This is a submittal requirements list for the Stanislaus National Forest Pavement Patching contract. The document specifies that all submittals must be sent to the Contracting Officer (CO) and Contracting Officer's Representative (COR) via email, with a submittal log completed within five days of the pre-work meeting. The government allows 14 days for review of all submittals, which should include relevant contract references, shop drawings, and applicable material or manufacturer's data, with additional requirements referenced in contract plans and specifications (FP-24 and FSSS).

The submittal list contains 19 items organized by category: administrative documents (bonding, submittal log, contractor representatives and emergency contacts); planning documents (schedule, safety plan, traffic control plan, dust control plan, spill prevention and containment plan, hazardous response plan, fire safety plan); technical submissions (construction surveying and staking, quality control plan, contractor sampling and testing); and material-related submittals (water drafting plan, aggregate, asphalt concrete). Additional requirements include equipment inspection prior to equipment arriving on USFS lands, material weigh tickets due within 24 hours of delivery, and quality control and testing data submitted periodically as available. The water drafting plan requires inspection of the drafting screen prior to use, and schedule updates must be submitted as needed or upon CO/COR request.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Stanislaus National Forest Pavement Patching

Submittal List

Submittals shall be submitted to CO and COR via email. A submittal log shall be completed with submission dates to the CO and COR within 5 days of the pre-work meeting. Please allow 14 days for review of submittals. Include relevant contract references, shop drawings and any applicable material or manufacturer’s data. Refer to contract plans and specifications (FP-24 & FSSS) for any additional submittal requirements.

1. Bonding

2. Contractor’s Submittal Log

3. Contractor's Representatives & Emergency Contacts

4. Schedule

a. Periodic schedule updates shall be submitted as needed or when requested by

CO/COR

5. Safety Plan

6. Traffic Control Plan

7. Dust Control Plan

8. Spill Prevention and Containment and Counter Measures (SPCC) Plan

9. Hazardous Response Plan

10. Fire Safety Plan

11. Construction Surveying and Staking

12. Quality Control Plan

13. Contractor Sampling and Testing

14. Water Drafting Plan

a. Requires inspection of drafting screen prior to drafting

15. Aggregate

16. Asphalt concrete

17. Equipment Inspection

a. Required prior to equipment being brought onto USFS lands

18. Material Weigh Tickets

a. Submit within 24 hours of material being delivered to site

19. QC and Other Testing Data

a. Periodic submission as testing data is available