C04_Attachment 1 - SOW 1232SA26Q0642.pdf
PDF 1 MB Posted
- Attached to
- Replacement of Cooling Tower Base Federal contract opportunity
- Solicitation number
- 1232SA26Q0642
About this file
This is a Scope of Work for the U.S. Department of Agriculture's Agricultural Research Service (ARS) regarding the replacement of a cooling tower structural steel base at the U.S. Horticultural Research Laboratory in Fort Pierce, Florida.
The contractor shall provide a complete turnkey project including all labor, materials, equipment, supervision, permitting, disposal, testing, startup, warranty, and documentation necessary to remove and replace the deteriorated cooling tower structural steel frame. The work comprises four primary tasks: (1) pre-construction activities including site walkthrough, OSHA 29 CFR 1910 safety plan preparation, and submittal of project schedule and disposal plan; (2) removal of the existing corroded base with lockout/tagout procedures and proper material disposal; (3) installation of new ASTM A36 structural steel framing, columns, beams, and connections with corrosion-resistant coatings and verification of alignment and load-bearing performance; and (4) testing and commissioning including structural inspections, operational testing, and submission of commissioning reports with as-built documentation. The contractor must provide a project manager responsible for resource management, deliverables, scheduling, and communication with the government's Contracting Officer Representative. Work shall be performed during regular weekday daylight hours (7:00 AM to 4:00 PM, excluding holidays) at the controlled-access federal facility. Key deliverables include project schedule (15 days after award), safety plan (prior to mobilization), submittals (prior to procurement), removal completion notice (after demolition), steel frame inspection report (post-installation), commissioning report (at project completion), as-built drawings (final acceptance), and warranty documents (prior to final invoice). The contractor shall provide a one-year warranty from final acceptance per FAR 52.246-1. All travel expenses must be identified as line items in the service proposal prior to contract award. Bids will be evaluated on best overall value for the USDA Agricultural Research Service.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| C05_Sol_1232SA26Q0642_Amd_0001.pdf | ||
| C05_Attachment 4 - Consolidated RFI Questions and Answers 1232SA26Q0642.pdf | ||
| Site Visit Information 1232SA26Q0642.pdf | ||
| C04_Solicitation_1232SA26Q0642.pdf | ||
| C04_Attachment 2 - Specifications 1232SA26Q0642.pdf | ||
| C04_Attachment 3 - Wage Determination FL20260228.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
SCOPE OF WORK
Replacement Cooling Tower Base
ARS/U.S. Horticultural Research Laboratory
2001 S. Rock Road
Fort Pierce, FL 34945
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished
5.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights
10.0 Section 508 – Electronic and Information Technology Standards
11.0 – Attachments
Project Replacement of Cooling Tower Base for U.S. Horticultural Research Laboratory, Fort Pierce, FL
General Information
1.0 Scope of Work
The Contractor shall provide all labor, materials, equipment, supervision, permitting, disposal, testing, startup, warranty, and documentation necessary to remove and replace the cooling tower structural steel frame located at the U.S. Horticultural Research Laboratory (USHRL)
The submitted project bid shall be turnkey, and all bids will be evaluated on best-overall value for the USDA Agricultural Research Service.
2.0 Background
A cooling tower removes heat from water used in building or industrial systems through evaporation and recirculating cooled water back into chillers and condensers.
The structural steel frame supporting the cooling tower has deteriorated due to constant exposure to moisture and environmental conditions common to coastal Florida. Replacement of the corroded framing, columns, beams, and connection points is required to restore structural integrity, ensure safe operation, and extend the tower’s service life.
Contractor Requirements
3.0 Technical Requirements / Tasks
1. Pre-Construction Activities
• Conduct site walkthrough with USHRL COR.
• Prepare safety plan meeting OSHA 29 CFR 1910 requirements.
• Submit project schedule, product data, and disposal plan.
2. Removal of Existing Base
• Lockout/tagout affected equipment.
• Support cooling tower systems as needed to allow for safe frame removal.
• Dismantle and remove all deteriorated structural components.
• Dispose of materials in accordance with local, state, and federal regulations.
3. Installation of New Base – Must be ASTM A36 Structural Steel
• Furnish and install new steel framing, columns, beams, and connections.
• Apply corrosion-resistant coatings.
• Verify alignment and load-bearing performance before reattaching tower components.
4. Testing & Commissioning
• Perform structural inspections.
• Conduct operational tests of the cooling tower once reassembled.
• Submit commissioning report and as-built documentation.
Normative References:
Policies and Procedures 242.1M-ARS ARS Facilities and Design Standards
Submittals:
Safety Requirements:
1. The Contractor shall be responsible for ensuring that the requirements of Department of Labor, Occupational Safety and Health Administration (OSHA) Standard 29 CFR 1910 will be followed.
2. The Contractor shall inform the USHRL Safety Officer of the following:
a. Any injury incurred by Contractor employee or subcontractor on-site that requires more than basic first aid.
b. Any medical care received for such injury.
Order and Scheduling of Work:
Work sequencing must minimize disruption to facility operations.
Coordinate access, staging, and shutdowns with the COR.
Warranties:
1. The contractor shall provide a 1-year warranty from the date of final acceptance of work per
FAR 52.246-1.
2. All warranties shall be turned over to the USHRL Contracting Officer Representative (COR) prior to final invoicing.
4.0 Government Furnished
Service shall be performed by the Contractor during regular weekday, daylight working hours (excluding holidays) 07:00 am to 4:00 pm. During period of work, Contractor will be given site access and issued a temporary contractors key badge.
5.0 Deliverables / Schedule
Key Deliverables
Item No.
Deliverable Objective Due
1 Project Schedule Establish milestones and sequencing 15 days after contract award
2 Safety Plan Compliance with OSHA and site requirements Prior to mobilization
3 Submittals (Steel specs, coatings, etc.)
Ensure conformance with ARS standards Prior to procurement
4 Removal Completion Notice
Confirm safe removal of existing steel frame After demolition
5 Steel Frame Inspection Report
Document structural integrity Post‑installation
6 Commissioning Report Verify system operational performance At project completion
7 As‑Built Drawings Accurate final documentation Final acceptance 8 Warranty Documents Meet FAR 52.246‑1 requirements Prior to final invoice in IPP
6.0 Travel
Any travel expenses incurred by Contractor must be a line-item in the service proposal prior to contract award.
7.0 Contractor’s Key Personnel
Contractor shall supply a project manager responsible for managing resources, deliverables, staying on schedule, and communicating with USHRL POC’s.
8.0 Security Requirements
The U.S. Horticultural Research laboratory is a controlled-access federal facility with restricted entry.
Contractor shall abide by all security measures. Contractor shall return any key badges assigned to them upon completion of work.
9.0 Data Rights
No data rights assigned to this contract.
10.0 Section 508 – Electronic and Information Technology Standards No IT resources assigned to this contract.
11.0 – Attachments
Figure 1. North Facing View of Tower and base
Figure 2. South Facing View of Tower and base
Figure 3. East Facing View of Tower and base
Figure 4. West Facing View of Tower and base
| Project |
| Replacement of Cooling Tower Base for U.S. Horticultural Research Laboratory, Fort Pierce, FL |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Government Furnished |
| 5.0 Deliverables / Schedule |
| 6.0 Travel |
| 7.0 Contractor’s Key Personnel |
| 8.0 Security Requirements |
| 9.0 Data Rights |
| 10.0 Section 508 – Electronic and Information Technology Standards |
| 11.0 – Attachments |
File details come from the government source that posted it. Updated .