for approximately 8.75 miles, the project site will be located on the east side of the road. The other two buildings are both located less than 150 feet from the Supervisor’s Office. The Yard office is located behind a locked gate and an access code will be provided at the time of the award of this project.

Building ID
Building Name
Location
Latitude
Longitude
8810516B
Supervisor’s Office
Chino Admin Site
34.756125°
-112.453483°
8810454A
Chino Yard Office
Chino Admin Site
34.755983°
-112.452840°
8810354B
Chino Shop (a.k.a. Crew 2 Building.)
Chino Admin Site
34.756026°
-112.452967°

1.4 PERFORMANCE PERIOD & WORK RESTRICTIONS

A. Work shall begin no more than 10 days after the notice to proceed is issued by the Contracting Officer.

B. The Contractor shall give the Contracting Officer’s Representative 48 hours’ notice prior to beginning work.

C. Work shall be completed within 60 days of the project start date.

1.5 POINTS OF CONTACT

Contracting Officer:

To be determined

Contracting Officer’s Representative:

Theresa “Terri” Beard, Theresa.beard@usda.gov, (928) 458-1503

1.6 CONTRACTOR STAGING

A contractor staging area near the Yard Office will be approved by the Contracting Officer’s Representative (COR) prior to work beginning. Keep staging and storge areas confined to previously ground-disturbed areas adjacent to the project locations. Rehabilitate and repair sites, removing ruts and restoring natural conditions and grading. Any damages resulting from the Contractor’s use of these sites will be repaired or replace at the Contractor’s expense at the direction of the COR.

1.7 USE OF PREMISES

This work center will remain open to government employees and construction will be performed during normal waking hours from 7:00 a.m. to 5:00 p.m. Monday through Friday.

Driveways, Walkways, and Entrances: Keep driveways, walkways and entrances serving clear premises and available to emergency vehicles and pedestrians. Do not use these areas for parking or storage of materials, unless approved by the COR.

The Contractor shall limit the ground disturbance and equipment to a minimal area in each area of work. The COR will be responsible for establishing the work limits and the Contractor is responsible for marking or otherwise communicating the limits to the Contractor’s personnel and subcontractors.

Smoking is not permitted within any government building, or within 25 feet of any entrance or window. Smoking is also prohibited outside an enclosed vehicle during Stage 1 and 2 fire restrictions.

Provide adequate signage and barricades and take necessary safety measures to protect the public during all construction operations. Minimize disturbance of all undisturbed areas. The work zones shall be delineated and marked adequately to warn other government contractors and all government employees of equipment operations and other hazardous conditions. The Contractor is responsible for providing barrier materials and maintaining barriers such as temporary barricades, barrier tape, curbs, etc. at all work zones. The Contractor shall remove all temporary facilities and restore the site to its prior condition as a part of the project closeout procedures. Any damage to existing improvements shall be repaired at the Contractor’s expense according to the direction of the COR.

Secure equipment and contract work against theft and vandalism. The Government is not responsible for the theft and/or vandalism of any materials or equipment, including government furnished items left at the project site even if they are behind the locked gate.

1.8 UTILITIES & SANITATION SERVICES

Non potable water is available at this site, as well as electricity and cell phone capabilities; however, the Contractor is responsible for supplying temporary portable restrooms for the Contractor’s employees and subcontractors to use during the duration of the project. All temporary services shall be completely removed, and the use area shall be restored upon the completion of use.

1.9 PROTECTION OF NATURAL RESOURCES

Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, and repair or replace damaged trees and plants, at no additional expense to the Government. Provide temporary barriers to protect existing trees and plants and root zones. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with COR and remove agreed-on roots and branches that interfere with construction. Do not fasten ropes, cables, or guys to existing trees.

1.10 SUPERVISION, QUALITY CONTROL, AND SAFETY

The Contractor shall provide an OSHA 30-HR certified safety inspector, a site superintendent, quality control representative, and traffic control supervisor during construction activities.

Contractor may elect to have all (traffic) safety, superintendent, and quality control duties under the supervision of one individual, so long as the individual is qualified and certified to meet the requirements.

1.11 GOVERNMENT FURNISHED ITEMS AND MATERIALS

The Government will not furnish any items or materials.

1.12 CONSTRUCTION SCHEDULE

Submit a detailed schedule that includes, but is not limited to:

· A detailed breakdown of all project tasks, phases, and sub-phases

· Key milestones, including Notice to Proceed, substantial completion, and owner-defined check-points.

· Identification of labor, equipment, and material procurements, including submittal approval, fabrication, and delivery times.

· Buffer/Float: Inclusion of reasonable buffers for weather, inspections, or unforeseen conditions.

1.13 SUBMITTALS

After award and pre-work meeting, furnish submittals for the following items before work begins:

-
Work Schedule
-
Rolled Asphalt Material (Style and Color)
-
Sheathing Material
-
Underlayment
-
Flashing
-
Drip Edges
-
Wall Insulation
-
Interior Primer Data
-
Interior Paint Data and Colors
-
Door/Door Frame
-
Ceiling Tile Style
-
Ceiling Insulation
-
Metal Roof Materials
-
Z Bar and Color
-
Wood Filling Epoxy
-
Interior Primer Data
-
Exterior Paint Data and Color
-
Window Caulk
-
Lap Siding Wood
-
Exterior Primer Data
-
Weather Stripping Materials
-
Vertical Siding Wood
-
Door Sweep
-
Bill of Lading for the Asbestos Disposal
-
Gutter and Downspout Materials/color

2.0 PROJECT SCOPE

2.1 SCOPE

The Contractor shall furnish all supervision, materials, equipment and vehicles, tools, parts, labor, transportation, lodging, and miscellaneous items to complete the Chino Emergency Repairs in accordance with the specifications, and other attachments referenced and contained herein. Repairs are to include: on the Chino Yard Office the complete asbestos abatement, roof replacement, dry wall and insulation replacement in two offices and the common area, a door replacement, ceiling and insulation replacement in two offices and the common area, to install gutters and downspouts and to replace approximately 74 square feet of siding. At the Supervisor’s Office, perform metal roof maintenance, install a Z-bar on the apex of the upper roof, repair the upper window frames, and caulk ALL windows. On the Chino Yard Office, perform metal roof maintenance, and to install gutters and downspouts.

If additional funds are available optional bid items will be awarded; these optional bid items can include: On the Chino Yard Office exterior painting; on the Chino Shop, install new weather stripping on two garage doors and install one door sweep on the manway door.

No changes to the specifications, terms, or conditions of this statement of work shall be made without the prior approval of the Contracting Officer, in writing.

2.2 BASE BID ITEMS

2.2.1 BASE BID 001 Mobilization

Mobilization, one-time cost.

2.2.2 BASE BID 002 Yard Office Asbestos Abatement

On August, 31, 2026 an asbestos test was conducted on the roofing material on the Chino Yard Office Building, it was found to contain asbestos materials in the gray roofing mastic with the silver paint and the black roof mastic with mesh. This material shall be completely removed, prior to the installation of the new roof and properly disposed of off Forest.

The contractor shall show proof of certification in compliance by EPA to engage in asbestos removal activities as per 40 CFR 745.225, 226 & 227. The contractor shall comply with the Federal Regulatory Agencies: U.S. Environmental Protection Agency (EPA), U.S. Housing and Urban Development Agency (HUD), U.S. Occupational Safety and Health Administration (OSHA), U.S. Department of Transportation (DOT), U.S. Department of Health and Human Services (HHS), U.S. Department of Labor (DOL). They shall also comply with local and State laws, regulation and regulatory agencies; and Arizona Department of Environmental Quality (ADEQ).

Asbestos removal activity in the building shall be conducted per OSHA and NESHAP standards and regulations. The Contractor shall be licensed by the State of Arizona as an Asbestos Abatement Contractor. Additionally, the contractor shall meet all local, state, and federal regulations for the abatement of asbestos.

All Asbestos Containing Material (ACM) shall be wet and double bagged in minimum 6 mil plastic containers with duct taped seams. Asbestos Containing Material shall be disposed of at an appropriate landfill, with a completed transportation manifest provided to the government upon completion of the project. The disposal costs are the responsibility of the contractor and the contractor shall provide a bill of lading to the COR.

An Asbestos NESHAP Notification/Permit Activity Application for Abatement/Renovation Activities must be filed with Arizona Department of Environmental Quality prior to commencement of work at all sites.

2.2.3 BASE BID 003 Yard Office Roof Replacement

On the Chino Yard Office, remove weakened or rotten decking, replacing with new decking, then install new underlayment, rolled roofing material and flashing around the roof edges and the HVAC Unit.

All existing materials shall be removed from Forest Service Lands and disposed of in an acceptable landfill.

All decking, underlayment; roofing materials including color and style; and shop drawings shall be approved by the COR.

2.2.4 BASE BID 004 Yard Office Dry Wall and Insulation Replacement

At the Chino Yard office, in the two offices on the north side and the common area remove approximately 608 square feet drywall and insulation of all the exterior walls and on the interior walls remove approximately four feet of the lower portion (176 square feet) of the dry wall between the north offices and the common area (both sides of the wall). After damaged drywall and insulation is removed, replace with new insulation and drywall; finish the walls to match the existing skip trowel finishing texture; prime; and paint the new drywall.

Insulation, primer and paint type and color shall be approved by the COR.

2.2.5 BASE BID 005 Yard Office Door Replacement

Remove existing door and door frame of the northeast office of the Chino Yard office building, saving the hardware to be reused on the new door. Replace the door, door frame, molding and stain to match the existing doors.

Door, molding and stain shall be approved by the COR.

2.2.6 BASE BID 006 Yard Office Ceiling and Insulation Replacement

At the Chino Yard office, in the two offices on the north side remove approximately 264 square feet drywall and insulation ceiling and replace with new insulation and drywall ceiling; finish the ceiling to match the existing skip trowel finish; prime; and paint the new ceiling. In the common area, remove approximately 80 square feet of damaged acoustic ceiling tiles; remove approximately 198 square feet of insulation; replace all insulation; replace damaged acoustic ceiling tiles with matching panels.

Primer; paint type and color; insulation and acoustic tiles shall be approved by the COR.

2.2.7 BASE BID 007 Metal Roof Maintenance on Supervisor's Office and Shop

The standing seam metal roofs of the Supervisor's Office (approximately 4900 square feet) and the Chino Shop (approximately 1520 square feet), require maintenance which is to include; inspection of all gaskets, joint fillers, and sealants for weatherproofing performance; replacement of any damaged or missing gaskets, joint fillers and sealants with manufacturer's recommended materials; checking all fasteners for snugness and insuring that rubber washers are not worn or over tightened; and to inspect all boots and reseal if necessary.

2.2.8 BASE BID 008 Supervisor's Office Install Z Bar on Upper Roof

Install approximately 102 linear feet of Z-bar flashing at the apex of the upper roof of the Supervisor’s office. Flashing shall be of the same material as the existing roof or shall be separated with a bituminous coating or self-adhering sheet underlayment.

Flashing material, and shop drawings shall be approved by the COR.

2.2.9 BASE BID 009 Supervisor's Office Repair Upper Window Frames

Remove solar shades from the upper windows of the Supervisor’s Office to remove all rot from approximately 310 linear feet of wood window frames and fill with wood filling epoxy and to replace all solar shades. There are a total of 24 windows that are separated by a total of twenty-seven (27) – 2” x 6” timbers that are approximately four (4) feet long. These windows also are framed at the top and bottoms with a total of forty-eight(48) 2” x 6” timbers that are four (4) feet. After repairing the rotten wood, install backer rod in the gaps that are to deep to caulk, caulk around the window frames and re-install all solar shades.

2.2.10 BASE BID 010 Supervisor's Office Window Caulking

Remove the solar shades from the windows on the south side of the building. Inspect the wood frames for any potential rot and advise the COR of findings. Caulk all windows and window frames, there are 32 sets of lower windows and 24 upper windows (outside windows are included in 2.2.9), for a total of 112 individual windows that will need to be caulked inside and out. After caulking is complete, re-install the solar screens.

2.2.11 BASE BID 011 Yard Office Gutters and Down Spouts

Install approximately 26 feet (52 feet total) of seamless gutters on both the north and the south sides of the Chino Yard Office, install four (4) each – approximately 10 feet (40 feet total) downspouts located on each corner of the building, and provide a concrete splash pad at each downspout.

Color, style and materials shall be approved by the COR.

2.2.12 BASE BID 012 Yard Office Siding

Remove approximately two (2) square feet of rotten wood lap siding on the east side of the building above the porch area and replace with new siding that matches the existing siding. On the north side of the building, remove approximately 72 square feet of vertical siding and replace with new siding that matches the existing lap siding on the rest of the building.

All Materials shall be approved by the COR.

2.2.13 BASE BID 013 Shop Gutters and Down Spouts

Install approximately 49 feet (98 feet total) of seamless gutters on both sides of the Chino Shop, install approximately four (4) each – 12 feet (48 feet total) downspouts located on each corner of the Cabin, and provide a concrete splash pad at each downspout.

Color, style and materials shall be approved by the COR.

2.3 OPTION BID ITEMS

2.3.1 OPTION BID 014 Yard Office Exterior Painting

Sand, prime and paint all window frames, door frames, eves, and fascia, of Chino Yard Office, with an acrylic latex exterior paint and primer that matches the existing colors.

Paint, paint color and primer shall be approved by the COR.

2.3.2 OPTION BID 015 Shop Garage Door Weather Stripping

Install new weather stripping on all sides and the bottom of two (2) garage doors on Chino Shop Building. The chains and the springs of the lifts will also be inspected and the lift chains shall be greased.

2.3.3 OPTION BID 016 Shop Door Sweep

Remove and replace existing the door sweep on the Chino Shop Building with a commercial grade sweep.

The sweep shall be approved by the COR.

