Building 1 Structural Condition Assessment and Images for Ft. Washakie, Wyoming Demolition

Building 1 is a single story building with a partial basement and is reportedly over 100 years of age. The original structure was constructed of rock masonry walls with a timber roof. Subsequent additions appear to be constructed of timber framing with a plaster finish. A summary of our observations is as follows:

The building burned in April 2005 and has since been abandoned.
The building is currently surrounded by a chain link fence and locked gate to prevent access. All windows and doors are boarded shut to prevent entry; see photograph 1.
Reportedly, all utilities have been disconnected from the building with visual observation of disconnected electrical lines during the site visit.
Because the exterior doors and windows have been covered with sheathing, observing the building interior was not possible during the visit. However a loose board at one location did allow for photographing the interior of the building in the southwestern wing; see photograph 2.
Burned timbers associated with the roof are visible from the ground in many places around the building. It was also observed that in multiple places the roof has either fully collapsed or collapse is impending; see photograph 3.
Leaning vent pipes located on the roof also indicate roof movement as seen in photograph 4.
During the site visit it was not possible to observe the condition of the main floor that overlies the basement to assess its ability to carry foot traffic.

The objective of this condition assessment was to determine if the building appeared to be safe for entry to collect and dispose of fire damaged debris including asbestos laden materials. If it was deemed impossible, it was reported the method of wet demolition could be used to demolish the building with heavy machinery instead of by manual labor. Said method utilizes a water shower to prevent the release of dust and contaminants during the demolition process. Given the condition of the roof and uncertainties regarding the main floor and basement, it is our opinion Building 1 is not safe for entry in its current condition.

file_0.jpg file_1.wmf

Photograph 1. View of the original rock masonry structure with covered windows and doors.

file_2.jpg file_3.wmf

Photograph 2. View of the building interior with debris on the floor and note the sagging ceiling joists.

file_4.jpg file_5.wmf

Photograph 3. View of collapsed roof with adjacent damaged and deteriorated structure.

file_6.jpg file_7.wmf

Photograph 4. View of collapsed roof and leaning vent pipes.

Other files

File Type Posted
Sol_140A0422R0009_Amd_0001.pdf PDF
Structure_Demolition_Specifications.docx DOCX document
Asbestos_Analysis.pdf PDF
Combined_Synopsis_Instruction.rtf RTF text file
Construction_Clauses_-_Demolition_of_Building_WR_FINAL_.rtf RTF text file
Statement_of_Work_Building_1.docx DOCX document
TERO_NOTICE.pdf PDF
EPA_Rules_and_Regulation_for_asbestos.pdf PDF
Sol_140A0422R0009.pdf PDF
Floor_Plan.pdf PDF
Fremont_County_Wage_Determination_Building.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .