C04 - 3 - Schedule of Items.docx

DOCX document 31 KB Posted

Attached to
USFS - Dillon Fire BAER and Suppression Road Repair
Solicitation number
127EAW26Q0043
Issued by

About this file

This is a Schedule of Items document for the Dillon Fire BAER and Suppression Road Repair solicitation issued by the U.S. Forest Service at Six Rivers National Forest in California. The file appears to be a pricing or line-item template used to organize the scope of work and associated costs for this road repair project. As a component of RFQ solicitation 127EAW26Q0043, this schedule would detail the specific work items, quantities, and unit prices required for contractors to complete fire suppression road repairs and Burned Area Emergency Response (BAER) work at the designated national forest location.

This total small business set-aside procurement falls under NAICS code 237310 (Highway, Street, and Bridge Construction) with a small business size standard of $45 million. Contractors responding to this combined synopsis/solicitation must provide quotations based on the itemized schedule provided in this document. The schedule serves as the baseline for pricing evaluation and would be referenced throughout the quotation process to ensure all required work items are addressed and priced appropriately by small business contractors competing for this Forest Service award.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Dillon Fire Baer and Suppression Road Repair Solicitation 127EAW26Q0043 Six Rivers National Forest

ATTACHMENT 3.

SCHEDULE OF ITEMS

BAER Base: All

Item No.
Description
Pay Unit
Est. QTY.
Unit Price
Total Price
15101
Mobilization
LS
1
$
$
Total Mobilization
$

BAER Base: 13N13

Item No.
Description
Pay Unit
Est. QTY.
Unit Price
Total Price
60701
R1a - Clean Culvert
EA
1
$
$
Total BAER Base: 13N13
$

BAER Base: 13N19

Item No.
Description
Pay Unit
Est. QTY.
Unit Price
Total Price
20105
S12a - Repair Stump Hole
EA
1
$
$
20420
R2a - Install Rolling Dip
EA
1
$
$
60701
R1a - Clean Culvert
EA
1
$
$
Total BAER Base: 13N19
$

BAER Base: 13N35

Item No.
Description
Pay Unit
Est. QTY.
Unit Price
Total Price
20105
S12a - Repair Stump Hole
EA
2
$
$
20420
R2a - Install Rolling Dip
EA
1
$
$
20420
R5 - Install Critical Dip
EA
1
$
$
30304
R14b - Reconstruct Roadside Ditch
Mile
0.067
$
$
60201
R6 - Culvert Modification (Reshape Catch Basin)
EA
2
$
$
60201
R6 - Culvert Modification (Cut Outlet, Energy Dissipator)
EA
1
$
$
60701
R1a - Clean Culvert
EA
4
$
$
60702
R10 - Channel Clearing (Woody Material Removal)
EA
1
$
$
63301
S1a - Road Hazard Signs
EA
1
$
$
Total BAER Base: 13N35
$

BAER Base: 14N21

Item No.
Description
Pay Unit
Est. QTY.
Unit Price
Total Price
20105
S12a - Repair Stump Hole
EA
3
$
$
20402
S2 - Physical Closure Device (Berm)
EA
1
$
$
20420
R2a - Install Rolling Dip
EA
1
$
$
20420
R5 - Install Critical Dip
EA
2
$
$
30304
R14b - Reconstruct Roadside Ditch
Mile
0.23
$
$
60201
R6 - Culvert Modification (Flared Inlet)
EA
1
$
$
60201
R6 - Culvert Modification (Remove Damaged Inlet)
EA
1
$
$
Total BAER Base: 14N21
$

Suppression Repair Base (Table 1: Road List)

Item No.
Description
Pay Unit
Est. QTY.
Unit Price
Total Price
15101
Mobilization
LS
1
$
$
20420
Drivable Drainage Dip w/aggregate
EA
4
$
$
30101
Aggregate Base, Compaction Method A
Ton
50
$
$
30304
Road Reconditioning, Grade Road, Pull Ditch, Outslope
Mile
38.50
$
$
Total Suppression Repair Base
$

Table 1: Road List

FS Road ID
Miles
FS Road ID
Miles
13N02
4.44
13N16
2.2
13N08
3.04
13N44
4.5
13N11
3.88
13N47
1.93
13N12
5.27
14N14
3.38
13N13
1.7
14N22
1.45

Total Cost for All Items Mobilization BAER Base: 13N13, 13N19, 13N35, 14N21 Suppression Repair Base

SCHEDULE NOTES

* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS. Refer to FP-24 109.02(b) for authorizing adjustments to contract quantities.

* Payment will be made on actual work performed as described in FP-24 109.01 unless otherwise noted.

* A single award will be made under this solicitation. To be considered for award, offerors shall provide pricing for all items.

* Bid Bond/Guarantee. REQUIRED for proposals exceeding $150,000.00 IAW FAR 52.228-1 Bid Guarantee.

NOTE: Payment for bond premiums shall not be in addition to the contract price.

The contractor shall complete the table below and include the information with their quote.

Company Name:

Company Address:

UEI Number:

POC Name and Title:

Phone Number:

Email:

Tax ID:

File details come from the government source that posted it. Updated .