2.4 SCOPE ATTACHMENTS

Attachment A – Project Vicinity Map (1 page) Attachment B – Specifications (64 pages) Attachment C – Submittal List (6 pages) Attachment D – Site Pictures (11 pages) Attachment E– PNF Fire Plan (5 pages) Attachment F – PNF Spill Prevention Plan (3 pages) Attachment G – EPA Compliance Advisory (1 page)

ATTACHMENT A

Vicinity Map

Building Locations within the Chino Admin. Site

2 | Page

ATTACHMENT B

Specifications

SOUTHWEST REGION 03

PRESCOTT NATIONAL FOREST

CHINO EMERGENCY REPAIRS

SPECIFICATIONS

U.S. FOREST SERVICE

September 2026

TABLE OF CONTENTS

DIVISION 1 – GENERAL2
010001 – ABBREVIATIONS3
010002 – DEFINITIONS6
010003 – MEASUREMENT AND PAYMENT10
013300 – SUBMITTALS12
014000 – QUALITY CONTROL AND QUANTITY MEASUREMENT13
016100 – MOBILIZATION17
018113.36 – SUSTAINABLE DESIGN REQUIREMENTS GREEN BUILDING STANDARD19
DIVISION 02– EXISTING CONDITIONS22
028200 – ASBESTOS ABATEMENT22
DIVISION 6 – WOOD24
060001 - WOOD SIDING24
061000 – CARPENTRY26
DIVISION 07– THERMAL AND MOISTURE PROTECTION28
070150.19 – PREPARATION FOR RE-ROOFING28
071326 – SELF-ADHERING SHEET WATERPROOFING31
074113 - METAL ROOF PANELS34
061600 - SHEATHING36
075216 - STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED BITUMINOUS MEMBRANE ROOFING39
076200 - SHEET METAL FLASHING AND TRIM42
077123 – GUTTERS AND DOWNSPOUTS44
077200 – ROOF ACCESSORIES46
079200 - JOINT SEALANTS48
079230 – BACKER RODS50
DIVISION 08 – OPENINGS51
081416 – FLUSH WOOD DOORS51
087100 – DOOR HARDWARE53
DIVISION 9 – FINISHES55
092300 - GYPSUM PLASTERING55
092900 - GYPSUM BOARD58
095113 - ACOUSTICAL PANEL CEILINGS60
099100 – PAINTING62

DIVISION 1 – GENERAL

010001 – ABBREVIATIONS

Organizations & Standards Whenever in these specifications, or in other contract documents, the following terms, or pronouns in place of them, are used, the intent and meaning shall be interpreted as follows. Reference to a specific standard of specification shall mean the latest edition or amendment in effect on date of invitation to bid.

AASHTO--American Association of State Highway and Transportation Officials
ACI--American Concrete Institute
AISC--American Institute of Steel Construction
AISI--American Iron and Steel Institute
AITC--American Institute of Timber Construction
ANSI--American National Standards Institute
APA--American Plywood Association
API--American Petroleum Institute
ASME--American Society of Mechanical Engineers
ASTM--American Society for Testing and Material
ATCC--American Type Culture Collection
AWPA--American Wood Preservers Association
AWPB--American Wood Preservers Bureau
AWS--American Welding Society
AWWA--American Water Works Association
CFR--Code of Federal Regulations
CRSI--Concrete Reinforcing Steel Institute
CS--Commercial Standard issued by U.S. Department of Commerce
DEMA--Diesel Engine Manufacturers Association
FAR--Federal Acquisition Regulation
FED SPEC. or FS-- Federal Specifications
FSS--Federal Specifications and Standards
GSA--General Services Administration
MIL--Military Specifications
MSHA--Mine Safety and Health Administration
MUTCD--Manual on Uniform Traffic Control Devices
NBFU--National Board of Fire Underwriters
NBS--National Bureau of Standards
NEMA--National Electrical Manufacturers Association
NESC--National Electrical Safety Code
NFPA--(Fire)--National Fire Protection Association
NFPA--(Forest)--National Forest Products Association
NWMA--National Woodwork Manufacturers Association
OSHA--Occupational Safety and Health Administration
PCA--Portland Cement Association
PCI--Prestressed Concrete Institute
PS--Product Standard issued by the U.S. Department of Commerce
PTI--Post-Tensioning Institute
RIS-Redwood Inspection Service
SAE--Society of Automotive Engineers
SF--Standard Form
SSPC--Steel Structures Painting Council
UL--Underwriter's Laboratories, Inc.
USASI--United States of America Standards Institute
WCLIB--West Coast Lumber Inspection Bureau
WWPA--Western Wood Products Association

Pay Units

CSF
100 Square Feet
LF
Linear Feet
EA
Each
LS
Lump Sum
GA
Gallon
SF
Square Feet
HR
Hour
SQ
Squares

