Business_Case_-_Sanitary_Sewer_Loomis_-_Construction_(Phase_1_and_Phase_2).xlsx

XLSX spreadsheet 1 MB Posted

Attached to
Loomis Rd Sanitary Sewer Replacement & Relocation - Phase 2 - Rebid
Solicitation number
25-002-GEN
Issued by
Kenton County, Kentucky

About this file

This is a Business Case document from the Kenton County Airport Board (KCAB) for a Sanitary Sewer Replacement and Relocation project at the Cincinnati/Northern Kentucky International Airport. The project involves replacing critical sanitary sewer infrastructure serving the cargo building and terminal zone, with Phase 1 to be completed by February 1, 2025, and Phase 2 by March 21, 2025. The project will include comprehensive replacement of aging sewer lines from 1947-1972, focusing on the outfall line connecting to the terminal pump station, with a pre-bid meeting scheduled for January 30, 2025, and bid submissions due by February 20, 2025.

The total project cost is estimated at $5,499,422, with $298,442 for design, $3,950,000 for construction/installation, $1,200,000 in contingency, and additional miscellaneous expenses. The project will be funded through CAPEX, with board approval anticipated on November 18, 2024, for Phase 1 and January 20, 2025, for Phase 2. Key risks include potential operational disruptions, environmental hazards, and regulatory non-compliance if the infrastructure is not upgraded. The project aligns with the airport's strategic objectives of operational excellence, financial sustainability, and supporting future growth, particularly for the F&F Cargo Facility and Global Logistics Park development.

View the file

Other files

File Type Posted
Loomis_Rd_Sanitary_Sewer_Replacement_&_Relocation_-_Phase_2_-_Rebid_(Addendum_#2_Revision).pdf PDF
Resident_&_Non-Resident_Bidder_Affidavits.pdf PDF
CCTV_Latest_Findings.pdf PDF
CCTV_104.04.26_to_104.04.26.01_Report.pdf PDF
33_0523-GSBE-Trenchless_Installation_of_Utilities-02.07.25.pdf PDF
CCTV_104.04.26_to_104.04.26.01_Video.mp4 MP4 file
CCTV_104.04.25_to_104.04.26_Report.pdf PDF
CCTV_104.04.25_to_104.04.26_Video.mp4 MP4 file
25-002-GEN_Loomis_Rd_CTL_Summary_of_Findings_Rev1.pdf PDF
Loomis_Rd_Sanitary_Sewer_Phase_1_Plans_-_IFC_11.11.24_-_Ref_Docs.pdf PDF
25-002-GEN_Loomis_Rd_Sani_Sewer-Ph_2_Rebid_-_Contract_&_Bonds-Exh_B.pdf PDF
Loomis_Rd_Sanitary_Sewer_Ph_2_Plans_-_Addendum_1_-_2.11.25.pdf PDF
25-002-GEN_Loomis_Rd_Sani_Sewer-Ph_2_Rebid_-_Proposal_Forms-Exh_A.pdf PDF
25-002-GEN_Loomis_Rd_Sanitary_Sewer_Ph_2_Rebid_-_Notice_to_Bidders_-_2nd_Ad.pdf PDF
6514.24_N_Cargo_Sanitary_Sewer_Service_Ph2_Revised_01.16.25_-_Probable_Cost.pdf PDF
25-002-GEN_Loomis_Rd_Sanitary_Sewer_Ph_2_Rebid_-_Notice_to_Bidders.pdf PDF
25-002-GEN_Loomis_Rd_Sanitary_Sewer_Phase_2-Rebid_-_Specs.pdf PDF
Business_Case_-_Sanitary_Sewer_Loomis_-_Construction_(Phase_1_and_Phase_2).xlsx XLSX spreadsheet
#25-000-GEN_Constr_Contractors_List_-_Bidders_List.xlsx XLSX spreadsheet
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Justification & Appropriations Sanitary Sewer Replacement and Relocation on Loomis Road - Construction (Phase 1 and Phase 2)

