Brickyard_Road_FEMA_Drainage_Improvements_-_Cost_Estimate_-_02-11-2026.pdf
PDF 7 KB Posted
- Solicitation number
- PD 25-26.053
- Issued by
- Escambia County, Florida
About this file
This is a cost estimate document for the Brickyard Road FEMA Drainage Improvements project in Escambia County, Florida, prepared on February 11, 2026. The project involves replacing a damaged 36-inch culvert pipe beneath Brickyard Road near Barth Road that was impacted by Hurricane Sally, with work including roadway reconstruction, shoulder armoring, headwall installation, and riprap placement. The cost estimate comprises 26 pay items encompassing mobilization, erosion control, material removal and replacement, dewatering, maintenance of traffic, clearing and grubbing, earthwork operations, asphalt removal and installation, aggregate base preparation, stabilized subgrade installation, articulated concrete block construction, riprap installation, pipe installation (including jack and bore operations for a 50-inch installation), various concrete end sections and drainage inlet structures, guardrail installation with end anchorages, and removal of existing site infrastructure. The project scope involves approximately 2,200 cubic yards of unsuitable material removal, 494 cubic yards of excavation, 2,067 cubic yards of fill, 3,913 square yards of sod installation, 358 square yards of graded aggregate base, 182 square yards of articulated concrete block placement, and 134 linear feet of jack and bore pipe installation with 36-inch RCP pipe.
The probable cost estimate for the Brickyard Road FEMA Drainage Improvements project totals $1,454,800.00. Major cost drivers include the 50-inch jack and bore installation with 36-inch RCP pipe at $670,000.00 (46 percent of total), earthwork fill at $103,350.00, mobilization at $70,000.00, and removal and replacement of unsuitable materials at $82,500.00. The project is funded through the Community Development Block Grant-Disaster Recovery (CDBG-DR HS005) program as part of Hurricane Sally recovery efforts. This estimate supports the associated Request for Qualifications for Construction Engineering & Inspection services, where Escambia County anticipates CE&I service costs not to exceed 7.5 percent of the estimated construction cost, or approximately $109,110.00 for this individual project component.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pay
Item # DESCRIPTION QUANTITY UNITS UNIT PRICE EXT.
1 Mobilization 1 LS $ 70,000.00 $ 70,000.00
Erosion Control (Silt Fence Type IV, Hay Bales, Floating Turbidity Barrier, SWPPP, NPDES Permit, & Monitoring)
1 LS $ 25,000.00 $ 25,000.00
3 Remove and Replace Unsuitable Materials (Approximately 2,200 CY) 1 LS $ 82,500.00 $ 82,500.00
4 Dewatering 1 LS $ 125,000.00 $ 125,000.00
5 Maintenance of Traffic 1 LS $ 12,500.00 $ 12,500.00
Clearing and Grubbing (Including Trees UNDER 12" dia.), per County Specifications 2230
4420 SY $ 6.25 $ 27,625.00
5 Earthwork Excavation by machine 494 CY $ 25.00 $ 12,350.00
6 Earthwork Fill 2067 CY $ 50.00 $ 103,350.00
7 Earthwork Establishing Grade 4420 SY $ 5.00 $ 22,100.00
8 Centipede Sod, Staked 3913 SY $ 6.25 $ 24,456.25
9 Remove Existing Asphalt 3"-6" Thick 325 SY $ 10.00 $ 3,250.00
10 2" Type SP 12.5 Asphalt, over 1500sy 325 SY $ 18.75 $ 6,093.75
6" Graded aggregate Base "Min. LBR 100 at 100% Modified Proctor", over 1000sy
358 SY $ 62.50 $ 22,375.00
12 12" Stabilized Subgrade, over 1000sy 390 SY $ 12.50 $ 4,875.00
13 Construct Articulated Concrete Block 182 SY $ 312.50 $ 56,875.00
14 Rubble Riprap w/Filter Fabric & Bedding Stone (18" thick) 30 SY $ 250.00 $ 7,500.00
15 24" RCP Pipe 29 LF $ 200.00 $ 5,800.00
16 36" RCP Pipe 76 LF $ 343.75 $ 26,125.00
17 50" Jack & Bore + 36" RCP Pipe Installation 134 LF $ 5,000.00 $ 670,000.00
18 24" Mitered End Section (FDOT Index No 430-022) 1 EA $ 5,625.00 $ 5,625.00
19 36" U-Type Concrete Endwall (FDOT Index No 430-012) 1 EA $ 25,000.00 $ 25,000.00
20 Type "D" DBI (FDOT Index No 425-052) 1 EA $ 10,000.00 $ 10,000.00
21 Doghouse Type "D" DBI (72" Ex Pipe) >6' in depth 1 EA $ 31,250.00 $ 31,250.00
22 W Beam Guardrail with Posts per FDOT Index No 536-001 260 LF $ 62.50 $ 16,250.00
23 End Anchorage Assembly per FDOT Index No 536-001 4 EA $ 6,875.00 $ 27,500.00
24 Remove Existing Stand Pipe 1 LS $ 2,500.00 $ 2,500.00
25 Remove Existing Brick Wall 1 LS $ 25,000.00 $ 25,000.00
26 Remove Existing Storm Pipe (Over 24" Diameter) 78 LF $ 50.00 $ 3,900.00
Grand Total =
BRICKYARD ROAD FEMA - DRAINAGE IMPROVEMENTS
FEBRUARY - PROBABLE COST ESTIMATE
$1,454,800.00
]Brickyard Road - Cost Estimate - 02-11-2026 Updated 2/11/2026
File details come from the government source that posted it. Updated .