ABBREVIATIONS

AluminumAL.
AsphaltASP.
Barbed WireB.W.
Bituminous Coated Corrugated Steel PipeB.C.C.S.P. OR B.C.C.S. PIPE
Bituminous Surface TreatmentBST
CementCEMT.
Cement TreatedCEMT.-T.
Cement Treated BaseCTB
Clearing & GrubbingCLEAR & GRUB
CompactionCMPCT.
ConcreteCONC.
Corrugated Metal PipeCMP
Corrugated Steel PipeC.S.P.
Corrugated Steel Pipe ArchC.S.P. ARCH
Cubic YardC.Y.
Cubic Yard MileC.Y.MI.
DiameterDIA.
EachEA.
EmulsifiedEMLSFD.
Erosion and Pollution ControlE&P CONTROL
FabricatedFABR.
Finish Floor ElevationF.F.E.
FoundationFOUND.
FurnishedFURN.
GallonGAL.
GradeGR.
HeightHT.
High StrengthH. STRENGTH
HorizontalHOR.
HourHR.
Linear FootL.F.
LiquidLIQ.
LoadingLD.
Lump SumL.S.
MaterialMAT'L
MaximumMAX.
MethodM.
MileMI.
MinimumMIN.
One Thousand Feet Board MeasureMFBM
One Thousand GallonsM.GALS.
One Thousand Gallons MileM.GALS.MI.
One Thousand Square FeetM.S.F.
PolyvinylchloridePVC
PoundsLBS.
ReflectorizedREFLECT.
SectionSEC.
Square FootS.F.
Square YardS.Y.
StationSTA.
Station YardSTA. YD.
StrandS.
StructuralSTRUCT.
Structural SteelS. STEEL
StumpSTMP
Target ValueTV
ThicknessTH.
Ton MileT.M.
Tops and LimbsT&L
Utilization of TimberUOT
VerticalVERT.
Welded Wire FabricW.W.F.
WhiteWH.
WidthW.
WithW/
WithoutW/O
Woven wireW.W.
YellowYE.

END OF SPECIFICATION 01101

010002 – DEFINITIONS

Wherever in these specifications, or in other contract documents, the following terms, or pronouns in place of them, are used, the intent and meaning shall be interpreted as follows:

· Adjustment in Contract Price - "Adjustment in contract price" shall mean "equitable adjustment" as used in the Federal Acquisition Regulations.

· Arch Pipe - A culvert section, usually formed of bolted structural plates, that is an arc of a circle (usually one-half or less); that is, a bottomless culvert.

· Base Course - The layer or layers of specified or selected material of designed thickness placed on a subbase or subgrade to support a surface course.

· Bearings - The portion of a beam, girder, or truss that transmits the bridge superstructure load to the substructure.

· Berm - Curb or dike constructed to control runoff water or traffic flow.

· Change - "Change" means "Change Order" as used in the Federal Acquisition Regulations.

· Clearing Limits - The limits of clearing as designated on the ground or on the drawings.

· Conduit - A natural or artificial channel for carrying fluids, as water pipes, canals, and aqueducts.

· Construction Slash - All vegetative material not meeting utilization standards, such as tops and limbs, timber, brush, and grubbed stumps associated with construction or reconstruction of a facility.

· Contracting Officer (CO) - The person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings.

· Contractor - The individual, partnership, joint venture, or corporation undertaking the execution of the work under the terms of the contract and acting directly or through their agent, employees, or subcontractors.

· Controlled Felling - Directing the placement of trees in felling by wedges, jacks, cable tension, or distribution of holding wood or any combinations of these which will ensure that trees are dropped into previously cleared areas, or clear of any objects that are to remain.

· Culvert - A conduit or passageway under a road, trail, or other obstruction. A culvert differs from a bridge in that it is usually constructed entirely below the elevation of the traveled way.

· Cushion Material - Native or imported material generally placed over rocky sections of unsurfaced roads to provide a usable and maintainable traveled way.

· Defect - A failure to meet a requirement with respect to a single quality characteristic.

· Drawings - The documents, including plan and profile sheets, cross sections, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials showing details for construction of a facility.

· Embankment - A structure of soil, aggregate, or rock material placed on the prepared ground surface and constructed to subgrade.

· Engineer - The Contracting Officer's Representative (COR) responsible for onsite administration of the contract.

· Equipment - All machinery and equipment, together with the necessary supplies for upkeep and maintenance, as well as tools and apparatus necessary for the proper construction and acceptable completion of the work.

· Excess Excavation - Material from the excavation in excess of that needed for construction of designed roadways and facilities.

· Forest Service - The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

· Gauge - The term "gauge" when used in connection with the measurement of plates will mean the U.S. Standard Gauge, except when reference is made to the measurement of metal sheets used in the manufacture of corrugated metal, pipe, metal plate culverts and arches, and metal cribbing, then the term means the "gauge" or "thickness" specified in AASHTO M 36, M 167, M 196, and M 219, as applicable. When the term "gauge" refers to the measurement of wire, it will mean the wire gauge specified in AASHTO M 32.

· Government Land - National Forest System lands, and other lands controlled or administered by the Forest Service or by other Federal agencies.

· Inspector - The Government-authorized representative designated in writing by the CO or COR responsible for detailed inspection.

· Job-Mix Formula - The percentage of each material in a mixture intended for a particular use.

· Laboratory - A testing laboratory of the Government or any other testing laboratory approved by the Contracting Officer.

· Materials - Any substance specified for use in the construction of the project and its appurtenances.

· Maximum Density - The highest density that can be obtained under stated conditions.

· Measurement - Determining and expressing the quantities of work or materials.

· Multi-Beam Girder - A precast, prestressed concrete member where the concrete deck is precast as an integral part of the member.

· Neat Line - A line defining the proposed or specified limits of an excavation or structure.

· Nominal Dimensions or Weights - The numerical values shown on the drawings or in the specifications as measurements of material to be used in the construction.

· Nominal Maximum Particle Size - The largest sieve size listed in the applicable specification upon which any material is permitted to be retained.

· Overbreak - Material beyond the neat line of an excavation that is removed in the process of excavation, usually by blasting.

· Pavement Structure Subbase - base, or surface course, or combination thereof, placed on a subgrade to support the traffic load and distribute it to the roadbed.

· Pipe - A culvert that is circular (round) in cross-section.

· Pipe-Arch - A pipe that has been factory-deformed from a circular shape such that the width (or span) is larger than the vertical dimension (or rise).

· Profile Grade - The trace of a vertical plane, as shown on the drawings, intersecting the top surface at the centerline of the proposed facility construction.

· Random Sampling - Sampling at times or locations determined in advance by the use of a table of random numbers.

· Reasonably Close - Conformity Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.

· Roadway - The portion of the road within the limits of excavation and embankment, including slope rounding.

· Schedule of Items - A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, methods of measurement, unit price, and amount.

· Second Samples - A sample taken when the initial sample indicates that the material is defective.

· Sidewalk - The portion of the roadway constructed primarily for pedestrian use.

· Specifications - A description of the technical requirements for a material, product, or service that includes criteria for determination whether these requirements are met.

· Standard Specifications - Specifications approved for general application and repetitive use.

· Subbase - The layers of specified or selected material of designed thickness placed on a subgrade to support a base course.

· Subgrade - The layers of roadbed that bring it up to the top surface, upon which subbase, base, or surface course is constructed. For roads without base course or surface course, that portion of roadbed prepared as the finished wearing surface.

· Tackifier - Binder for vegetative mulch.

· Target Value - The percentage of each material in a mixture intended for a particular use from which allowable variations are measured.

· Unit of Measurement - The unit and fractions of units shown in the Schedule of Items.

· Unsuitable Material - The material excavated during roadway construction that is not usable in embankment and must be disposed of or that can be used only in certain locations or for limited purposes.

END OF SPECIFICATION 01102

010003 – MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 – Requirements Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered incidental to and included in the payment of the pay items in the SCHEDULE OF ITEMS.

1.2 – Method of Measure One of the following methods of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item.

A. Actual Quantities (AQ): The quantity to be paid is the quantity listed in the bid schedule. The contract quantity will be adjusted for authorized changes that affect the quantity or for errors made in computing this quantity. If there is evidence that a quantity specified as a contract quantity is incorrect, submit calculations, drawings, or other evidence indicating why the quantity is in error and request in writing that the quantity be adjusted.

Final payment will be made for the actual quantities at the unit price shown in the SCHEDULE OF ITEMS, subject to the Variation in Quantities Provision.

B. Lump Sum Quantities (LSQ): These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They will not be measured.

C. Estimated Quantity (EQ): If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment to extend the completion date as, in the judgement of the Contracting Officer, is justified.

1.3 – Pay Units:

One of the following methods of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item.

A. Lump Sum (LS): This pay unit denotes complete unit of work as required by or described in the contract, including all necessary materials, equipment, and labor to complete the job. They will not be measured.

B. Linear Feet (LF):Is a standard unit of measurement representing exactly 12 inches in a straight line.

C. Centum Square Feet (CSF): Is a standard unit of measurement equal to 100 square feet.

D. Each (EA): These quantities denote one complete unit of work as required by or described in the contract, including all necessary materials, equipment, and labor to complete the job. They will not be measured.

Payment will be by units defined and determined according to U.S. Standard measure.

PART 2 – PRODUCT

None

PART 3 – EXECUTION

None

PART 4 - MEASUREMENT AND PAYMENT

4.1 - Measurement There will be no separate measurement for this section.

4.2 - Payment This work is incidental to other items in the contract and direct separate item payment will not be made.

END OF SPECIFICATION 01103

013300 – SUBMITTALS

PART 1 - GENERAL

1.1 - Requirements It will be the Contractor's responsibility to submit all items with such promptness as to cause no delay in the work. Approvals must be obtained before starting work which involves the item. Contractor shall allow ten days for processing of submittals by the Government.