Current Situation/Background Information
Recent inspections have revealed critical damage and non-functionality within the sanitary sewer infrastructure serving the Cargo building in the Terminal zone of the CVG campus, which discharges into the terminal pump station at Donaldson Road and Loomis Road. This infrastructure is crucial for the proposed F&F Cargo Facility, future Global Logistics Park facilities, and several existing Terminal zone areas, including the Terminal facility, Concourse A, and Lincoln Road. The Terminal Area main trunk line, active since 1971, suffers from shifted joints, cracks, and a significant belly, posing a risk of further deterioration. The Central line, with components from 1951 and 1972, has multiple breaks and submerged portions, raising concerns about imminent failure. Additionally, the T1 line, constructed around 1947 and currently inactive, shows severe structural failure with collapsed areas and a gravel-filled manhole. The sanitary line serving the T2/Sign Shop is also partly collapsed, compounding the issues. These compromised sections threaten operational integrity and pose serious environmental hazards, such as soil contamination, necessitating urgent assessment and remediation to ensure the safety and functionality of campus facilities.
Project Definition
Project Information: Sanitary Sewer Replacement

The business objectives: Ensure the F&F Cargo Facility and associated facilities receive reliable and compliant sanitary sewer service.

Project Justification: to ensure uninterrupted operations, protect the environment, comply with regulations, and support future growth while addressing immediate sanitary needs

Project Approach
To ensure the F&F Cargo Facility receives reliable sanitary service, prioritize the replacement of the outfall line connecting to the terminal pump station. Begin with a comprehensive review of the current infrastructure to develop a phased approach if viable. Design a new outfall line that meets the capacity requirements for the entire terminal area and is strategically aligned with the future Global Logistics Park development. Additionally, ensure that the replacement plan includes connecting the partly collapsed sanitary line from the sign shop to the new outfall line of the F&F Cargo Facility. During implementation, focus on minimizing disruptions to campus operations and ensure the new line’s placement accommodates future growth. This approach will address immediate needs and support long-term infrastructure goals efficiently.
Alternatives
If immediate sanitary sewer service cannot be established for the F&F Cargo Facility due to the critical condition of the current infrastructure, consider using portable bath trailers as an interim solution. Deploy these trailers to provide temporary sanitary facilities on-site until the new sanitary sewer connections are completed. Ensure proper site preparation, including access and utilities for the trailers, and maintain them regularly to uphold hygiene standards. Communicate with stakeholders about the temporary arrangement and the expected timeline for permanent solutions, while adhering to health and safety regulations. This approach will manage sanitary needs effectively while allowing for necessary infrastructure upgrades.
Recommendation
Develop a phased replacement strategy for the sewer infrastructure. Begin with the most critical sections, such as serving the F&F Cargo Facility, the Terminal Area main trunk line and cental line, which are currently active and pose significant environmental risks. Replace these sections with modern, durable materials designed to handle current and future loads.

Phase 1 Construction - Immediate tie-in to existing sanitary system and pickup of the Sign Shop (includes some temporary solutions in order to complete this portion as quickly as possible) to be complete by February 1, 2025 Phase 2 Construction - Implementation of permanent solution to complete the sanitary system work to be complete by March 21, 2025

Cost
Design: $298,442
Construction/Installation: $3,950,000
Contingency (min 30%): $1,200,000
Force Labor: $50,000
Miscellaneous: $1,000
Total Cost: $5,499,422
Total Fast Track Request for Design + Force Labor + Miscellaneous Costs: $349,442
Total Q4 Appropriations Request for Construction (Phase 1 and Phase 2): $5,150,000
Project Funding
CAPEX
Project Schedule
October 7, 2024 - Receive bid documents from designer