Submittals may also be referred to as shop drawings.

1.2 - Manufacturer's Literature and Shop Drawings Submit one (1) electronic copy to the COR for approval on the items required herein.

Submittal specifications are to be submitted in the following format:

A. The specifications and salient qualities of the item specified in the contract.

B. The specifications and salient qualities of the submittal item.

C. A listing of the differences and a comparison between the two, including but not limited to the structural qualities, operational qualities, any modifications necessary to accomplish installation of unit, and guarantee and warranty.

D. A cost comparison between the specified and submitted item(s) with the cost reduction benefit to the government or adequate justification for a cost increase to the government.

E. Shop drawings of submitted item(s) including wiring or layout diagrams.

If there are any modifications necessary to facilitate installation, a set of drawings showing installation of specified item and a set showing how the submittal item will be installed.

Submittals will be waived if contractor furnishes exact item used for design when manufacturer's model, size, etc. are shown in the contract.

Submittals are required per the following sections:

1. 014000 – QUALITY CONTROL AND QUANTIY MEASUREMENT

Contractor's Representative Quality Control Plan Construction Schedual As Built Drawings Certificates of Compliance Quantity Measurements Warranties and Owner’s Manuals

014000 – QUALITY CONTROL AND QUANTITY MEASUREMENT

PART 1 – GENERAL

1.1 - Description This work shall consist of providing quality control in conformance with the Inspection of Construction provisions of this contract to ensure compliance with the drawings, specifications, and provisions of the contract, and measuring the quantities of completed work in conformance with the provisions of the applicable specification. The contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of this specification.

1.2 - Related Work Specified Elsewhere General Provisions FAR 52.236-5, Material and Workmanship General Provisions FAR 52.236-6, Superintendence by the Contractor General Provisions FAR 52.246-12, Inspection of Construction

1.3 – Submittals Submittals under this section shall be furnished to the COR. Submittals include, but are not limited to the following:

Contractor's Representative Quality Control Plan Construction Schedual As Built Drawings Certificates of Compliance Quantity Measurements Warranties and Owner’s Manuals Test Results

PART 2 – PRODUCTS

NONE

PART 3 – EXECUTION

3.1 – Contractor's Representative Submit a letter to the Contracting Officer stating the name of the on-the-job superintendent or representative for the Contractor and the duties and authorities of the representative during work under this contract.

3.2 – Quality Control Plan The Quality Control Plan shall consist of the following:

A. Authorities and responsibilities of inspection and testing personnel.

B. Experience and qualifications of inspection and testing personnel to be assigned and name and location of any (for hire) testing facility to be used.

The contractor's proposed quality control plan for all items requiring quality control shall be submitted to the COR for review prior to the contractor commencing work. Within 10 days of receipt of the plan, the COR shall notify the contractor whether the plan adequately covers quality control requirements. Construction work shall not be performed prior to contractor's receipt of written approval of the proposed plan. The contractor shall submit to the COR, in writing, any proposed changes in the approved quality control plan. Proposed changes shall not be put into effect until approved in writing by the COR.

All work shall comply with local applicable codes and codes referenced in individual sections of the technical specifications.

3.3 – Construction Schedule Submit a detailed schedule that includes, but is not limited to:

· A detailed breakdown of all project tasks, phases, and sub-phases

· Key milestones, including Notice to Proceed, substantial completion, and owner-defined check-points

· Identification of labor, equipment, and material procurement, including submittal approval, fabrication, and delivery times

· Buffer/Float: Inclusion of reasonable buffers for weather, inspections, or unforeseen conditions

3.4 – As Built Drawings The contractor shall maintain a set of the contract drawings depicting as-built conditions. These drawings shall be maintained in a current condition and shall be available for review. All variations from contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as built drawings shall be submitted to the COR.

3.5 – Certificates of Compliance The contractor shall provide and maintain appropriate measuring and testing devices, equipment, and supplies to accomplish the required measurement, testing, and inspection in a timely manner. Tests, measurements, and certifications shall be made as required by the drawings and specifications. The contractor shall take samples and perform inspections and tests necessary to achieve the quality of construction required by the contract and make required measurements of work under this contract performed onsite or offsite. Sampling and testing frequency for specific items shall be specified in the related section.

The contractor shall maintain current records of all inspections and tests performed. The following information will be acceptable to the Government:

PROJECT NAME:_____________________CONTRACT No.____________ Pay Item No. TestDate Location Standard Result Test By(Initials) The contractor shall engage inspection and testing agencies which are prequalified as complying with the recommendations of "Independent Laboratory Qualification" by the American Council of Independent Laboratories, and which specialize in the types of inspections and tests to be preformed.

The contractor shall protect construction exposed by or for quality control service activities and protect repaired construction. Upon completion of inspection and testing repair damaged construction and restore substrates and finishes to eliminate deficiencies. The contractor is responsible for repair and protection of inspected work, whether inspection is performed by the contractor or by the Government.

The contractor shall certify in writing that all inspections and tests were performed in accordance with specifications.

3.6 – Quantity Measurements The contractor shall make all measurements for computation of quantities for all work items. The contractor shall compute the quantities for periodic progress payments; the COR will compute the quantities for the final payment based on measurements taken by the contractor. All contractor measurements are subject to verification. The contractor shall submit all field notes, calculation sheets, and other data used to determine quantities. The contractor shall certify in writing as to the accuracy of the measurements and computations submitted.

The following format or one containing the following information will be acceptable to the Government:

PROJECT NAME:CONTRACT No.
Quantity or Pay Item No.DateMeasurementTest By(Initials)

3.7 – Warranties and Owner’s Manuales Upon completion of the project, the contractor will submitt to the COR, all manufactures warranties and the owner’s manuals for all products.

3.8 Test Results

Upon the completion of bid item 009 Load Testing, the contractor shall provide an electronic copy of the Engineering Report conducted by the structural engineer. This report shall contain but is not limited to the following:

A. Project name B. Contract number C. Date load test was conducted D. Engineer conducting the analysis E. Analysis preformed F. Implementation of the analysis G. Summary of Engineer’s results H. Calculations I. Conculsion J. Engineer’s stamp and signature

PART 4 - MEASUREMENT AND PAYMENT

4.1 - Measurement There will be no separate measurement for this section.

4.2 - Payment This work is incidental to other items in the contract and direct separate item payment will not be made.

END OF SPECIFICATION 01410

016100 – MOBILIZATION

PART 1 - GENERAL

A.1 – Description This work shall consist of preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.

PART 2 – PRODUCTS

NONE

PART 3 - EXECUTION

NONE

PART 4 – MEASUREMENT AND PAYMENT

4.1 - Measurement Progress payments will be made as follows:

The Contractor can request payment for performance and payment bonds. The amount of the premium, including coinsurance and reinsurance agreements, will be paid upon reciept of evidence of full payment to the surety. When separate payment for bonding cost is made, the bonding cost will be subtracted from the total contract amount for this pay item and the balance paid in accordance with the progress payment schedule outlined below.

A. When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent of the original contract amount, whichever is less, will be paid.

B. 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less, will be paid.

C. Upon completion of all work on the project, any unpaid amount for mobilization will be paid.

Any bonding costs in excess of the total contract amount of this pay item will be paid under one or more other pay items under this contract as determined by the Contracting Officer. In no circumstance will the total amount of this contract be increased as a result of bonding costs exceeding the total contract amount of this pay item.

The total of all payments shall not exceed the original contract amount for this item.

4.2 - Payment Payment will be made under:

PAY ITEMDESCRIPTIONPAY UNIT
001Mobilization (Including Bonding Cost)L.S.

END OF SPECIFICATION 01601

018113.36 – SUSTAINABLE DESIGN REQUIREMENTS GREEN BUILDING STANDARD

PART 1 – GENERAL

1.1 – Section Requirements A. Definitions:

1. Regional Materials: Materials that have been extracted, harvested, or recovered, as well as manufactured, within 500 miles (800 km) of Project site. If only a fraction of a product or material is extracted, harvested, or recovered and manufactured locally, then only that percentage (by weight) shall contribute to the regional value.

2. Recycled Content: The recycled content shall be determined by weight.

a. "Postconsumer" material is defined as waste material that is generated by end users of the product and that can no longer be used for its intended purpose.

b. "Preconsumer" material is defined as material diverted from the waste stream during the manufacturing process. Excluded is reutilization of materials such as scrap generated in a process that is reclaimed in the same process that generated it.

B. Submittals:

1. None

PART 2 – PRODUCTS

2.1 – Materials A. Provide products and procedures necessary to meet requirements of this Section. Although other Sections may specify similar requirements, the Contractor shall determine additional materials and procedures necessary to comply with this Section.

B. Recycled Content of Materials: Building materials shall have recycled content such that postconsumer recycled content plus one-half of preconsumer recycled content constitute a minimum of 10 percent of cost of materials used for Project.

C. Do not include mechanical and electrical components in the calculation.

D. Regional Materials: Not less than 10 percent of building materials (by cost) shall be regional materials.

1. Certified Wood:

a. Wood or wood-based products shall be certified to the requirements of one of the following:

b. American Forest Foundation's "American Tree Farm System Standards."

c. CSA Z809, "Sustainable Forest Management."

d. FSC STD-01-001, "FSC Principles and Criteria for Forest Stewardship," and FSC STD-40-004, "FSC Standard for Chain of Custody Certification."

e. Sustainable Forestry Initiative's "Sustainable Forestry Initiative Standard."

f. Other product programs recognized by Program for…

This is the start of the file's text. The full file is on GovTribe.