October 11, 2024 - Bid documents due to Procurement Team October 17, 2024 - Out to bid November 11, 2024 - Receive Bids November 18, 2024 - Present to Board March 31, 2025 - Construction complete Revised Schedule October 7, 2024 ‐ Receive Phase 1 construction bid documents from designer October 8, 2024 - Phase 1 construction bid documents due to Procurement Team October 10, 2024 ‐ Phase 1 construction out to bid (only 2 weeks, instead of the usual 3) October 24, 2024 – Receive Phase 1 construction bids November 7, 2024 - Phase 1 construction board materials due to Shannon November 8, 2024 - Phase 1 construction board materials due to Candace November 18, 2024 ‐ Present Phase 1 construction to Board **TENTATIVE DATES FOR PHASE 2 CONSTRUCTION Board Approval** November TBD, 2024 - Receive Phase 2 construction bid documents December TBD, 2024 - Phase 2 construction bid documents due to Procurement Team December TBD, 2024 ‐ Phase 2 construction out to bid December TBD, 2024 – Receive Phase 2 construction bids January 9, 2025 - Phase 2 construction board materials due to Shannon January 10, 2025 - Phase 2 construction board materials due to Candace January 20, 2025 ‐ Present Phase 2 construction to Board Completion Dates February 1, 2025 - Phase 1 construction complete March 21, 2025 - Phase 2/Full construction complete

Known Risks & Limitations
If the inaccessible T1 portion of the sanitary sewer line serving the F&F Cargo Facility is not addressed, the building will not receive occupancy approval. This could lead to significant operational disruptions, including inadequate sanitary service and potential delays. Environmental risks may increase, with worsening soil contamination and potential regulatory violations. The remaining sewer sections could become overloaded, leading to system failures, backups, and further infrastructure deterioration. Additionally, non-compliance with environmental and building regulations could result in fines and legal issues, while neglecting the problem might damage the project's reputation and stakeholder trust, impacting future developments.
Approvals:
Candace McGraw
Dil Gruffydd
Executive Sponsor, Shannon Oldfield
Concurrence Leader, Tim Haizlip
Business Unit Leader, Bill Siemer
Sponsor/Originator, Bob Huck/Michael Miller
Visuals

Strategic Plan Fit Sustainability Fit Master Plan Fit

Board Justificaiton

Project Title (Clear Representation of the Project)
Requested Action
Bullet points, describe the current situation, problem this project aims to solve or the opportunity it aims to develop
Project Definition
Project Information: What is the current situation - what are we aiming to solve?
Business Objective: What is the desired outcome of the project?
Project Justification: why we need to implement a particular solution to the problem we have narrated above
Expected Benefits/Product Produced: the measurable improvement deriving from a result perceived as an advantage by one or more stakeholders, which contributes to the achievement of one or more organizational objectives
Fuel performance via Operational Excellence, Ensures Financial Sustainability, Grows Air Service, Leverages Ventures, Partnerships and Collaborations, Creates a customer Centric CVG Brand Experience
Bid or Proposal Details
Include posted/due dates, # of bids/proposals, proposers/bidders, engineers estimate comparisons
Recommendation
After studying the various options from the standpoint of costs, economic benefits, ease of construction, schedule impacts, as well as the all-important matter of alignment with organization objectives - recommend an option to proceed with successful completion of the project.
Cost
Design:
Construction/Installation:
Contingency(min 10%):
Recurring Costs
Total
Project Schedule
mm/dd/yyyy: Design
mm/dd/yyyy: Construction/Installation Start
mm/dd/yyyy: Construction/Installation complete.
Visuals
Copy and paste any helpful visual images in this section; check View/Page Break Preview to make sure all images are within the print area.

Strategic Plan Fit Sustainability Fit Master Plan Fit

Board Draft Motion - Service

KENTON COUNTY AIRPORT BOARD

CINCINNATI/NORTHERN KENTUCKY INTERNATIONAL AIRPORT

DRAFT MOTION

POWER MONITORING – DIAGNOSTICS AND MAINTENANCE SUPPORT
AUTOMATION & INDUSTRIAL SERVICES, INC.

November 14, 2022

I move the Kenton County Airport Board authorize its Chair, Chief Executive Officer or her designee, to enter into a 1-year contract with Automation & Industrial Services, Inc. (“AIS”) to provide Maintenance and Diagnostic support for KCAB’s Power Monitoring and Control System in an amount not to exceed $27,000.

Board Draft Motion - Product image1.png image2.png